LawGrids logoLAWGRIDS.ORG

Rule 9, Marble Development and Conservation Rules, 2002: Modification of scheme of prospecting

Marble Development and Conservation Rules, 2002 - Rule 9

Text of rule 9

Modification of scheme of prospecting

9. Modification of scheme of prospecting.- (1) A prospecting scheme prepared and submitted under rule 8 may be modified at any time on geological considerations by the holder of a prospecting licence during continuance of the prospecting licence. (2) Any modification carried out under sub-rule (1) shall be intimated to the State Government or any person authorised in this behalf by that Government, by the holder of a prospecting licence within a period of fifteen days

Previous and next

All provisions of Marble Development and Conservation Rules, 2002

Questions people ask

Is rule 9 of Marble Development and Conservation Rules, 2002 still in force?

No repeal of Marble Development and Conservation Rules, 2002 is recorded.