Rule 25, Offshore Areas Mineral Concession Rules, 2006: Renewal of production lease
Offshore Areas Mineral Concession Rules, 2006 - Rule 25
Text of rule 25
Renewal of production lease
25. Renewal of production lease.- (1) If an application for renewal of a
production lease made within the time referred to in clause (b) of sub-rule (1) of rule 23,
is not disposed by the administering authority before the date of expiry of the lease, the
3518 GI/2006 -15
114 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(i)]
period of that lease shall be deemed to have been extended by a further period till the
administering authority passes order thereon.
(2) The administering authority may condone delay in filing an application for renewal
of production lease made after the time limit specified in clause (b) of sub-rule (1) of rule
23 provided the application has been made before the expiry of the lease.
Previous and next
← Rule 24Acknowledgement of applicationRule 26 →Status of the grant on the death of applicant for production lease
All provisions of Offshore Areas Mineral Concession Rules, 2006
Questions people ask
Is rule 25 of Offshore Areas Mineral Concession Rules, 2006 still in force?
No repeal of Offshore Areas Mineral Concession Rules, 2006 is recorded.