Regulation 24, Central Electricity Authority (Grid Standards) Regulations, 2010: Maintenance schedules
Central Electricity Authority (Grid Standards) Regulations, 2010 - Regulation 24
Text of regulation 24
Maintenance schedules
24. Maintenance schedules.- (1) Entities shall identify critical equipment and
as far as possible, practice condition based maintenance for such equipment in
place of traditional time based maintenance.
(2) In case of time based maintenance, the periodicity of maintenance of lines shall
be fixed based on whether they are passing through normal area or polluted area or
coastal area and the transmission lines and sub-stations in polluted or coastal areas
shall be maintained more frequently.
(3) The maintenance of lines passing through and sub-stations located in such areas
should be completed once before onset of winter so as to minimise tripping under
Page 16 of 19
conditions of fog or due to salt deposit on insulator discs in coastal areas and once
before onset of summer.
(4) Maintenance and cleaning of various equipment fittings, accessories, primary
instruments and sensors shall be carried out when they are de-energised during the
shut-down of main equipment so as to minimise shutdown time.
(5) Where defects are observed through condition monitoring or during patrolling
and inspection, the maintenance work on various items of equipment may be
advanced depending on the condition of the equipment.
Previous and next
← Regulation 23Inspection and PatrollingRegulation 25 →Use of diagnostic techniques for condition monitoring of equipment
All provisions of Central Electricity Authority (Grid Standards) Regulations, 2010
Questions people ask
Is regulation 24 of Central Electricity Authority (Grid Standards) Regulations, 2010 still in force?
No repeal of Central Electricity Authority (Grid Standards) Regulations, 2010 is recorded.