LawGrids logoLAWGRIDS.ORG

Regulation 14, Central Electricity Authority (Grid Standards) Regulations, 2010: Restoration of grid following grid incident and grid disturbance

Central Electricity Authority (Grid Standards) Regulations, 2010 - Regulation 14

Text of regulation 14

Restoration of grid following grid incident and grid disturbance

14. Restoration of grid following grid incident and grid disturbance.- (1) The Regional Load Despatch Centre, in consultation with Regional Power Committee, shall develop procedures for enabling restoration and normalisation of the Grid for inter-State system at the earliest, following grid incident and grid disturbance of the categories specified in regulation 11. (2) The State Load Despatch Centre shall also develop procedures accordingly for restoration of intra-State system. (3) The restoration procedures shall be reviewed following any addition of generating station or transmission line or at least once in two years, and revised, if considered necessary by the Regional Load Despatch Centre and State Load Despatch Centre, as the case may be. (4) The procedures specified in sub-regulations (1), (2) and (3) shall be made available to, and be followed by all concerned Entities, Regional Load Despatch Centres and State Load Despatch Centres.

Previous and next

All provisions of Central Electricity Authority (Grid Standards) Regulations, 2010

Questions people ask

Is regulation 14 of Central Electricity Authority (Grid Standards) Regulations, 2010 still in force?

No repeal of Central Electricity Authority (Grid Standards) Regulations, 2010 is recorded.