Rule 56, Atomic Energy (Factories) Rules, 1996: RAILWAYS IN FACTORIES
Atomic Energy (Factories) Rules, 1996 - Rule 56
Text of rule 56
RAILWAYS IN FACTORIES
56. RAILWAYS IN FACTORIES.-
(1) This rule shall apply to railways in the precincts of a factory which are not subject to the
Railways Act, 1988.(59 of 1988)
(2) Gateways.- A gateway through which a railway track passes shall not be used for the
general passage of workers into or out of a factory.
(3) Barriers and Turngates.-
(a) Where building or walls contain doors or gates which open to a railway track, a
barrier about 1 m high shall be fixed parallel to and about 60 cm. away from the
building or wall outside the opening and extending several metres beyond it at
either end, so that any person passing out may become aware of the approaching
train when his pace is checked at the barrier:
Provided that if the traffic on the nearest track is all in one direction the barrier
shall be in the form of an "L" with the end of the short leg abutting on to the wall
and the other end opening towards the approaching train.
(b) If the distance between wall and track cannot be made to accommodate such a
barrier, the barrier or a turngate shall be placed at the inside of the opening.
(c) Where a footway passes close to a building or other obstruction as it approaches a
railway track, a barrier or a turngate shall be fixed in such a manner that a person
approaching the track is compelled to move away from the building
Atomic Energy Factory Rules, 1996
88
Rule 56
or obstruction and thus obtain timely sight of an approaching locomotive or
wagon.
(4) Crowds.-
(a) Workers' pay-windows, first-aid stations and other points where a crowd may
collect shall not be placed near a railway track.
(b) At any time of the day when workers are starting or ending work, all railway
traffic shall cease for not less than five minutes.
(5) Locomotives.-
(a) No locomotive shall be used in shunting operations unless it is in good working
order.
(b) Every locomotive and tender shall be provided with efficient brakes, all of which
shall be maintained in good working order. Brake shoes shall be examined at
suitably fixed intervals and those that are worn out replaced at once.
(c) Water-gauge glasses of every locomotive, whatever its boiler pressure, shall be
protected with substantial glass or metal screens.
(d) Suitable stops and hand-holds shall be provided at the corners of the locomotive
for the use of shunters.
(e) Every locomotive crane shall be provided with lifting and jacking pads at the four
corners of the locomotive for assisting in re-railing operation
(f) It shall be clearly indicated on every locomotive crane in English and in language
understood by the majority of the workers in the factory, for what weight of load
and at what radius the crane is safe.
(6) Wagons.-
(a) Every wagon (and passenger coach, if any ) shall be provided either with self-
acting brakes capable of being applied continuously or with efficient hand brakes
which shall be maintained in good working order. The hand brakes shall be
capable of being applied by a person on the ground and fitted with a device for
retaining them in the applied position.
(b) No wagon shall be kept standing within 3 metres of any authorised crossing.
(c) No wagon shall be moved with the help of crowbars or pinch bars.
(7) Riding on locomotive, wagon or other rolling stock.- No person shall be permitted to be
upon (whether inside or outside)any locomotive, wagon or after rolling stock except
Atomic Energy Factory Rules, 1996
89
Rule 56
where secure foothold and handhold are provided.
(8) Attention to brakes and doors.-
(a) No locomotive, wagon or other rolling stock shall be kept standing unless its
brakes are firmly applied and, where it is on a gradient, without sufficient number
of properly constructed scotches placed firmly in position.
(b) No train shall be set in motion until the shunting jamadar has satisfied himself that
all wagon doors are securely fastened.
(9) Projecting loads and cranes.-
(a) If the load on a wagon projects beyond its length, a guard or dummy-truck shall be
used beneath the projection.
(b) No loco-crane shall travel without load unless the jib is completely lowered and
positioned in line with the track.
(c) When it is necessary for a loco-crane to travel with a load, the jib shall not be
swung until the loco-crane has come to rest.
(10) Loose-shunting.- Loose-shunting shall be permitted only when it cannot be avoided. It
shall never be performed on a wagon not accompanied by a man capable of applying and
pinning down the brakes. A wagon not provided with brakes in good working order and
capable of being easily pinned down shall not be loose-shunted unless there is attached to
it at least another wagon with such brakes. Loose-shunting shall not be performed with,
or against a wagon containing passengers, live-stock or explosives.
(11) Fly-shunting.- Fly-shunting shall not be permitted on any factory railway.
(12) The shunting jamadar.-
(a) Every locomotive or wagon in motion in a factory shall be in charge of a properly
trained jamadar.
(b) Before authorising a locomotive or wagon to be moved, the shunting jamadar
shall satisfy himself that no person is under or in-between or in front of the
locomotive or wagon.
(13) Hand signals.- The hand signals used by the shunting jamadar by day and night shall be
those prescribed by the shunting rules of railways, working under the Railways Act , 1988
(59 of 1988).
(14) Night work and fog.-
(a) In factories where persons work at night, no movement of locomotive, wagon or
other rolling stock
Atomic Energy Factory Rules, 1996
90
Rule 56
otherwise than by hand shall be permitted between sunset and sunrise unless the
tracks and their vicinity are lighted on a scale of not less than 10 lux as measured
at the horizontal plane at the ground level.
(b) In no circumstances shall any locomotive or train be moved between sunset and
sunrise or at any time when there is fog, unless it carries a white head light and a
red rear light.
(15) Speed control.-
(a) A locomotive or train shall not move at a speed greater than seven kilometres per hour.
(b) A train, locomotive, wagon or other rolling stock shall not be moved by mechanical or
electrical power unless it is preceded at a distance of not less than 10 metres during the
whole of its journey by a shunting jamadar. He shall be provided with signaling flags or
lamp and whistle necessary for calling the attention of the driver.
(16) Tracks.-
(a) The distance,
(i) between tracks;
(ii) between tracks and buildings, blind walls or other structures; and
(iii) between tracks and materials deposited on the ground shall be respectively
not less than :-
(1) from centre to centre of parallel tracks, the overall width of the
widest wagon of that gauge plus twice the width of the door of
such a wagon when opened directly outward plus metre.
(2) from a building or structure other than a loading platform to the
centre of the nearest track, half the overall width of the widest
wagon of the gauge, plus the width of its door when opened
outward, plus 1.5 m.
(3) from material stacked or deposited alongside the track, on the
ground or on a loading platform, to the centre of the nearest track,
half the overall width of its door when opened directly outward,
plus 1 m.
(b) Sleepers of a track shall be in level with the ground and at the crossings of the
track with a road or walkway, the surface of the road or walkway shall be in level
with the top of the rails.
(c) All track ends shall be equipped with buffer stops of adequate strength.
(d) Barriers of substantial construction shall be securely and permanently fixed across
any doorway or gateway in a building
Atomic Energy Factory Rules, 1996
91
Rule 56
or in a wall which conceals an approaching train from view, between the building
and the tracks as prescribed in clause (a) of sub-rule (3).
(e) Where tracks are carried on a gantry or other elevation, a safe footway or footways
with hand rails and toe-boards shall be provided at all positions where persons
work or pass on foot; and where there is an opening in the stage of an elevated
track for the dropping of material to a lower level, the position shall be adequately
fenced or the opening itself provided with a grill through which a person cannot
fall.
(f) All point levers shall have their movements parallel to, not across, the direction of
the track.
(g) All loading platforms which are more than 60 cm. above the level of the ground
on which the track is laid and more than 15 m. in length, shall be provided with
stops at intervals not greater than 15 m. apart to enable the platform to be easily
mounted from the track.
(h) Turn tables on plant railways shall be provided with locking devices which will
prevent the tables from turning while locomotives or wagons are being run on or
off the tables.
(i) Workers shall be prohibited from passing under, between or above railway
wagons.
(17) Crossings.-
(a) At all crossings of a track with a road or walkway, danger or crossing signs and
wherever reasonably practicable, blinking lights or alarm lights shall be provided.
At all important crossings, manned gates or barriers or watchmen shall be
provided. Swinging gates and barriers shall be secured against inadvertent
opening or closing.
(b) All crossing, warning signs, gate and barriers shall be illuminated during hours of
darkness.
(18) Duties of drivers and shunters.- It shall be the duty of every driver of a locomotive, or a
shunter including a shunting jamadar, to report without delay to their superior any defect
in permanent way, locomotive or rolling stock.
(19) The Competent Authority may by an order in writing exempt a factory or part of it from
all or any of the provisions of this rule to such extent and on such conditions as it deems
necessary.
Atomic Energy Factory Rules, 1996
92
Rules 57-59
Previous and next
Questions people ask
Is rule 56 of Atomic Energy (Factories) Rules, 1996 still in force?
No repeal of Atomic Energy (Factories) Rules, 1996 is recorded.