Form XV, GSR 625 (E) The Railways (Opening for Public Carriage of Passengers) Rules, 2000: FORM XV
GSR 625 (E) The Railways (Opening for Public Carriage of Passengers) Rules, 2000 - Form XV
Text of form XV
FORM XV
FORM XV
[ See rule 5 (3) ]
LIST OF QUESTIONS AND ANSWERS
SECTION
Length in km
Sl. No.
(1)
1
2
3
4.
5
6
7 .
8
9
Questions
(2)
Formation Earthwork
Are there any sections of the line over which
special precautions to ensure safe working are
necessary, owing to sharp curves or steep grades?
What widths of formation have been adopted:
(a) in bank,
(b) in cutting (exclusive of side drains) ?
Have any special precautions been taken against
slips in cutting and embankments ?
Are side drains to the formation and catch water
drains above the side slopes, provided for all
cuttings?
Are trolley refuges necessary in any long cuttings,
and if so, have they been provided at suitable
intervals ?
TUNNELS
Are there any tunnels not fully lined ?
If so, are they safe without further lining ?
Do any portions of the sides or roof of any tunnel
infringe maximum and minimum dimensions ?
Have adequate facilities been provided to enable
workmen to escape from an approaching train
without difficulty ?
Have the tunnels been properly ventilated ?.
Answers
(3)
2009 GI/2000—13
98 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(i)]
(1)
10
11
12
13
14
15
16
17
18
(2)
BRIDGES
Are the bridges/elevated structures designed in
accordance with the provisions contained in
Bridge Rules, having regard to the standards of
loading which they are intended to carry? Full
particulars should be appended of any case of
departure from the requirements ?
Has due care been taken to provide sufficient
waterway to guard against scour ?
Are free board and vertical clearance under bridge
provided according to bridge sub structure code?
If not, quote sanction number with date.
Has due notice been taken of Railway affected
works in the catchement of the waterways and all
necessary safeguards provided for wash aways
and breaches due to breaching of tanks/bunds ?
Have the waterways provided been formally
approved by the Local Government?
Have sufficient head-way been provided
for crafts plying or likely to ply, on navigable
waters ?
Are there any bridges intended for use by the
public ?
(a) If so, in the case of a road or pathway clear of
the track, have adequate handrails or parapets
been provided ?
(b) Or in the case of a passage common with the
track, have suitable gates across the roadway, and
signals for trains been provided ?
Are long bridges provided with adequate facilities
to enable workmen to stand clear of an
approaching train without difficulty ?
Have trolley refuges been provided if necessary ?
(3)
99
(1)
19.
20
21
22.
23
24
25
26
27
(2)
Are the wooden sleepers, adequately protected from
fire?
Are all girder bridges provided with guardrails?
Are there any bridges where it is necessary to
provide guard rails but these are not yet provided?
Has information of the nature and depth of the
foundation and hidden work in bridges, culverts
and other structures likely to be exposed to scour,
been recorded on the structures themselves ?
Have surplusing arrangements been made for
canals crossing track ?
Have completion drawings of all important
bridges and other structures been prepared ?
Do these contain all information regarding
foundations and other hidden work as actually
executed? Where are they recorded ?
LAND BOUNDARIES AND FENCING
Have the boundaries of the Railway land been
properly defined by suitable marks, which can
readily be found and identified ?
Have complete and accurate land plans been
prepared and do they bear the signatures of the
responsible Civil and Railway Officer concerned?
Where are they recorded ?
LEVEL CROSSINGS
Has the Local Government approved the sitting
and classification of the level crossings ?
Have all level crossings been constructed in
accordance with the Standard Sepcifications for
level crossings (vide Chapter IX of P. Way
Manual) according to the class of crossing ?
100 THE GAZETTE OF INDIA: EXTRAORDINARY [PART II—SEC. 3(i)]
(1)
28.
29
30
31
32
33
34
35
36
37
(12)
If not, at which crossings and in what respects do
they fall short of them ?
KILOMETER AND GRADIENT POSTS
Are proper Kilometer and gradient posts
provided?
(a) Are the telegraph posts numbered, and
(b) can the figures be read with ease from
passing trains and trolleys?
From which fixed point has the Kilometrage been
reckoned?
BALLAST AND PERMANENT WAY
Is the ballast provided of good quality and
sufficient in quantity for the traffic anticipated ?
Is there any departure from permanent way
manual ?
Is the permanent way properly laid, complete with
fastenings, and is it suitable for the proposed
speed & loads ?
Are there any especially sharp curves at which
checkrails are considered necessary? Have they
been provided at all such curves ?
Are the curves laid out with transition curves at
each end ?
Have all curves been adequately super elevated for
the speeds in force? Is the super-elevation to be
given to each curve indicated at site ?
STATION FACILITIES
Have Maximum and Minimum Dimensions in
station yards been observed ?
Has suitable accommodation for passengers been
provided at all stations ?
Have latrines been provided on platforms, and are
they properly situated, constructed and lighted ?
101
(1)
38
39
40
41
42
43
(2)
Are there proper arrangements for supplying
drinking water?
Is foot over bridges or sub-ways for crossing the
line provided where necessary?
Are any landings provided*
Are the rise and tread of steps properly
proportioned?
•If the total height of steps exceeds 4.57 metres, it
is usually desirable that there should be an
intermediates landing not less than 1.22 metres in
length.
Are the names of stations shown both in Hindi
and English and in vernacular language, in large
and distinct letters in conspicuous positions so as
to be seen readily by passengers in the trains both
during day and night?
Are clocks provided at all block stations?
SIGNALLING AND TELECOMMUNICATION
/BLOCK WORKING
Have the requirements and recommendations for
signalling and interlocking, and the catechism for
signalling and interlocking installations vide
Chapter VII of these rules, and the appendix
thereto, being fully complied with, according to
the class of signalling and interlocking installed?
If not, in what respect do the arrangements
provided fell short of them?
Have the requirements and recommendations for
signalling and telecommunications installations in
accordance with the instructions issued for the
installations of S&T equipment in 25 kV 50 Hz
electrified sections been complied with? If not, in
what respect the arrangements provided fall short
of them ?
102 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(i)]
(1)
44
45.
46
(2)
STATION WORKING
Is provision made, whether by trap points or other
means, to prevent, vehicles standing on sidings,
from fouling any running line?
Are there any stations situated on a steeper grade
than 1 in 400? If so, what special safety devices
are adopted and / or special rules enforced at those
Stations?
What safety sidings are provided?
Are they suitable? @
Are any others necessary?
*Note l : No station should be constructed nor
should any siding join a passenger line on a
steeper gradient than 1 in 260, except where it is
unavoidable, and then only with the previous
sanction of the Railway Board obtained through
the Commissioner of Railway Safety, when a slip
siding or other arrangements is made, sufficient to
prevent accidents.
@Note 2: At any station situated in the immediate
neighbourhood of an incline steeper than 1 in 100
felling away from the station, a catch siding in the
former case, and a slip siding in the latter case,
should be provided, if necessary, in a suitable
position. The take off points to a catch siding or a
slip siding should normally be set and locked for
the siding, except where required to be trailed
through.
"For the purpose of the footnotes marked* 1 and 2
the definition of a station yard as given in item 2
103
(1)
47
48
49
50
51
52
(2)
of Chapter II of Schedule of Dimensions shall
apply"
Are station yards so arranged that shunting past
junctions or level crossings may be avoided as far
as possible?
Are shunting necks for goods working provided in
large yards, where shunting operations cannot
otherwise be carried on without interfering with
incoming trains?
ROLLING STOCK
Is the following information noted in a
conspicuous position on each vehicle?
(i)Passenger Carriages- The maximum number of
passenger intended to be carried in each
compartment of every description of carriage? *
(ii) Goods wagons-The tare weight of the empty
wagon (including wheels, axles and axle boxes
and springs) and the maximum load, in tonnes,
which the wagon is constructed to carry?
Are means for communications between
passengers and the guard, provided in all trains
carrying passengers? **
Have all engines and tenders, and all vehicles
intended to run on passenger trains been fitted
with the vacuum/air brake?
Are all locomotive & motor coaches provided
with:
(a) Cattle guards
(b) High power headlights
(c) Other prescribed safety equipments.
*Note: This information should be in the
vernacular language as well as in English and
Hindi.
104 THE GAZETTE OF INDIA: EXTRAORDINARY [PART II—SEC. 3(i)]
(1)
53
54
55
56
57.
58.
59
(2)
**Except in the case of complete or partial failure
of vaccume, trains carrying passengers may run
without such means of communication, only in
accordance with general Rule 4.18.
FACILITIES FOR BOOKING
Are suitable arrangements made at all stations for
the booking of passengers ?
Are suitable weighing machines provided
at all stations open for goods/parcel booking ?
Are time and fare tables placed in a convenient
position for inspection by the public at each
station? Are these documents clearly exhibited in
Hindi & English and also the vernacular language
of the district?
Is a copy of the general rules for regulating the
working of the railway available for inspection at
every station ?
Is every station provided with station diagram,
station working orders, coaching and goods
tariffs, and all other necessary manuals or
instructions, forms and registers for the work of
the station ?
Do the working orders provide suitably for all
special conditions met with at each station ?
ELECTRICAL
Have the Rules for the Design and Inspection of
equipment for Electric Traction (Vide Chapter
VIII of these rules) been individually and fully
complied with ?
If not, where and in what respect, do the
arrangements provided fall short of them?
GENERAL
What provision of Medical First Aid equipment
has been made for use in the event of accident ?
105
Previous and next
All provisions of GSR 625 (E) The Railways (Opening for Public Carriage of Passengers) Rules, 2000