Rule 11, Atomic Energy (Factories) Rules, 1996: ILLUMINATION, TEMPERATURE AND VENTILATION

Atomic Energy (Factories) Rules, 1996 - Rule 11

Text of rule 11

ILLUMINATION, TEMPERATURE AND VENTILATION

11. ILLUMINATION, TEMPERATURE AND VENTILATION.- (1) Illumination.- (a) General : Adequate lighting is necessary for all buildings and in the open area so as to- (i) promote work and other activities carried out in the area; (ii) promote safety of the people; and (iii) create a pleasing environment conducive for feeling of well-being. (b) Adequate lighting will be achieved by,- Atomic Energy Factory Rules, 1996 8 Rules 11-11(Tab.) (i) planning of brightness in relation to task itself, immediate background of the task and the general surrounding; (ii) avoiding glare produced by excessive contrast or abrupt and large change in brightness; and (iii) planning of lighting for movement about a building and around. (c) The recommended values of illumination for different locations is given in the Table below: TABLE Sr.No. Visual Tasks Illumination (Lux) 1. Industrial Buildings & Process (a) General Factory Areas 100-150 -canteens, cloakrooms, entrances corridors, stairs (b) Factory- outside Areas -Stockyards, main entrances 20 (c) Assembly, Inspection, Wood working, Welding & Soldering, Machine & Fitting Shops, (i) Rough Work - Frame assembly 150 (ii) Medium Work - Assembly of parts 300 (iii) Fine Work - Electronic assembly, 700 inspection (iv) Very Fine Work - Assembly of 1500 precision parts, optical aids to be provided. (v) Very Precise Work 3000 (d) Boiler Houses (i) Coal & ash handling 100 (ii) Boiler rooms-operating area 100 (iii) Boiler rooms- other areas 20-50 (iv) Outdoor plants 150 Atomic Energy Factory Rules, 1996 9 Rule 11(Tab.) (e) Chemical Works (i) Hand furnace, boiling tanks, 150 driers, evaporators etc. (ii) Controls, gauges, valves etc. 100 (Supplementary lighting for viewing) (iii) Control rooms 200-300 (f) Electricity Generating Station (indoor ) (i) Turbine halls 200 (ii) Auxiliary equipment areas 100 (iii) Boiler houses 70-100 (iv) Boiler house & Turbine house 100 (v) Basement areas 70 (vi) Conveyer areas 70-100 (vii) Control rooms 200-300 (viii) Nuclear reactors & steam 150-200 generating plants (g) Engraving 1000 (h) Foundries (i) Charging floors, tumbling etc. 150 (ii) Fine moulding, core making & 300 inspection (iii) Repairs 300 (i) Garages (i) Parking areas 70 (ii) Washing, polishing etc. 150 (iii) Repairs 300 (j) Gauge & Tool room 700 (Supplementary lighting if required) Atomic Energy Factory Rules, 1996 10 Rule 11(Tab.) (k) Laboratories & Test Rooms (i) General Labs & balance rooms 300 (ii) Electronic & Instrument Labs 450 (l) Laundries, Dry cleaning & ironing 200-300 (m) Paint Shops & Spraying Booths (i) Dipping, rubbing 150-300 (ii) Fine painting & retouching 450-700 (n) Plating Shops (i) Vat & baths 150 (ii) Final buffing & polishing Special lighting (o) Structural Steel Fabrication Plants (i) General 150 (ii) Marking off 300 (p) Libraries (i) Shelves 70-150 (ii) Reading rooms 150-700 (iii) Cataloguing, sorting 150-300 (iv) Book binding etc. 300-700 (q) Offices (i) Entrance & Reception 150 (ii) Conference rooms & Gen. office 30 (iii) Drawing offices 300-450 (iv) Corridors & Lifts 70 (v) Stairs, Lift landing 100-150 (vi) Telephone exchanges 150-200 Atomic Energy Factory Rules, 1996 11 Rule 11(Tab.) (r) Hospitals (i) General & Wards 150 (ii) Operating Theatres General 300 (iii) Operation table Special lighting (iv) Laboratories 300 (v) Radiological rooms 100 (vi) Other areas 100-300 (s) Restaurants (i) Dining room tables 100 (ii) Self service counters 300 (iii) Kitchen 200 (iv) Cloak room & toilets 100 (2) Temperature.- It is essential to provide such temperature in work environment so that workers can be exposed to it repeatedly without adverse health effects. The nature of work can be light , moderate or heavy and the corresponding heat loads for the type of work are 200, 200-350 & 350-500 K Cal/hr. The heat stress is measured in terms of Wet Bulb Globe Temperature (WBGT) Index.* (* Note - on page 12) The permissible WBGT index in degrees Celsius is given in the following WBGT Table. WBGT TABLE Work Load Work-Rest Regimen in each hour Light Moderate Heavy Continuous Work 30.0 26.7 25.0 75% Work - 25% Rest 30.6 28.0 25.9 50% Work - 50% Rest 31.4 29.4 27.9 25% Work - 75% Rest 32.2 31.1 30.0 The Competent Authority shall specify the optimum working temperature & humidity and also the rest periods for specific factories & jobs. Atomic Energy Factory Rules, 1996 12 Rule 11(Tab.) (3) Ventilation.- Ventilation shall be provided in buildings to supply fresh air for respiration & to dilute inside air to prevent vitiation by body odours & to remove any other products of combustion or other air contaminants. Contaminants from concentrated sources such as smoke, heat & fumes shall be collected separately by local exhaust ventilation. The recommended air changes per hour for various areas is given in the Table below: TABLE Area Air Changes/hour Factories 3 - 6 Dining Hall 12 - 15 Garages 12 – 15 Kitchen 6 - 9 Laboratories 3 – 6 Offices 3 – 6 Bathrooms & Toilets 6 - 12 Provided that the competent authority may relax the requirements regarding the number of air changes if it is satisfied that having regard to the location of the factory, orientation of the workroom, prevailing winds, roof height and the nature of manufacturing process carried on, sufficient supply of fresh air into the workroom is afforded during most part of the working time: Provided further that in the regions where in summer (15th March-15th July) dry-bulb temperatures of outside air in the shade during most part of the day exceed 35 degrees Celsius and simultaneous wet-bulb temperatures are 25 degrees Celsius or below and in the opinion of the Inspector the manufacturing process carried on in the workroom of a factory permits thermal environments with relative humidity of 50% or more, the Inspector may serve on the manager of the factory an order to have sufficient supply of outside air for ventilation cooled by -------------------------------------------- * (a) Outdoors with Solar load (b) Indoor or Outdoor without Solar load WBGT = 0.7NWB + 0.2GT + 0.1DB WBGT = 0.7 NWB + 0.3GT Where NWB = Natural Wet Bulb Temperature DB = Dry Bulb Temperature GT = Globe Thermometer Temperature Atomic Energy Factory Rules, 1996 13 Rules 11(Tab.)-16 passing it through water sprays either by means of unit type of evaporative air coolers(desert coolers) or, where supply of outside air is provided by mechanical means through ducts in a plenum system, by means of central air washing plants.

Previous and next

All provisions of Atomic Energy (Factories) Rules, 1996

Questions people ask

Is rule 11 of Atomic Energy (Factories) Rules, 1996 still in force?

No repeal of Atomic Energy (Factories) Rules, 1996 is recorded.