Coordination in Operations
6. Coordination in Operations.- (1) No Entity shall introduce or take out the
element of the grid without the concurrence of the Appropriate Load Despatch
Centre except in case of imminent risk of safety of plant and personnel in which case
it must intimate Appropriate Load Despatch Centre giving reasons therefore.
(2) The Appropriate Load Despatch Centre shall inform all affected parties of the
outage.