Executive Order M&V timeline extension 2020
- Kind: Order
- Under: The Energy Conservation Act, 2001
Text of this order
No. 10/4/2020-EC
Government of India
Ministry of Power
'F' Wing, Nirman Bhawan.
New Delhi, 31 m August, 2020
Order
Whereas in exercise of the powers conferred by clauses (g) and (n) of section 14 of the Energy
Conservation Act, 2001 (52 of 2001) the Central Government in consultation with the Bureau of
Energy Efficiency (BEE) had specified for the Designated Consumers, the Energy Consumption
Norms and Standards for the period 2017-2018 to 2019-2020 vide Notification of the
Government of India in the Ministry of Power number S.O. 998 (E) dated the 30th March, 2017,
published in the Gazette of India, Extraordinary, Part II, Section 3, Sub-section (ii) for
compliance in the target year 2019-2020 under the Energy Conservation (Energy Consumption
Norms and Standards for Designated Consumers, Form, Time within which, and Manner of
Preparation and Implementation of Scheme, and Procedure for Issue of Energy Savings
Certificates, and the value of Per Metric Ton of Oil Equivalent of Energy Consumed) Rules,
2012 [For the purpose of reference known as Energy Conservation Rules, 2012] vide
Notification of the Government of India in the Ministry of Power number G.S.R. 269(E) dated
the 30th March, 2012, published in the Gazette of India, Extraordinary, Part II, Section 3, Sub-
section (i).
And whereas sub-rule (1) of rule 6 of the Energy Conservation Rules, 2012, referred to in Para 1
above, provide that every designated consumer, specified in the Notification of the Government
of India in the Ministry of Power number S.O. 998 (E) dated the 30th March, 2017 referred to in
Para 1 above, within four months of the conclusion of the target year, shall submit to the State
designated agency ,with a copy to the Bureau, the performance assessment document in Form 'A'
covering the performance for their cycle-2017- 2018 to 2019-2020- specifying the compliance
with the energy consumption norms and standards, duly verified together with the certificate in
Form 'B' given by the Firm of empanelled accredited energy auditors (EmAEAs) accompanied
by the documents specified in the aforesaid rule 6 of the Energy Conservation Rules, 2012.
And whereas the designated consumers are required to submit the performance assessment
document by the 31' July, 2020 in compliance with the aforesaid sub-rule 1 of rule 6, most of the
designated consumers have informed that they are not in a position to submit the performance
assessment document by the target date of 3Ist July, 2020 on account of COVID-19 pandemic
and subsequent travel and other restrictions beyond their control.
Due to the COVID-19 pandemic and subsequent travel and other restrictions, both DCs and
EmAEAs have been facing challenges to carry out the M&V performance audit and have been
approaching BEE for relaxation in the timelines as it is apprehended that it will not be possible to
Cont. 2/..
2
initiate, conduct and submit the performance assessment document by the notified target date of
31S` July, 2020.
And whereas the Central Government in the Ministry of Power in consultation with BEE has
taken into consideration the above difficulties expressed by the various Firms of empanelled
accredited energy auditors and Designated Consumers and is of the opinion that the verification
of the implementation of the Perform, Achieve and Trade scheme, launched in 2017-18 for third
cycle (2017-2018 to 2019-2020), involves many challenges due to pandemic situation of
COVID-19 for which the timeframe could not be ascertained prior to the launch of the scheme
and consider it expedient and in public interest to assist the Designated Consumers in the
implementation of the scheme in right earnest.
Now, therefore, in exercise of the powers conferred by sub-rule 1 A of rule 6 of the Energy
Conservation Rules, 2012 the Central Government in the Ministry of Power in consultation with
the Bureau grant an extension of time of two months with effect from the 1st of August, 2020, to
enable the Designated Consumers to submit to the respective State Designated Agencies, with a
copy to the Bureau, the performance assessment documents complete in all respects for the
Cycle (2017-2018 to 2019-2020), in compliance with sub-rule (1) of rule 6 of Energy
Conservation Rules, 2012.
(Arun ,kgg al)
Under Secretary to the Government of India
Tel: 23061623
Copy of this Order is sent for compliance to:
(i) All Designated Consumers (by name)
(ii) All State Designated Agencies.
(iii) The Director General, Bureau of Energy Efficiency, New Delhi, with reference to
letter No.NMEEE-11023/21/2020-BEE/524 dated 14th August, 2020.
(Ar n Agga 1)
Under Secretary to the Government of India
Tel: 23061623
Page 1