Annexure I, Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007: ANNEXURE-I
Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 - Annexure I
Text of annexure I
ANNEXURE-I
ANNEXURE-I
Title of Format Frequency of
data
furnishing
Format
No.
Target Date (By)
Generation of Electricity Annual 1 30-Jun
Transmission of Electricity Annual 2 30-Jun
Distribution of Electricity Annual 3 30-Jun
Trading of Electricity Annual 4 30-Jun
Details of actual sale and purchase of Gross
Electrical Energy
Annual 5 30-Jun
Installed Electricity Generating Capacity Annual 6 30-Jun
Details of electricity generating capacity added Annual 7 30-Jun
Details of electricity generating sets retired from
service
Annual 8 30-Jun
Details of derations of electricity generating sets Annual 9 30-Jun
Details of fuel consumption Annual 10 30-Jun
Details of step-up transformers in service at the
power stations and various sub-stations as on
31.03.20..
Annual 11 30-Jun
Details of step-down transformers in service as on
31.03.20..
Annual 12 30-Jun
Details of distribution transformers in service as on
31.03.20..
Annual 13 30-Jun
Details of transmission and distribution lines as on
31.03.20..
Annual 14 30-Jun
Details of electricity consumers, connected load and
consumption
Annual 15 30-Jun
Details of manpower Annual 16 30-Jun
Training Facilities/Training Capacity in the Power
Sector (Man-days of year)
Annual 17 30-Jun
Details of theft of electricity Annual 18 30-Jun
Statistics on electrical accidents Annual 19 30-Jun
Reasons for electrical accidents Annual 20 30-Jun
LIST OF FORMATS, FREQUENCY (IES) AND TARGET DATE (S)
106 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Title of Format Frequency of
data
furnishing
Format
No.
Target Date (By )
Annual data of HV/EHV industry having electricity
demand of 1 MW or above
Annual 21 30-Jun
Daily Operational Data of Thermal Power Stations
and Nuclear Power Stations
Daily 22 1030 hrs
Daily Operational Data of Hydro Power Stations Daily 23 1030 hrs
Monthly Operational Data of Thermal Power Stations
and Nuclear Power Stations
Monthly 24 7th day
Monthly Operational Data of Hydro Power Stations Monthly 25 7th day
Data for fixation of annual targets of electricity
generation for year 20--- 20---
Annual 26 30-Nov
Regional Power Supply Position (Daily Operation
Report)
Daily 27 0900 hrs
Provisional Power Supply Position Monthly 28 5th day
Revised Power Supply Position Monthly 29 18th day
Daily data regarding loss of generation on account
of shortage of coal, gas and unrequisitioned liquid
fired capacity
Daily 30 0900 hrs
Monthly Data regarding Loss of Generation on
account of shortage of coal, gas, unrequisitioned
liquid fired capacity & backing down due to system
constraints
Monthly 31 10th day
Data for load generation balance report (LGBR) Annual 32 End February
Unscheduled Interchange (UI) Status Monthly 33 10th day
Details of Power Traded by the Trading Company Monthly 34 10th day
Progress of capacitor installation programme Monthly 35 20th day
Daily Coal Report Daily 36 1500hrs.
Coal Report Monthly 37 15th day
Generation Loss due to fuel shortage Monthly 38 7th day
Report of Monthly Average Ash percentage Monthly 39 7th day
106 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Report of Quarterly/Annual Average Ash Percentage
(by weight) in coal received
Quarterly 40 30th day after the end of
quarter
Title of Format Frequency of
data
furnishing
Format
No.
Target Date (By )
Proposed Coal Allocation for Short Term Linkages
for Thermal Power Stations
Quarterly 41 40 days before the
commencement of the
quarter
Monthly Fuel Supply Data of Gas Based Thermal
Power Stations
Monthly 42 15th day
Monthly Fuel Supply Data of Liquid Fuel Based
Thermal Power Stations
Monthly 43 15th day
Monthly Fuel Supply Data of DG Power Stations Monthly 44 15th day
Fuel-Oil Data Monthly 45 15th day
Status of Progress of Villages Electrification and
Irrigation Pump sets Energisation
Monthly 46 3rd day
District wise status of progress of village
electrification and energisation of Pump sets
Monthly 47 3rd day
District wise Monthly Progress of Inhabited Village
Electrification
Monthly 48 3rd day
District-Wise Monthly Progress of Energisation of
Irrigation Pump sets
Monthly 49 3rd day
Villages electrified in various population groups and
the population covered as on……..
Monthly 50 3rd day
Metering Status for the Month---------year--------- Monthly 51 3rd day
Details of Failure of Distribution & Power
Transformers in the Month---,Year 20--------
Monthly 52 3rd day
Reliability Index at Customer Level for the Month-----
,year------
Monthly 53 3rd day
Reliability Indices(11KV Feeders) for the Month----
,Year-----
Monthly 54 3rd day
Financial Turn Around of Power Distribution for the
Financial Year---
Annual 55 30th April
Aggregate Technical & Commercial (A T & C)
Losses for the Financial Year------------
Annual 56 30th April
Fuel Data of Fossil Fuel Based Thermal Power
Stations for the month--------20----
Monthly 57 20th day
Heat Rate Data of Coal/Lignite Based Thermal
Power Stations for Month-----Year
Monthly 58 20th day
107 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Heat Rate Data of Combined Cycle Gas Turbine
Power Stations for Month-------- 20----------
Monthly 59 20th day
Monthly Environmental Data of Thermal Power
Plants
Monthly 60 20th day
Title of Format Frequency of
data
Format
No.
Target Date (By )
Monthly Peak Hours Generation Data by
Coal/Lignite Based or Combined Cycle Gas Turbine
(CCGT) Power Stations
Monthly 61 7th day
Generating Company Data for Financial Study Annually 62 30th June
Transmission Company Data for Financial Study Annually 63 30th June
Power Distribution Company Data for Financial
Study
Annually 64 30th June
Monthly Abstract of Ash Generation and Utilisation Monthly 65 20th day.
108 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Title of Format
Form-
at No. Genco Transco Discom Traders
SEBs /
Licensees/Elecy.
Deptts. RLDCs SLDCs RPCs CPPs/ Industries
Generation of Electricity 1 Y Y
Transmission of Electricity 2 Y Y
Distribution of Electricity 3 Y Y
Trading of Electricity 4 Y
Details of actual sale and purchase of Gross
Electrical Energy 5 Y Y Y Y
Installed Electricity Generating Capacity 6 Y Y
Details of electricity generating capacity added
7 Y Y
Details of electricity generating sets retired from
service 8 Y Y
Details of derations of electricity generating sets
9 Y Y
Details of fuel consumption 10 Y Y
Details of step-up transformers in service at the
power stations and various sub-stations as on
31.03.20.. 11 Y Y Y Y
Details of step-down transformers in service as
on 31.03.20.. 12 Y Y Y Y
Details of distribution transformers in service as
on 31.03.20.. 13 Y Y Y
Details of transmission and distribution lines as
on 31.03.20.. 14 Y Y Y Y
Details of electricity consumers, connected load
and consumption 15 Y Y
Details of manpower 16 Y Y Y Y
Training Facilities/Training Capacity in the Power
Sector (Man-days of year) 17 Y Y Y Y
Details of theft of electricity 18 Y Y
Statistics on electrical accidents 19 Y Y Y Y Y Y
Reasons for electrical accidents 20 Y Y Y Y Y Y
Annual data of HV/EHV industry having electricity
demand of 1 MW or above 21 Y
Daily Operational Data of Thermal Power
Stations and Nuclear Power Stations 22 Y Y Y Y
110 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Statement of Specific Applicability of formats
Annexure-II
Title of Format
Form-
at No. Genco Transco Discom Traders
SEBs /
Licensees/Elecy.
Deptts. RLDCs SLDCs RPCs CPPs/ Industries
Daily Operational Data of Hydro Power Stations
23 Y Y Y Y
Monthly Operational Data of Thermal Power
Stations and Nuclear Power Stations 24 Y Y Y Y
Monthly Operational Data of Hydro Power
Stations 25 Y Y Y Y
Data for fixation of annual targets of electricity
generation for year 20---20….. 26 Y Y Y
Regional Power Supply Position (Daily Operation
Report) 27 Y
Provisional Power Supply Position 28 Y Y
Revised Power Supply Position
29 Y Y
Daily data regarding loss of generation on
account of shortage of coal, gas and
unrequisitioned liquid fired capacity 30 Y Y Y Y
Monthly Data regarding Loss of Generation on
account of Shortage of Coal, Gas, Unrequisitoned
Liquid Fired Capacity & Backing Down due to
System Constraints 31 Y Y
Data for load generation balance report (LGBR)
32 Y Y Y
Unscheduled Interchange (UI) Status 33 Y Y
Details of Power Traded by the Trading Company
34 Y
Progress of capacitor installation programme
35 Y
Daily Coal Report 36 Y Y
Coal Report 37 Y Y
Generation Loss due to fuel shortage 38 Y Y
Report of Monthly Average Ash percentage 39 Y Y
Report of Quarterly/Annual Average Ash
Percentage (by weight) in coal received 40 Y Y
Proposed Coal Allocation for Short Term
Linkages for Thermal Power Stations 41 Y Y
111 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Title of Format
Form-
at No. Genco Transco Discom Traders
Licensees/Elecy.
Deptts. RLDCs SLDCs RPCs CPPs/ Industries
Monthly Fuel Supply Data of Gas Based Thermal
Power Stations 42 Y Y
Monthly Fuel Supply Data of Liquid Fuel Based
Thermal Power Stations 43 Y Y
Monthly Fuel Supply Data of DG Power Stations
44 Y Y
Fuel-Oil Data 45 Y Y
Status of Progress of Villages Electrification and
Irrigation Pump sets Energisation 46 Y Y
District wise status of progress of village
electrification and energisation of Pump sets 47 Y Y
District wise Monthly Progress of Inhabited Village
Electrification 48 Y Y Y
District-Wise Monthly Progress of Energisation of
Irrigation Pump sets 49 Y Y
Villages electrified in various population groups
and the population covered as on…….. 50 Y Y
Metering Status for the Month---------year--------- 51 Y Y
Details of Failure of Distribution & Power
Transformers in the Month---,Year 20-------- 52 Y Y
Reliability Index at Customer Level for the Month--
---,year------ 53 Y Y
Reliability Indices(11KV Feeders) for the Month----
,Year----- 54 Y Y
Financial Turn Around of Power Distribution for
the Financial Year--- 55 Y Y
Aggregate Technical & Commercial (A T & C)
Losses for the Financial Year------------ 56 Y Y
Fuel Data of Fossil Fuel Based Thermal Power
Stations for the month--------20…. 57 Y Y
Heat Rate Data of Coal/Lignite Based Thermal
Power Stations for Month-----Year….. 58 Y Y
Heat Rate Data of Combined Cycle Gas Turbine
Power Stations for Month----------20---------- 59 Y Y
Monthly Environmental Data of Thermal Power
Plants 60 Y Y
112 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Title of Format
Form-
at No. Genco Transco Discom Traders
SEBs /
Licensees/Elecy.
Deptts. RLDCs SLDCs RPCs CPPs/ Industries
Monthly Peak Hours Generation Data by
Coal/Lignite Based or Combined Cycle Gas
Turbine (CCGT) Power Stations 61 Y Y
Generating Company Data for Financial Study
62 Y Y
Transmission Company Data for Financial Study
63 Y Y
Power Distribution Company Data for Financial
Study 64 Y Y
Monthly Abstract of Ash Generation and
Utilisation 65 Y Y
Y= Yes Applicable
Note: If certain items of a format are not applicable to an Entity, then 'Not Applicable' may be marked at appropriate places.
113 THE GAZETTE OF INDIA : EXTRAORDINARY [PART III - SEC.4]
Previous and next
Questions people ask
Is annexure I of Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 still in force?
No repeal of Central Electricity Authority (Furnishing of Statistics, Returns & Information) Regulations, 2007 is recorded.