Rule 85, Atomic Energy (Factories) Rules, 1996: EXEMPTION OF CERTAIN ADULT WORKERS

Atomic Energy (Factories) Rules, 1996 - Rule 85

Text of rule 85

EXEMPTION OF CERTAIN ADULT WORKERS

85. EXEMPTION OF CERTAIN ADULT WORKERS.- Adult workers engaged in factories specified in column 2 of the schedule to this rule on the work specified in column 3 of the said schedule shall be exempted from the provisions of the sections specified in column 4 subject to the conditions, if any, specified in column 5 of the said schedule. Atomic Energy Factory Rules, 1996 114 Rule 85 (Sch.) SCHEDULE Section of the Act empowering grant of exemption Class of factory Nature of exempted work Extent of exemption Remarks 1 2 3 4 5 64 (2)(a) and 64(3) All factories Urgent repairs. Sections 51,52, 54,55, 56 and61. (i) No worker shall be employed on such repairs for > 15 hours on any one day, 39 hrs during any three consecutive days, or 66 hrs. during each period of seven consecutive days commencing from his first employment on such repairs. (ii) Within 24 hours of commencement of the work notice shall be sent to the Competent Authority describing the nature of the urgent repairs and the period probably required for their completion. (iii) Exemption from the provisions of section 54 shall apply only in the case of adult male workers. Atomic Energy Factory Rules, 1996 115 Rule 85(Sch.) 1 2 3 4 5 64(2)(b) and 64(3) All factories (a) Work in the machine shop, the smithy or the foundry or in connection with the mill gearing, the electric driving or lighting apparatus, the mechanical or electrical lifts or the steam or water pipes or pumps of a factory. (b) Work of examining or repairing any machinery or other part of the plant which is necessary for carrying on work in the factory. (c) Work in boiler houses and engine rooms such as lighting fires in order to raise steam or generate gas preparatory to the commencement of regular work in the factory. Sections 51, 54, 55, 56 and 61. do do The limits of work inclusive of overtime shall not exceed those mentioned in sub- section (4) of section 64. do do 64(2)(c) and 64(3) All factories (a)Work performed by drivers on lighting, ventilating and humidifying apparatus. (b) Work performed by fire pumpmen. Sections 51,54, 55 and 61. do do do Atomic Energy Factory Rules, 1996 116 Rule 85(Sch.) 1 2 3 4 5 64(2)(d) and 64(3) (1) Oil tank installations. Work performed by workers connected with pumping operations. Sections 51, 52, 54, 55, 56 and 61. In the absence of a worker who has failed to report for duty, a shift worker shall be allowed to work the whole or part of a subsequent shift provided that- (i) the next shift of the shift worker shall not commence before a period of 16 hours has elapsed; (ii) within 24 hours of the commencement of the subsequent shift, notice shall be sent to the Competent Authority describing the circumstances under which the worker is required to work in the subsequent shift; (iii) the exemption will be restricted to only male adult workers; and Atomic Energy Factory Rules, 1996 117 Rule 85(Sch.) 1 2 3 4 5 (iv)the limits of work inclusive of over time shall not exceed those mentioned in sub- section(4) of section 64. (2)Electrical transforming factories Work of operation and maintenance of the transforming plant, switch yards such as substations etc. do do (3)Chemical factories. All continuous processes such as production of heavy water. do do (4)All factories Work on automatic equipment engaged in galvanizing, anodising and enamelling. Sections 51, 52,54, 55,56 and 58. (1)The limits of work inclusive of overtime shall not exceed those mentioned in sub-section (4) of section 64 (2)The exemption shall be granted only in respect of adult male workers. Loading and unloading of railway wagons, lorries or trucks Sections 51, 52, 54, 55 & 56 do Atomic Energy Factory Rules, 1996 118 Rule 85(Sch.) 1 2 3 4 5 Any factory or class or description of factories as may be notified by the Central/ State Govt. in the Official Gazette. Work of national importance as may be notified by the Government in the Official Gazette. Sections 51, 52,54, 55,56 & 58. (1)The limit of work inclusive of overtime shall not exceed those mentioned in sub-section (4) of section 64. (2)The exemption shall be limited to adult male workers. Explanations:- 1. The following shall be considered to be urgent repairs:- (a) repairs to any part of the machinery, plant or structure of a factory which are of such a nature that delay in their execution would involve danger to human life or safety or the stoppage of manufacturing process; (b) breakdown repairs to the motive power, transmission or other essential plant of other factories, collieries, railways, dockyards, harbours, tram-ways, motor transport, gas, electrical generating and transmission, pumping or similar essential or public utility services carried out in general engineering works and foundries and which are necessary to enable such concerns to maintain their main manufacturing processes, production or services during normal working hours; (c) repairs in connection with a change of motive power, for example, from steam to electricity or vice versa, when such work cannot possibly be done without stoppage of the normal manufacturing process. 2. Periodical cleaning is not included in the terms "examining" or "repairing". Atomic Energy Factory Rules, 1996 119 Rule 86

Previous and next

All provisions of Atomic Energy (Factories) Rules, 1996

Questions people ask

Is rule 85 of Atomic Energy (Factories) Rules, 1996 still in force?

No repeal of Atomic Energy (Factories) Rules, 1996 is recorded.