Regulation 19, Telecommunication Mobile Number Portability Regulations, 2009.: Inspection and Auditing
Telecommunication Mobile Number Portability Regulations, 2009. - Regulation 19
Text of regulation 19
Inspection and Auditing
19. Inspection and Auditing.----- (1) The Authority may, if it considers it expedient
so to do, and to ensure compliance of the provisions of these regulations, by order, in
writing, direct any of its officers or employees or an independent agency appointed by
the Authority, to inspect any records maintained by a service provider under these
regulations or get such records audited.
(2) The Authority, if it considers it expedient so to do, may require the service provider
referred to in sub-regulation (1) to get the records maintained by such service provider
audited through an independent agency as may be specified by the Authority and submit
the report in respect of such audit to the Authority and the cost of such audit shall be
borne by the concerned service provider.
(Sudhir Gupta)
Advisor (Mobile Network)
Note: The Explanatory Memorandum explains the objects and reasons of the
Telecommunication Mobile Number Portability Regulations, 2009 (8 of 2009)
20
Explanatory Memorandum to the Telecommunication Mobile Number
Portability Regulations, 2009 (8 of 2009)
Background
1. Promotion of competition and efficiency in the telecom sector, particularly
in the area of mobile telecommunication, requires, inter alia, the facilitation of easy
movement of subscribers from one service provider to another or across mobile
technologies. Mobile Number Portability (MNP) allows the subscribers to retain
their existing mobile telephone number when they move from one Access Provider
to another irrespective of the mobile technology or from one cellular mobile
technology to another of the same Access Provider, in a licensed service area. The
facility of retention of existing mobile telephone number despite moving to a new
telecom service provider helps the subscriber maintain contact with his
friends/clientele. Introduction of MNP also helps in increasing competition
between the service providers and acts as a catalyst for the service providers to
improve their quality of service.
2. Based on the recommendations of the Authority, Government issued
guidelines for MNP service license on 1
st
August 2008. It also identified two MNP
operators for two zones in the country and issued licenses to them. It has also since
been decided that MNP shall be implemented w.e.f. 31
st
December 2009 in Metros &
category ‘A’ service areas and by 20
th
March 2010 in rest of the country.
3. Through these regulations, the Authority is laying down the basic business
process framework for implementation of MNP in the country. TRAI placed the draft
regulations on the subject on its website on 30
th
June 2009 for consultation with the
stakeholders. Comments of stakeholders on the draft regulations were solicited by
14
th
July 2009. Written comments of stakeholders were posted on TRAI’s website,
21
following which Open House Discussions were held with stakeholders in Delhi on
27
th
July 2009 and the stakeholders were requested to send further comments, if any,
by 31
st
July, 2009. After careful analysis of the views of the stakeholders expressed
both through their written comments and in the Open House, the Authority has
framed the present regulations.
4. The regulations seek to provide a framework governing all relevant aspects of
MNP by –
a. laying down clear eligibility conditions for porting of mobile telephone
numbers;
b. defining rights and obligations of various stake holders, i.e., the Donor
Operator, the Recipient Operator, the MNP Service provider;
c. laying down the procedure to be followed by each player in the chain in
processing number porting request;
d. specifying clear time limits for completion of various steps by each player
in the chain i.e. the Donor Operator, Recipient Operator and the MNP
service provider; and
e. envisaging least disruption of service to the consumer.
Salient features of the MNP under these regulations are as follows:
i MNP facility shall be available only within a given licensed service area.
ii A subscriber holding a mobile number is eligible to make a porting request
only after 90 days of the date of activation of his mobile connection. If a
number is already ported once, the number can again be ported only after
90 days from the date of the previous porting.
22
iii The Subscriber who wishes to port his mobile number should approach the
Recipient operator (the operator to whom the subscriber wants to port his
number). The Subscriber may be required to pay porting charges, if any, to
the Recipient Operator.
iv The subscriber making the porting request is required to have cleared all
the bills issued prior to the date of porting request. He shall give an
undertaking that he has already paid all billed dues to the Donor Operator
as on the date of the request for porting and that he shall pay dues to the
Donor Operator pertaining to the mobile number till its eventual porting
and that he understands and agrees that in event of non-payment of any
such dues to the Donor Operator, the ported mobile number shall be liable
to be disconnected by the Recipient Operator.
v A subscriber may withdraw his porting request within 24 hours of its
submission to the Recipient Operator. However, the porting charges shall
not be refundable.
vi The regulation envisage a maximum time period of four days for the
completion of porting process.
vii Access Providers are required to implement All Call Query method.
viii The Originating operator shall be responsible to route the call to correct
terminating network.
23
Stakeholders’ comments on key issues and its analysis
1. Definition of Donor operator and Recipient operator in the context of dual
technology provider:-
Some stakeholders suggested that the definition must clearly indicate the Donor
& the Recipient Operator would be the same in case of porting of a number from one
technology to other technology within the same service provider.
The definition clearly states that the Donor Operator is the one to whom the
subscriber belongs before porting his number. Mobile Number Portability includes
porting from one technology to another technology of the same service provider. It is
immaterial whether the Donor and the Recipient Operator are same or different as the
functions of Donor Operator and Recipient Operator are to be carried out independently.
In view of the above, it is felt not necessary to state that the Donor & Recipient Operator
will be same in case of same service provider providing Mobile Number Portability
across the technologies.
2. Levying porting charge where requests cannot be considered
Suggestions were made by some stakeholders that the porting charges should be
levied only in case of a successful porting except in a case where the subscriber himself
withdraws his porting request. There were others who felt that irrespective of whether
the porting is carried out or not, porting charge should be payable, since for every
processing of porting request, the service provider incurs certain cost.
Having considered the comments, the Authority is of the view that there is a
merit in the argument that the customer is being informed in advance about the
eligibility criteria. Examination of the request involves work on the part of the Recipient
24
Operator/MNP service provider. Besides, refund of porting charge also involves
additional expenditure for the service providers. It is therefore felt that there should be
no provision for refund of porting charges paid to the Recipient Operator.
3. Sharing of Porting charge between Donor, Recipient and MNP Service provider
Some service providers commented that as the MNPSP, the Donor/ Recipient
operators have to carry out additional work for porting the subscribers; the porting
charge should be shared among all these operators. This issue will be dealt at the time of
determining the Per-Port transaction charge, Dipping charge and Porting charge.
4. Defining Business Days and Hours
Some service providers felt that the Business Day and hours / End of Business
Day should be defined. They suggested that Business Days should be (Monday to
Saturday) and working hours should be 9 am – 6 pm while some were of the opinion
that as these terms are already defined under the Negotiable Instrument Act, there is no
necessity of defining the same in these regulations.
Defining the business hours is not feasible as the operators presently have their
own timings. Therefore, regulations have specified the timelines, wherever required, in
terms of number of hours permitted for completion of specified process. Sundays and
public holidays declared under the Negotiable Instrument Act, 1881 (No.26 of 1881)
have been excluded wherever required.
5. Eligibility condition for applying for porting
There were conflicting views on the regulation of 90 days as minimum eligibility
for porting. Some stakeholders suggested a clarification that the 90 days period should
25
be applicable for cross technology porting also. Some consumer representatives
suggested that no timeframe be defined for porting. However, most of the Service
providers were agreeable to the timeframe of 90 days.
This has been examined and Authority is of the view that a minimum period is
required to be specified so as to enable the service provider to recover the customer
acquisition cost. The Mobile Number Porting definition takes care of scenario of the
cross technology porting within same operator too.
6. Recovery of dues by the Donor Operator from the ported subscriber
In the draft Regulation on MNP, it was proposed that the subscriber shall be
eligible for porting his number only if he has paid his last bill (in case of post-paid
subscription) and provided he has given an undertaking that he shall continue to pay all
future dues to the Donor Operator till its eventual porting . The stakeholders’ comments
were that-
• it needs to be clearly prescribed in the Regulation that even after disconnection of
his mobile number; the subscriber will be liable to pay all the pending dues of the
Donor Operator.
• an extra procedure was suggested wherein the Donor Operator was to raise the
bill for the subscriber to pay before his porting requested was accepted.
• TRAI should prescribe the format of the undertaking to be furnished by MNP
customer to Recipient Operator.
The Regulations have adequate provision for recovery of these. The porting
request can be valid only if the subscriber has paid his dues as per bills issued before the
date of porting request. He will also be liable to pay all the bills issued after the porting
request, failing which the Recipient Operator is entitled to disconnect his number, after
following the due procedure. The Authority is of the opinion that any extra procedure
26
for the Donor Operator to recover his dues before porting takes place will complicate the
procedure for number portability. Porting from an Operator is similar to disconnection
for the purpose of recovery of dues. Besides, suitable provisions have been made in the
regulations for other legal remedies for recovering dues.
7. Verification of subscriber by Recipient Operator and Authentication by Donor
Operator
The draft regulation proposed that the Recipient Operator, upon receipt of the
porting request of a subscriber, within five days of receipt of the porting request, shall
carry out subscriber verification in the same manner as required for the acquisition of a
new subscriber.
Some stakeholders suggested that Subscriber verification being a security issue,
verification should be done before porting. The time period of 5 days may not be
sufficient to carry out physical verification of post-paid subscribers particularly
subscribers located in rural and remote areas and also in states like J&K and NE, and as
such no time period should be prescribed. On the other hand, those who favoured speedy
porting put forward an argument that unlike new subscriber, the porting subscriber has
already been verified by the Donor Operator and also has been on the network for a
minimum of 90 days. Therefore, it may be possible to do post verification after the
completion of porting.
In its submission, that was also placed on the TRAI website and in the
discussions, one of the stakeholders suggested that in order to ensure speedy porting and
reduce the chances of rejection by the Donor Operator because of mismatch of the
subscriber’s details, the pre-paid subscriber applying for porting of his number should be
asked by the Recipient Operator to send a SMS from his mobile handset to a designated
short code. On receipt of SMS the subscriber will get authenticated and the Donor
27
Operator will also be able to verify that the SMS has originated from a subscriber of his
network. This was not opposed by others.
The object of the Regulations is to make the MNP a simple affair. The
Authority’s concern is that the request of the subscriber should not be rejected merely on
account of change of address, difference in use of spelling in the name or address
between the data given by the subscriber at the time of porting and that available with
the Donor Operator, or non-availability of the original CAF details. In such cases, the
probability of either rejection of subscriber’s request or delay in grant of clearance by
the Donor Operator is very high. Moreover, the subscriber is only getting disconnected
from the Donor Operator. Therefore, the Donor Operator needs only to confirm that the
mobile number applying for porting belongs to its network. Additionally In order to
implement the MNP successfully, the key aspect is to make the process simple, easy and
speedy for the subscriber. The Authority in its analysis found that the suggestion given
above by one of the stakeholders with minor customization can make the porting process
simple and speedy and will also take care of unnecessary rejections by the Donor
Operator. Accordingly, the regulations have introduced a procedure wherein a unique
porting code to be generated by Donor Operator for the authentication of the subscriber
requested for porting of his mobile number. The subscriber will have to incorporate this
code in the porting form while submitting it with the customer acquisition form to the
Recipient Operator.
8. Duration of No service period
During the consultation, stakeholders were of the view that the time period of 2
hours specified for the ‘No Service Period’ is very short and that more time was required
to carry out the disconnection/activation of the subscriber number. They wanted this
time period to be increased to 4-5 hours each.
28
The Authority felt the window period of one hour each for the disconnection and
activation by the Donor operator and the Recipient operator respectively is in
accordance with the MNP Service license condition. Moreover, further increasing this
time period will cause inconvenience to the subscriber. Therefore, the ‘No Service
Period’ is proposed to be maintained as it is.
9. Reasons for rejection due to contractual obligation
Some of the stakeholders have suggested that any Contractual obligation between
the Donor Operator and the subscriber should also be included as a reason for rejection
by the Donor operator. After consideration, the Authority found merit in the argument
that the subscriber, who is under a subsisting contractual obligation having an exit clause
with the Donor operator and has not complied with the exit clause can not be allowed to
port the number. Accordingly, provisions have been incorporated in the regulations.
10. Discretion of the Donor Operator to continue ISD and International roaming
facilities of the subscriber during the process of porting
Some stakeholders were of the view that continuation of high exposure services
like ISD, International Roaming, and other Value Added facilities for subscribers
applying for porting should not be mandated. While the contrary view was that all such
services, or facilities, that the subscriber was receiving prior to his porting request, must
be allowed to be continued on the subscriber number, while under porting period.
The Authority is of the view that the service providers normally maintain a credit
limit beyond which the subscribers are not allowed to use such facilities. Secondly, in
view of the revised porting procedure, the period for the entire process has been
considerably reduced. Thirdly, subscribers having ISD/International roaming facility are
29
few in number and they may need these facilities on a day to day basis. It is therefore
felt that there is no need to make such provision available to the Donor Operator.
11. Notice Period by the Donor Operator and Recipient Operator for the defaulting
subscriber who has ported his number to the Recipient Operator
The draft Regulations provided that in case, a post-paid subscriber fails to pay the
outstanding bills to the Donor Operator by the due date as per the bill, the Donor
Operator shall issue a notice for such payment. If the subscriber still fails to pay the
dues, the Recipient Operator, on intimation by the Donor Operator was required to
disconnect the number after issuing a notice. A period of “Not less than 15 days”
and “Not less than 7 days” was prescribed to the Donor Operator and Recipient Operator
respectively.
Some of the stakeholders suggested that the notice period of 15 days was unduly
long as already sufficient time is given to the subscriber to pay his dues, while others felt
that the notice period of 7 days should be increased.
The Authority, based on the practical considerations, has decided that the notice
period for the defaulter subscriber by the Donor operator be kept as ‘Not less than 7
days’ and by the Recipient Operator as ‘Not less than 7 days, but not more than 15
days’.
12. Establishment of connectivity between the Access Providers/ILDOs and MNP
Service providers:-
The Access Providers were of the opinion that every new service provider
(Seeker) irrespective of the type of service being provided by them e.g.
30
CMTS/BSO/UASL/NLDO/ILDO has to seek interconnection from the existing
operators (Provider). The interconnect arrangement between the MNP service provider
and every Access Provider/ ILDO should be governed by present RIO provisions
notified by TRAI. They may not be forced to establish the Interconnection at their own
cost contrary to the provisions of license.
The Authority deliberated in detail on the submission of the stakeholders on this
issue. The primary purpose to introduce MNP in the country is to provide freedom to the
subscribers to change their service providers while retaining their mobile numbers. MNP
service providers have been given licenses to facilitate and help the Access Providers in
providing such a facility. Therefore, the issue of seeker/provider is not relevant in this
case. Moreover, this Regulation is in accordance with the clause 31.13 of the Licence
agreement of the MNP Service and the instructions of the Government to all the Basic
service, CMTS, UAS, NLD and ILD licensees vide Department of Telecommunication’s
letter no.20-201/2008-AS-I, dated 6
th
May, 2009. Therefore, the Authority finds no
merit in the stakeholders’ submission.
TO BE PUBLISHED IN THE GAZETTE OF INDIA, EXTRAORDINARY,
PART III, SECTION 4
TELECOMMUNICATION MOBILE NUMBER PORTABILITY
(AMENDMENT) REGULATIONS, 2010
(1 of 2010)
TELECOM REGULATORY AUTHORITY OF INDIA
NOTIFICATION
New Delhi, the 28th January, 2010
No. 116-1/2010-MN --------------- In exercise of the powers conferred by sub-section
(1) of section 36, read with sub-clauses (i), (iii) and (v) of clause (b) of sub-section (1)
of section 11 of the Telecom Regulatory Authority of India Act, 1997 (24 of 1997), the
Telecom Regulatory Authority of India hereby makes the following regulations to
amend the Telecommunication Mobile Number Portability Regulations, 2009 (8 of
2009), namely:-
1.(1) These regulations may be called the Telecommunication Mobile Number
Portability (Amendment) Regulations, 2010,
(2) In sub-regulation (2) of regulation 1 of the Telecommunication Mobile Number
Portability Regulations, 2009 (8 of 2009), for clause (b), the following clause shall be
substituted, namely:-
1
“(b) Regulations 6, 7, 8, 9,10,11,12 and 13 of these regulations shall come into force
on the 31st March, 2010”
(R. K. ARNOLD)
SECRETARY
Note1: The principal regulations were published in the Gazette of India, Extraordinary,
part III, Section 4 vide notification No. 116-4/2009-MN (Vol. II) dated 23rd Sep
2009
Note2: The Explanatory Memorandum explains the objects and reasons of the
Telecommunication Mobile Number Portability (Amendment) Regulations,
2010 (1 of 2010)
2
Explanatory Memorandum
The Telecom Regulatory Authority of India issued the Telecommunication
Mobile Number Portability Regulations, 2009 (8 of 2009) dated 23rd September, 2009
laying down the basic business process framework for implementation of mobile
number portability in the country. Regulations 6,7,8,9,10,11,12 and 13 of these
regulations were required to be implemented on 31st December, 2009.
2. Considering the present preparedness of various service providers and the
process involved, the Government has decided to extend the time for implementation of
these regulations from 31st December, 2009 to 31st March, 2010, for all circles.
3. Therefore, Clause (b) of sub-regulation (2) of regulation 1 of the
Telecommunication Mobile Number Portability Regulations, 2009 has been amended.
3
1
TO BE PUBLISHED IN THE GAZETTE OF INDIA, EXTRAORDINARY,
PART III, SECTION 4
TELECOMMUNICATION MOBILE NUMBER PORTABILITY (SECOND
AMENDMENT) REGULATIONS, 2010
(05 of 2010)
TELECOM REGULATORY AUTHORITY OF INDIA
NOTIFICATION
New Delhi, the 24
th
November, 2010
No. 116-1/2010-MN --------------- In exercise of the powers conferred by sub-section
(1) of section 36, read with sub-clauses (i), (iii) and (v) of clause (b) of sub-section (1)
of section 11 of the Telecom Regulatory Authority of India Act, 1997 (24 of 1997), the
Telecom Regulatory Authority of India hereby makes the following regulations to
amend the Telecommunication Mobile Number Portability Regulations, 2009 (8 of
2009), namely:-
1. (1) These regulations may be called the Telecommunication Mobile Number
Portability (Second Amendment) Regulations, 2010,
(2) They shall come into force from the date of their publication in the official
Gazette
(3) In sub-regulation (2) of regulation 1 of the Telecommunication Mobile Number
Portability Regulations, 2009 (8 of 2009), (hereinafter referred to as the principal
regulations) for clause (b), the following clause shall be substituted, namely:-
2
"(b) Regulations 6, 7, 8, 9, 10, 11, 12 and 13 of these regulations shall come into force
in Haryana service areas on the 25
th
November, 2010:
Provided that regulations 6, 7, 8, 9, 10, 11, 12 and 13 of these regulations shall
come into force in different service areas, as may be specified by direction issued by the
Authority, from time to time.
2. In regulation 10 of the principal regulations, for the words “twenty four hours”,
wherever appearing, the words “four working days” shall be substituted;
(Sudhir Gupta)
Principal Advisor (Mobile Network)
Note1:The principal regulations were published in the Gazette of India,
Extraordinary, part III, Section 4 vide notification No. 116-4/2009-MN
(Vol. II) dated 23
rd
Sept.2009 and amended vide:
(i) Notification no. 116-1/2010 dated 28th January,2010 (1 of 2010)
Note2: The Explanatory Memorandum explains the objects and reasons of these
regulations
3
Explanatory Memorandum
The Telecom Regulatory Authority of India issued the Telecommunication
Mobile Number Portability Regulations, 2009 (8 of 2009) dated 23
rd
September, 2009
laying down the basic business process framework for implementation of mobile
number portability in the country. Regulations 6,7,8,9,10,11,12 and 13 of these
regulations were required to be implemented on 31
st
December, 2009.
2. The Government extended the time for implementation of these regulations from
31
st
December, 2009 to 31
st
March, 2010, for all circles considering the preparedness of
operators at that time. Accordingly, TRAI issued the Telecommunications Mobile
Number Portability (Amendment) Regulations, 2010 (1 of 2010) dated 28
th
January
2010. However, due to the non-preparedness of the Telecom Service Providers, DoT
further extended the timeframe for implementation of MNP from time to time.
3. Recently Government has announced that the MNP services would start in
Haryana Licensed Service Area on 25
th
November 2010. This has necessitated amending
the regulations.
4. The modification in the timelines (from 24 hrs to 4 working days) for Donor
operator in the regulation 10 of the principal regulations has been necessitated due to the
request by DoT citing security reasons. With this amendment to the principal
Regulation, the maximum time period for porting would become seven working days
except in Jammu & Kashmir, Assam and North East licenced service areas, wherein it
would be 15 working days.
1
TO BE PUBLISHED IN THE GAZETTE OF INDIA, EXTRAORDINARY,
PART III, SECTION 4
TELECOMMUNICATION MOBILE NUMBER PORTABILITY (THIRD
AMENDMENT) REGULATIONS, 2012
(16 of 2012)
TELECOM REGULATORY AUTHORITY OF INDIA
NOTIFICATION
New Delhi, the 8
th
June, 2012
No. 116-5/2012-MN --------------- In exercise of the powers conferred by sub-section
(1) of section 36, read with sub-clauses (i), (iii) and (v) of clause (b) of sub-section (1)
of section 11 of the Telecom Regulatory Authority of India Act, 1997 (24 of 1997), the
Telecom Regulatory Authority of India hereby makes the following regulations to
further amend the Telecommunication Mobile Number Portability Regulations, 2009
(8 of 2009), namely:-
1(1) These regulations may be called the Telecommunication Mobile Number
Portability (Third Amendment) Regulations, 2012.
(2) They shall come into force from the date of their publication in the Official
Gazette.
2. In regulation 6 of the Telecommunication Mobile Number Portability
Regulations, 2009 (8 of 2009), (hereinafter referred to as the principal
regulations), the following proviso shall be inserted at the end, namely:-
2
“ Provided further that nothing contained in para (a) of the first proviso shall apply to the
subscribers of those service providers whose licences stand quashed pursuant to the
judgment and order passed by the Hon’ble Supreme Court in writ petition (civil) No.
423 of 2010 and writ petition (civil) No. 10 of 2011.”
3. In regulation 12 of the principal regulations, after clause (b), the following
proviso shall be inserted, namely:-
“Provided that nothing contained in clause (b) shall apply to the subscribers of those
service providers whose licences stand quashed pursuant to the judgment and order
passed by the Hon’ble Supreme Court in writ petition (civil) No. 423 of 2010 and writ
petition (civil) No. 10 of 2011.”
(Rajeev Agrawal)
SECRETARY
Note1: The principal regulations were published in the Gazette of India,
Extraordinary, part III, Section 4 vide notification No. 116-4/2009-MN
(Vol. II) dated 23
rd
Sept.2009 and amended vide:
(i) Notification no. 116-1/2010 dated 28th January, 2010 (1 of 2010)
(ii) Notification no. 116-1/2010 dated 24th November, 2010 (5 of 2010)
Note2: The Explanatory Memorandum explains the objects and reasons of these
regulations
3
Explanatory Memorandum
The Telecom Regulatory Authority of India issued the Telecommunication
Mobile Number Portability Regulations, 2009 (8 of 2009) dated 23rd September, 2009
laying down the basic business process framework for implementation of mobile
number portability in the country. The Regulations 6,7,8,9,10,11,12 and 13 of these
regulations came into effect in all telecom service areas in the country from 20
th
January
2011 through the Authority’s direction dated 18
th
January, 2011.
2. Hon’ble Supreme Court in its Judgment dated 2
nd
February, 2012, in the WRIT
PETITION (CIVIL) NO. 423 OF 2010 and WRIT PETITION (CIVIL) NO. 10 OF 2011
inter alia ordered that:
(i) The licences granted to the private respondents on or after 10.1.2008
pursuant to two press releases issued on 10.1.2008 and subsequent
allocation of spectrum to the licensees are declared illegal and are quashed.
(ii) The above direction shall become operative after four months.
3. Subsequently the Hon’ble Supreme Court in its order dated 24
th
April , 2012 in
connection with the application by Union of India for clarification of judgment dated
2.2.2012 and for grant of permission to conduct the auction, the Hon’ble Supreme Court
stated
“In our view, it will be just and proper to partially accept the prayer made in the
application and extend the time fixed by the Court up to the end of August, 2012.
Accordingly, the application is disposed of in the following terms:
1) The time specified in judgment dated 2.2.2012 in Writ Petition No.423 of 2010
and Writ Petition No. 10 of 2011 for conducting the auction for grant of fresh
licenses and allocation of spectrum is extended up to 31.08.2012. This would
necessarily mean that the applicant shall have to finalise the auction on or
before 31.08.2012.
2) The existing licenses shall be entitled to continue to operate till 07.09.2012.”
4. In view of the above order, and in order to facilitate the porting of the mobile
number of subscribers of the licensees whose licenses have been quashed by the
Hon’ble Supreme court w.e.f four months from the date of the order, the regulation 6
4
and 12 of the Telecommunication Mobile Number Portability Regulations, 2009 have
been amended.
--------
1
TO BE PUBLISHED IN THE GAZETTE OF INDIA, EXTRAORDINARY,
PART III, SECTION 4
TELECOM REGULATORY AUTHORITY OF INDIA
NOTIFICATION
New Delhi, the 25th February, 2015
TELECOMMUNICATION MOBILE NUMBER PORTABILITY (SIXTH
AMENDMENT) REGULATIONS, 2015
(03 of 2015)
No. 116-19/2014-NSL-II--------------- In exercise of the powers conferred by sub-
section (1) of section 36, read with sub-clauses (i), (iii) and (v) of clause (b) of sub-
section (1) of section 11, of the Telecom Regulatory Authority of India Act, 1997 (24
of 1997), the Telecom Regulatory Authority of India hereby makes the following
regulations to further amend the Telecommunication Mobile Number Portability
Regulations, 2009 (8 of 2009), namely:-
1. (1) These regulations may be called the Telecommunication Mobile Number
Portability (Sixth Amendment) Regulations, 2015 (03 of 2015)
(2) They shall come into force on the 3rd day of May, 2015
2. In regulation 2 of the Telecommunication Mobile Number Portability
Regulations, 2009 (8 of 2009) (herein after referred to as the principal regulations) --
------------
2
(a) in clause (a), after the words “ Unified Access Service licence, the words “or
Unified licence (access service) or unified licence having authorization to provide
access service” shall be inserted ;
(b) after clause (j), the following clauses shall be inserted, namely:-
“(ja) “Mobile Number Portability zone” or “MNP zone” means the zones
contained in the Annexure-VI of the licence agreement for the Mobile Number
Portability Service ;”
(jb) “mobile number range” means the number series allocated by the licensor
to an Access Provider in an MNP zone;
3. In regulation 3 of the principal regulations, sub-regulation (1) shall be deleted
4. In regulation 8 of the principal regulations, in sub-regulation (6) -----
(a) for the words “concerned Mobile Number Portability service provider”, the
words “Mobile Number Portability Service Provider of MNP zone to which the
mobile number range holder of number under porting belongs” shall be
substituted;
(b) in the first proviso, after the words “the Mobile Number Portability Service
provider”, the words “of MNP zone to which the mobile number range holder of the
number under porting belongs” shall be inserted.
5. In regulation 11 of the principal regulations, in sub-regulation (1), in the proviso to
clause (c), after the words “provided that in”, the words “case the Recipient
Operator belongs to” shall be inserted.
6. In regulation 12 of the principal regulations, the clause (f) shall be deleted.
7. In regulation 14 of the principal regulations, -----------
(a) after the sub-regulation (4), the following proviso shall be inserted, namely:-
3
“Provided that no notice shall be given after thirty days from the last date of
payment mentioned in the outstanding bill”;
(b) in sub-regulation (5), after the words “the Donor Operator shall communicate”
the words “within thirty days” shall be inserted;
(c) after sub-regulation (5), the following proviso shall be inserted, namely:-
“Provided that no communication for disconnection of ported number shall be given
to the Mobile Number Portability Service Provider after sixty days from the last date
of payment mentioned in the outstanding bill”.
8. In regulation 15 of the principal regulations, -----------
(a) in sub-regulation (3),---
(i) after the words “a notice” and before the words “ to the concerned subscriber”,
the words “ of fifteen days” shall be inserted;
(ii) the words “the period of which shall be not less than seven days and not
more than fifteen days, ” shall be deleted;
(b) for sub-regulation (4) the following sub-regulation shall be substituted,
namely:-
“(4) In case, the subscriber fails to provide evidence of having settled the
outstanding dues with the Donor Operator within the time so allowed in the
notice under sub-regulation (3), the Recipient Operator shall immediately
bar all outgoing services on the mobile number of such subscriber except
accessibility to emergency services as specified in the licence agreement of
the service provider;
Provided that if the subscriber furnishes evidence to the Recipient Operator
regarding payment made to the Donor Operator, within fifteen days from the
date of barring of outgoing services, the services of the subscriber shall be
restored with immediate effect;
4
Provided further that, in case the subscriber fails to make payment referred
to in the first proviso, the Recipient Operator shall disconnect the mobile
number of the subscriber and inform the Mobile Number Portability Service
Provider of the action taken by it with request for reversal of such number to
the Number Range Holder after expiry of sixty days.”;
(c) in sub-regulation (5), for the words “ninety days”, the words “sixty days” shall
be substituted.
(Sudhir Gupta)
Secretary
Note 1: The principal regulations were published in the Gazette of India,
Extraordinary, part III, section 4 vide notification No. 116-4/2009-MN (Vol.II) dated
23rd Sept. 2009 and amended vide:
a) Notification no. 116-1/2010 dated 28th January, 2010 ( 1 of 2010)
b) Notification no. 116-1/2010 dated 24th November, 2010 (5 of 2010)
c) Notification no. 116-5/2012 dated 8th June, 2012 (16 of 2012)
d) Notification no. 116-5/2012 dated 19th September, 2012 (19 of 2012)
e) Notification no. 116-4/2013 dated 22nd July, 2013 (9 of 2013)
Note 2: The explanatory memorandum explains the objects and reasons of these
regulations
5
Explanatory Memorandum
1. The Telecom Regulatory Authority of India issued the Telecommunication Mobile
Number Portability Regulations, 2009 (8 of 2009) dated 23rd September, 2009
laying down the basic business process framework for implementation of intra-circle
mobile number portability in the country. The regulation 6,7,8,9,10,11,12 and 13 of
the Regulations came into effect in all telecom service areas in the country from 20th
January 2011 through the Authority’s direction dated 18th January, 2011.
2. Now the Government has decided to implement inter-service area mobile number
portability (Full Mobile Number Portability). Accordingly, necessary amendments to
the MNP service license were issued by the Department of Telecommunications
(DoT) through letter No. 800-22/2013-AS-II dated 3rd November, 2014 wherein it is
stated that Full MNP would be implemented in the country within six months from
the said amendment. In this context the Authority issued a draft The
Telecommunication Mobile Number Portability (Sixth Amendment), 2015 on 23rd
January, 2015 seeking comments of stakeholders for facilitating Full MNP. In
addition, the draft amendments also proposed some changes to the existing porting
process viz. reduction in timelines for number return process, refining non-payment
disconnection issues etc.
3. In response to the draft Amendment, fifteen stakeholders submitted their comments.
These comments have been examined by the Authority and, after deliberations, this
Sixth Amendment to the MNP Regulations is being issued. The explanation for the
amendments made in the Regulations is provided in the following paragraphs.
6
Time period for implementation
4. As per the DoT’s amendment to the MNP service licence, full MNP (inter and intra
Licensed Service Area MNP) is to be implemented within six months from the date
of the said amendment to the Licenses. Accordingly, the Authority has made the
Sixth Amendment to the MNP Regulations effective from 3rd May 2015.
Forwarding of porting request by the Recipient Operator
5. On a request by a subscriber for porting of his number, the Recipient Operator (RO)
will forward the porting requests to the MNP Service provider (MNPSP) to which the
number range holder (service provider who originally allocated the mobile number)
belongs. Even if a subscriber ports his mobile number from one MNP Zone to
another, the same MNPSP will continue to handle his porting requests for all
subsequent portings. This is required as the porting history of the subscriber is
maintained by the MNPSP of the MNP zone to which his number range holder
belongs.
Time period for Donor Operator to raise non-payment disconnections:
6. The MNP Regulations provide that in case a post paid subscriber defaults in the
payment which was due to the Donor Operator (DO), the DO may request the RO
for disconnection of the ported mobile number. It is noticed that in many cases, the
DO raises disconnection requests (due to non-payment of outstanding bill) long
after the subscriber has ported his number. Therefore, there is a need to bring
order in this matter so that non-payment disconnection cases are settled in a timely
manner by the Donor as well as the RO to avoid any inconvenience to the
subscriber at a later date. Accordingly, in the Amendment, time period of ‘thirty
days’ from the due date of the outstanding bill has been specified for a DO to raise
the non-payment notice to the subscriber who has defaulted in the payment. It is
also stipulated that after completion of ‘sixty days’ from the due date of payment of
the outstanding bill, the DO will not be entitled to raise non-payment disconnection
requests to the RO through the MNP service provider.
7
Increase in Notice period for disconnection by the RO
7. In response to the draft Amendment, most stakeholders have requested for
increase in the notice period given by the RO to the subscriber who has defaulted
in the payment to the DO from the existing fifteen days period to thirty days. After
examination, the Authority has agreed to increase the time period. However,
provision has been made for barring outgoing services of such defaulting
subscriber for fifteen days, so as to prompt the subscriber to pay the outstanding
amount due to the DO. Further, the extended period will also help inter-service
area porting subscribers who may have to settle outstanding payments of a
different service area from where the subscriber ported his mobile number. In case
the subscriber fails to make payment within fifteen days, his mobile number will be
disconnected permanently by the RO and number will be returned to the number
range holder after sixty days.
Reduction in timelines for Number return process
8. In the existing MNP Regulations, in case of disconnection of a mobile number in the
network of RO, it is mandated that such mobile number will be returned to the
number range holder after the expiry of ninety days. This implies that once a mobile
number is disconnected, it remains unutilized for as long as ninety days. For
effective utilization of such a mobile number, the Authority has reduced this time
period to sixty days.
-----
Previous and next
All provisions of Telecommunication Mobile Number Portability Regulations, 2009.
Questions people ask
Is regulation 19 of Telecommunication Mobile Number Portability Regulations, 2009. still in force?
No repeal of Telecommunication Mobile Number Portability Regulations, 2009. is recorded.