19. Licence to be executed within three months.- (1) Where on any application
for an exploration licence, an order has been made for the grant of such licence, a
deed granting such licence shall be executed within ninety days of the date of the
communication of the order or such further period as the administering authority may
allow in this behalf, and if no such deed is executed within the said period due to any
default on the part of the applicant, the administering authority may revoke the order
granting the licence and in that event the exploration charges paid shall be forfeited to
the administering authority.
(2) The deed referred to in sub-rule (1) shall be in Form K, or in a form as near thereto
as circumstances of each case may require.
(3) The date of the commencement of the period, for which an exploration licence is
granted shall commence on the date on which the deed is executed after all necessary
clearances have been obtained.
Previous and next
All provisions of Offshore Areas Mineral Concession Rules, 2006
Questions people ask
Is rule 19 of Offshore Areas Mineral Concession Rules, 2006 still in force?
No repeal of Offshore Areas Mineral Concession Rules, 2006 is recorded.