Form XIX, Bangalore Metro Railway (General) Rules, 2011: FORM XIX
Bangalore Metro Railway (General) Rules, 2011 - Form XIX
Text of form XIX
FORM XIX
FORM XIX
[See rule 27(2)(b)J
CERTIFICATE
l)?ART II-SEC. 3(i)]
Certified that it is safe to use (particulars of the equipment) at the station I on
the section of the metro railway with the following precautions.
!. ___________ _
2.___________ _
3.____ ....,... _______ etc.
Director-in-charge of Signal and Telecommunication
Note: The application should be scrutinized by the Commissioner who, if
satisfied, will communicate his sanction to the metro railway administration, in
case he is not fully satisfied, he will give his comments and recommendation
for suitable further action. · : ,,·, ·. · ··,
Appendix A
[See rule 41 (7))
CATECHISM FOR SIGNALING AND INTERLOCKING INSTALLATIONS
SIGNALING AND TRAIN CONTROL
Have the requirements and recommendations for signaling and train control
systems vide Chapter IX these rules and appendix thereto pertaining to
Signaling and Train Control systems installed on the section being complied
with?
A. SIGNAL
1. Do the signals comply with the requirements as laid down in Bangalore
Metro Railway General Rules,2011.
1,1 , I •
..
•
['11'1 II-- 3(1)]
2. Have the signal posts been placed on the left side of the track of the
approaching train to which they refer? If otherwise, for what reason?
3. Are all running signals controlling placed in such a position and at such a
height above rail level so they can be clearly seen by the drivers in
sufficient time and be readily distinguished by night or by day from
subsidiary signals?
4. In case of slotted or controlled signals, can the signals be freely returned
to danger by either of the controlling agencies?
5. Are signals not commissioned have their aspects covered and the cover
displaying two crossed white bars on a black background, the bars not
being less than 30 ems x lOcms?
B. POINTS
1. Are the locking of facing points such that the points cannot be or
become unlocked while a train is passing over them i.e electrically
controlled by track circuits or alternative devices?
2. Are detectors (internal/external) fitted to all facing points and do they
Efficiently detect with switches the signals controlling the movement of
train over them?
3. Are switches adjusted to come tight against stock rails? Does the
insertion of Smm obstruction piece between the switch and stock rails
lSOmm from the toe of the switch prevent the points being locked and
prevent the relevant signal being taken 'OFF', the giving of which is
preceded by the locking of the points?
C. STATION CONTROL ROOM
1. Are all signals, points and track circuits electrically/ electronically
repeated on the Station Control Panel/Work Station as & where
provided?
2. Is the station controller provided with necessary means of stopping the
train at his station?
3. Have instructions for working been issued to all staff and included in
Metro Railway Working Instructions and are they correct and efficient?
109
HO THE GAZETIE OF INDIA : EXTRAORDrNARY
D. TEST IN STATION CONTROL ROOM
[PART II --SIT. 3(i)]
It is essential that the interlocking of all signals with points rnu�t be so
effected as to ensure the following conditions, which may be tested from
the Station Control panel or Work station
1. Is it possible to take off conflicting signals at the same time?
2. Is it possible to take off a signal until
(a) All points on the running line including overlap are correctly set and
the point locked where required?
(b) All points, giving access to the running line frorn sidings are set
against the running line?
E. OPERATION CONTROL CENTRE
Are all signals, points and track circuits electrically/electronically repeated on
the Operation Control or Work station as and where provided?
F. CAB SIGNAL
1. Are the various modes of train control clearly distinguishable on the
Driver's Man machine Interface (MMl).
2. Under Cab Signaling System of working, is Automatic Train Protection
system able to bring the train to a stop before an obstruction?
Appendix B
[See rule 41 (7))
A. ADDITIONAL CATECHISM FOR SIGNALING AND TELECOMMUNICATION
. 1. Have the requirements and rec.ommendations for signaling and
telecommunication installation in accordance with the instructions
issued for the installation of Signaling and Telecommunication
equipment in 750V DC traction systems as adopted on the section, been
complied with?
If not, in what respect the arrangements provided fall short of them?
"'"" '" '"
['ll'T II-� 3(i))
STATEMENT OF DEVIATION - SIGNALING AND TELECOM SYSTEMS
Items Existing Prescribed Deviation/Infringe Remarks Approval/
parameters Parameters ment Sanction
(1) (2) (3) (4) (5) (6)
SIGNAL
POINTS
TRACK CIRCUITS
CABLES
ELECT SIGNALING
EQUIPMENT
BATIERIES
EARTHING
MOBILE TRAIN RADIO
COMMUNICATIONS
GENERAL SAFETY
�-
[F. No.K-14011/45/2010-Metro]
S. K. LOHIA, OSD (Urban Transport) & E. 0. Jt. Secy.
Printed by the Manager, Government of India Press, Ring Road, Mayapuri, New Delhi-110064
and Published by the Controller of Publications, Delhi-! 10054.
Ill
Previous and next
All provisions of Bangalore Metro Railway (General) Rules, 2011
Questions people ask
Is form XIX of Bangalore Metro Railway (General) Rules, 2011 still in force?
No repeal of Bangalore Metro Railway (General) Rules, 2011 is recorded.