Rule 54, Offshore Areas Mineral Concession Rules, 2006: Work programme of production lease
Offshore Areas Mineral Concession Rules, 2006 - Rule 54
Text of rule 54
Work programme of production lease
54. Work programme of production lease:- Every holder of a production lease
shall submit to the administering authority within a period of sixty days from the date of
execution of the production lease, a work programme including a scheme of production
operations indicating the manner in which he proposes to carry out production
operations in the area covered by the lease.
55. Modification of scheme of production - (1) A scheme of production
operations prepared and submitted under rule 54 may be modified at any time on
geological considerations by the holder of a production lease during continuance of the
lease.
(2) Any modification carried out under sub-rule (1) shall be. intimated to the
administering authority by the holder of production lease within a period of fifteen days
of such modification.
Previous and next
← Rule 53Submission of reports about exploration operationsRule 56 →Production operations to be carried out in accordance with the scheme of production
All provisions of Offshore Areas Mineral Concession Rules, 2006
Questions people ask
Is rule 54 of Offshore Areas Mineral Concession Rules, 2006 still in force?
No repeal of Offshore Areas Mineral Concession Rules, 2006 is recorded.