Regulation 9, Central Electricity Authority (Grid Standards) Regulations, 2010: Automatic under frequency Relay
Central Electricity Authority (Grid Standards) Regulations, 2010 - Regulation 9
Text of regulation 9
Automatic under frequency Relay
9. Automatic under frequency Relay.- (1) All Entities shall set their under-
frequency (UF) Relays and rate of change of frequency with time Relays in their
respective systems, in accordance with the plan made by the Regional Power
Committee, to provide adequate load relief for grid security and ensure the operation
of these relays at the set frequencies.
(2) All constituents shall submit a detailed report of operation of these Relays at
different frequencies to Regional Load Despatch Centre and Regional Power
Committee on daily basis and the Regional Power Committees shall carry out
inspection of these Relays as and when required.
Page 10 of 19
Previous and next
← Regulation 8Instructions by Regional Load Despatch Centres and State Load Despatch Centres to be recordedRegulation 10 →Islanding Schemes
All provisions of Central Electricity Authority (Grid Standards) Regulations, 2010
Questions people ask
Is regulation 9 of Central Electricity Authority (Grid Standards) Regulations, 2010 still in force?
No repeal of Central Electricity Authority (Grid Standards) Regulations, 2010 is recorded.