Form X, GSR 625 (E) The Railways (Opening for Public Carriage of Passengers) Rules, 2000: FORM X
GSR 625 (E) The Railways (Opening for Public Carriage of Passengers) Rules, 2000 - Form X
Text of form X
FORM X
FORM X
[ See rule 5(1) (j)]
BRIEF PARTICULARS OF TRACTION INSTALLATION
Section - Tundla-Delhi Northern Railway
Length 292 RKM Gauge 1676 mm
1. Total track kms electrified section - 650
2. Brief particulars of traction system: -
The type of Over Head Equipment installed on main line of the section is
of the simple polygonal with swivelling brackets having tensions in the
conductors regulated automatically. The tension in the catenary and
contact wire is kept as 1000 kgf each. The contact wire has been given a
presage of 103mm for a span of 72m (suitably reduced for smaller
spans). On secondary lines and yards the Over Head Equipment is of
fixed type and unregulated. The contact wire is grooved hard drawn
copper with 107 sq. mm cross section supported by means of copper
droppers from catenary which is standard (19.210mm) with 65mm cross
section made up of cadmium copper having 80% conductivity. The
maximum wind pressure for design of masts and foundation has been
taken as 112.5 kg/sqm. maximum span adopted on main lines is 63 m.
The Over Head Equipment has been designed for a maximum speed of
160km/h.
The power supply is taken from UPSEB at a single point viz. Aligarh
from where railways own transmission lines are run for feeding the sub
stations located at Hathras, Khurja and Sahibabad. At each of the sub
stations two power transformers 12.5 MVA, 132/25 KV are installed, one
of them acting as standby. Standard arrangement of having neutral
section 41m in length has been provided between two sub stations for
separation of phases. From sectioning and isolating facilities sub
sectioning and paralleling stations have been provided. All the switching
operations at power supply stations are remote controlled from a single
remote control centre located at Tundla.
Note: The Railway will provide suitable information as per sample.
94 THE GAZETTE OF INDIA : EXTRAORDINARY [PART II—SEC. 3(i)]
Previous and next
All provisions of GSR 625 (E) The Railways (Opening for Public Carriage of Passengers) Rules, 2000