Rule 6, The Explosives Rules, 2008: Authorisation of explosives
The Explosives Rules, 2008 - Rule 6
Text of rule 6
Authorisation of explosives
6. Authorisation of explosives :— (1) No person shall
manufacture, import, export, transport, possess, sell or
use any explosive unless it has been declared as an
authorised explosive, by an order issued by the Chief
Controller and published by the Central Government in the
Official Gazette:
Provided that nothing in this rule shall apply to the
manufacture and possession for test and trial purposes
and not for sale of a new explosive composition under
development at a place specially approved for the purpose
by the Chief Controller.
(2) Any person desirous of including an explosive
in the list of authorised explosives shall submit an
application to the Chief Controller.
(3) The application submitted in accordance with
sub-rule (2) shall be accompanied by following particulars,
namely :—
(a) the nature and composition of the explosives
and in case of plastic explosives, the name and
percentage of the marking agent;
(b) the limiting range of percentage of each
ingredient of the explosive, including
substitutes, if any;
(c) method of function, purpose of use and
performance characteristics of the explosives
and instructions governing its use;
168 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(i)]
(d) in the case of a new explosive to be
manufactured in India, the process of
manufacture stating safe operating procedures
and precautions;
(e) where an explosives is enclosed in a case or
other contrivance, the dimensions of the case
or other contrivance, the quantity, nature,
brand of explosives contained therein and
markings thereon;
(f) the box, wrapping or other container in which
the explosive will be handled, used or displayed
or otherwise distributed including the markings
thereon;
(g) the package in which the explosive will be
transported and stored including the markings
thereon;
(h) country of origin with name and address of
the manufacturer, UN Classification and UN
number of the explosives; recommended
methods of disposal; material Safety Data
Sheet for the explosives and raw material;
(i) fee referred to in Part 2 of schedule IV to these
rules;
(4) When, in the opinion of the Chief Controller, an
explosive in respect of which an application is made may
properly be considered for authorisation, the Chief
Controller shall instruct the applicant as to the samples
required and the manner of forwarding the same to the
Departmental Testing Station, or to any other authority
specified by the Chief Controller in this behalf for testing
thereof along with prescribed fees.
(5) No person shall send a sample of an explosive
unless such person has first received the instruction
referred to under sub-rule (4).
(6) No person shall send a sample of an explosive
otherwise than in accordance with instructions given by
the Chief Controller under sub-rule (4).
(7) (i) Sample forwarded under sub-rule (4) shall be
subjected to such of the tests enumerated in clause (ii) of
this sub rule as are necessary having regard to the nature
and type of explosive submitted to ensure that the explosive
is capable of being safely manufactured, handled, stored
transported and used.
(ii) The tests referred to in clause (i) pertain to —
(a) physical properties including consistency,
reaction tendency to absorb moisture,
segregation in transport or otherwise of the
constituents, exudation, behaviour at low
temperatures, specific gravity and such other
physical properties as may be considered
necessary;
(b) chemical composition —determination of the
percentage composition of the ingredients
forming the explosive, and the quality of the
ingredients employed in its manufacture;
(c) stability — determination of stability after
subjection to such varying environmental
conditions as would tend to produce
spontaneous ignition or variation in
sensitiveness of an explosive;
(d) ignition characteristics — ignition point,
behaviour on ignition, liability to spontaneous
ignition, behaviour on ignition in bulk;
(e) mechanical sensitiveness — determination of
sensitiveness to friction and impact;
(f) air gap and transmission of detonation;
(g) velocity of detonation;
(h) determination of strength;
(i) composition of gases evolved upon explosion;
(j) ensure that plastic explosives are detected by
vapour detection technique;
(k) such other tests and field trials as the Chief
Controller may specify.
(8) An explosive tested in accordance with sub-rule
(7) shall be declared by the Chief Controller to be an
authorised explosive if, he is satisfied that such an explosive
can be safely manufactured, handled, stored, transported
and used.
(9) Authorisation issued by the Chief Controller
under sub-rule (8) in respect of indigenous explosives shall
be valid as long as it is included in the list of authorised
explosives, and conforms to the descriptions outlined while
issuing authorisation.
(10) In case of explosives manufactured in a foreign
country and already authorised in that country, the
manufacturer, in addition to the report of tests stated in
clause (ii) of sub-rule (7) shall submit the information
regarding country of origin, the copies of various approvals
or permissions obtained for testing, packaging, markings
etc. required for authorisation of the explosives as well as
for export of explosives from the country of manufacture to
other countries and report of such other tests as the Chief
Controller may specify.
(11) The authorisation issued by the Chief Controller
of Explosives under sub-rule (8) in respect of any imported
explosives shall be valid for one year from the date of
authorisation, if the foreign manufacturer certifies that there
has been no change in the composition or any other
characteristics of the explosives.
(12) The Chief Controller, may, on his own accord
once in a year or on the request of manufacturer or importer
or exporter or consignor, subject any explosive to the tests
enumerated in clause (ii) of sub-rule (7) to verify the
approved composition and characteristics of the explosives
at the Departmental Testing Station and as a result of the
¹Hkkx II¹[k.M 3(i)º Hkkjr dk jkti=k % vlk/kj.k 169
tests or otherwise, if the Chief Controller is satisfied that
the explosive is no longer safe for manufacture, handling,
storage, transport or use, or unfit for continuation of
authorisation, may delete such explosive from the
authorised list after giving the applicant or licensee an
adequate opportunity of being heard.
(13) The samples required for testing under sub-
rule (7) or sub-rule (12) and as required in rule 3 of rule 45
and testing fees as prescribed in Part 2 of Schedule IV, shall
be submitted by the licensee or applicant.
(14) The Chief Controller, on completion of the
testing of an explosive, in pursuance of sub-rule (7) shall
deicide whether or not the explosives should be declared
to be an authorised explosive; and
(a) where the explosive is declared to be an
authorised explosive, shall assign the class
including any division and sub-division and
category within which the explosive falls;
(b) where the explosive is not declared to be an
authorised explosive, shall communicate the
same with reasons thereof to the applicant.
(15) (i) The Chief Controller shall maintain a list of
authorised explosives showing-
(a) the brand or trade name of the explosives;
(b) the name and address of the manufacturers;
(c) the class, including any division and sub-
divisions thereof, within which each explosive
falls ; and
(d) the safety distance category and the
corresponding UN Classification and UN
Number.
(ii) The list of authorised explosives shall be
published by the Chief Controller from time to time.
(16) (i) No alteration in the composition, limiting
percentage of ingredients or substitute ingredients, the
process of manufacture, the description and construction
of the case or the contrivance as submitted in accordance
with sub-rule (3) shall be carried out without prior approval
of the Chief Controller.
(ii) The Chief Controller may order fresh test to be
carried out if the proposed alteration in the percentage,
composition, nature of ingredients, process of manufacture
or construction of the case or contrivance of the explosive
are likely to change the results of the original test prescribed
in these rules.
(17) For trial manufacture and field trial of new
explosive composition, the following procedure shall be
observed, namely :—
(i) Upon scrutiny of the proposal, the Chief
Controller may grant permission to
manufacture trial batches of the explosives in
laboratory not exceeding explosive limit of
laboratory and direct to carry out such tests,
as he may consider necessary.
(ii) The applicant shall submit test report seeking
permission for trial manufacture in the plant or
manufacturing unit.
(iii) On receipt of test report, the Chief Controller
may permit manufacture of limited quantity of
the explosives in the manufacturing unit or
plant on trial basis.
(iv) In case of existing plants or conventional type
of explosives, the Chief Controller may permit
trial manufacture directly in the manufacturing
plant without manufacturing in the laboratory
scale.
(v) On being satisfied with the reports of the tests
as may be required by the Chief Controller, he
may issue field trial permission under such
conditions as he may specify.
(vi) After field trial, applicant shall submit to the
Chief Controller the reports of field trial and
necessary fees referred to in Part 2 of Schedule
IV of these rules.
(vii) For permitted explosives, test report and field
trial report from Central Mining Research
Institute and Central Mine Planning and
Design Institute are required to be submitted
to the Chief Controller and in case of non-
permitted explosives field trial report from
reputed mining or construction company.
(viii) On receipt of report and being satisfied, the
Chief Controller may authorise the explosives
and permit its manufacture on regular basis
provided that nothing in this sub-rule shall be
applicable for fireworks.
Chapter III
General provisions
Previous and next
Questions people ask
Is rule 6 of the Explosives Rules, 2008 still in force?
No repeal of the Explosives Rules, 2008 is recorded.