Form AT-41, Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007: FORMAT-41
Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 - Form AT-41
Text of form AT-41
FORMAT-41
FORMAT-41
Periodicity-Quarterly
Submission 40 days before the
commencement of the quarter
PROPOSED COAL ALLOCATION FOR SHORT TERM LINKAGES FOR
THERMAL POWER STATIONS
1. Name of the Power Station
2. No. of Units & Total installed capacity
3. Name of the Quarter (Period)
4. Planned Outage:
Outage Period Sl. No. Unit No. Capacity in MW From To Nature of maintenance
5. Generation Target for the Quarter in MkWh
First Month Second Month Third Month Average Target Generation
6. Average Overall Specific Coal Consumption (Kg/kWh) for Station.
7. Coal Requirement to achieve Targeted Generation in metric tonnes:
First Month Second Month Third Month Average Target Generation
8. Average Stock Building per month in metric tonnes subject to stocking capacity of the station’s
stock yard.
9. Average monthly coal requirement during the quarter in metric tonnes (details below)
Sl. No. Source of supply/field/company Mode of Transportation Quantity
Total
Sl.No Item
1
2
3
4 Installed capacity ( Installed capacity & Unit rating in MW and No. of
Units)
5 Type of station (Whether CCGT/ OCGT)
6 Energy generation of station during the month Target Actual
(MkWh)
7 Alternate fuel being used (Naphtha/ HSD)
8 Fuel supply position of the month
(1.) Allocation Gas HSD Naphtha
MMSCM kl mt
(a.) As per original allocation for the month by Gas Linkage
Committee
(b.) Present allocation for the month
(2.) Consumed during the month
(a.) For generation from existing Units
(b.) For commissioning, testing etc. of new Units
9 Cumulative consumption during the year
10 Average gross calorific value of the fuel for the month kcal/SCM kcal/ kl kcal/ kg
11 Generation loss in MkWh, if any, due to shortage of gas/alternate fuel
during the month
12
Reasons for short supply of fuel compared to present allocation, if any
13 Source of supply
14 Mode of transport from source to power station (Rail/Road/Pipeline)
15
Landed cost (Average for month) of fuel at power station in Rs./SCM Rs./SCM Rs./kl Rs./mt
16 Remarks, if any.
MMSCM-Million Metric Standard Cubic Metre
mt = metric tonne
kl = kilo litre
Submission by 15th day
Particulars/ Data
Owner's name:
Name of the gas based Thermal power station
MONTHLY FUEL SUPPLY DATA OF GAS BASED THERMAL POWER STATIONS
(UTILITY) FOR THE MONTH ……. YEAR 20--
170 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Telephone No.
Fax No.
Mailing address:
Previous and next
Questions people ask
Is form AT-41 of Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 still in force?
No repeal of Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 is recorded.