Project Imports Regulations, 1986 (PIR) - Instructions - Circular No.22/2011-Customs, dated 4.5.11
Circular - The Customs Act, 1962
- Kind: Circular
- Under: The Customs Act, 1962
Text of this circular
Circular No.22/2011-Customs
F.No.528/38/2008-Cus.(TU)
Government of India
Ministry of Finance
Department of Revenue
Central Board of Excise and Customs
227-B, North Block.
New Delhi-110001.
4th May, 2011.
To
All Chief Commissioners of Customs / Customs (Prev).
All Chief Commissioners of Customs & Central Excise.
All Commissioners of Customs / Customs (Prev).
All Commissioners of Customs (Appeals).
All Commissioners of Customs & Central Excise.
All Commissioners of Customs & Central Excise (Appeals).
All Directors General under CBEC.
Subject: Project Imports Regulations, 1986 (PIR) - Instructions - regarding.
***
Sir / Madam,
Attention is invited to the provisions of Project Imports Regulations, 1986 (PIR) and
various circulars and instructions issued by the Board on the above subject from time to time.
2. The Comptroller & Auditor General of India (C&AG) had conducted a review of the
working of 'Project Imports' scheme with a view to ascertaining the level of compliance,
effectiveness of internal control and whether finalization has been done by field formations
within a reasonable time frame. The audit review has revealed some systemic as well as
compliance weaknesses relating to grant of project imports benefits and finalization of project
imports cases. The C&AG has taken a serious view on the weak monitoring of the Project
Imports and on the substantial delay in finalization of Project Imports as detailed in their
Performance Audit Report No. PA 24 of 2009-10. In the light of various shortcomings
pointed out in their report, the C&AG has recommended for a comprehensive review of the
working of the scheme including the internal control and monitoring mechanism in vogue
which govern the project imports, and to further strengthen this mechanism.
3.1. The matter has been examined and the recommendations made by C&AG have been
carefully gone through by the Board. One of the recommendations made by C&AG is that the
Government should fix a realistic time frame for finalization of assessments of project import
cases after submission of the requisite documents by the importers to ensure that there is no
loss of revenue. In this regard, it has been decided by the Board that finalization of
assessments under Project imports should completed within a period of 60 days from the date
of submission of required documents by the importer. However, in exceptional circumstances
where it is not possible to complete the finalization within the time limit for justifiable
reasons, the time limit may be extended by the jurisdictional Commissioner of Customs for
such further period as may be decided by him and for the reasons to be recorded in writing.
3.2. It may also be recalled that as per Board's Circular No.12/2001-Customs dated
1.3.2011 issued from File No.334/3/2011-TRU, the field formations were advised not to
renew the bank guarantee in respect of project imports, on completion of a period of six
months from the date of submission of necessary documents from the jurisdictional Central
Excise authority or any other specified authority, as proof of utilization / installation of goods
for the finalization of the contract. It is hereby clarified that the above said relaxation is
applicable, only if all the required documents including certificate for installation of imported
goods at the Plant/ Project site, utilization of imported goods in the manufacture of declared
goods etc. are submitted up to the satisfaction of proper officer for finalisation of contract.
The Commissioner shall therefore ensure that the aforesaid time limit for finalization of
Project Imports under PIR, 1986 is adhered to in all cases, so that such finalization is
completed within the validity period of the bank guarantee in order to ensure that the
government revenue is safeguarded. However, in cases where the importers have not
submitted the requisite documents in time, it may be ensured that the bank guarantees are
kept alive until finalization of project imports so that resultant delay does not adversely affect
the interests of revenue.
4. It has also been recommended by C&AG that in order to improve compliance, penal
provisions may be invoked for delay in submission of reconciliation statements and other
requisite documents by importers. In this regard, you may refer to the Regulation 7 of PIR,
1986, which stipulates that importer shall submit a statement indicating details of goods to be
imported together with necessary documents as proof regarding the value and quantity of the
goods imported within three months from the date of clearance of the last consignment along
with any other documents that may be required by the proper officer for finalization of the
Project Imports cases. While the provisions contained in the Regulations are explicit, it has
been brought to the notice of the Board that there are a large number of cases where project
imports have not been finalized on account of non-submission of Statement by importers
which indicate that the implementation of these provisions has been far from satisfactory. In
order to address this issue and to deter the importers from non-submission or delayed
submission of relevant documents, the Commissioners should ensure that in cases where the
requisite Statement / documents under Regulation 7 of PIR, 1986 is not submitted in time or
submitted incomplete, then necessary action for enforcing bond / undertaking, cash security/
bank guarantees executed in this regard, issue of notice for demand of duty, penalty for non-
compliance with the provisions of the Regulations may be initiated against the importer. The
adjudicating authority is expected to appreciate the evidence on record including documents
submitted, if any, to arrive at a decision whether duty is to be confirmed and / or penalty
imposed.
5. In respect of goods cleared under Release Advice (RA), at ports other than the port
where the contract for project imports is registered, it has been reported by field formations
that provisionally assessed Bills of Entry are not finalized expeditiously, causing delay in
finalization of Project Imports. It has, therefore, been decided that importer and his Custom
House Agent should ensure that the provisionally assessed Bills of Entry for the imported
goods at the ports other than the port of registration of project imports are finally assessed
and audited at the respective ports, and should be submitted along with the documents
submitted for finalization of Project Imports. In these cases the concerned Commissioner
should ensure that such Bills of Entry are finalized without undue delay.
6. In terms of the provisions of Regulation 7 of PIR, 1986 read with Board's instructions
for finalization of project imports, the importer is also required to submit a certificate from a
registered Chartered Engineer certifying the installation of imported items of machinery
along with other documents. In this regard, all importers may be advised to produce this
document without any delay so as to ensure timely finalization of Project Imports. Further, in
order to ensure that the imported goods have actually been used for the projects for which
goods have been imported, Plant Site Verification (PSV) is required to be done in cases
where value of project exceeds Rs. 1 crore and in other cases at least 10% of the project
imports registered will be subject to such plant verification. All the relevant particulars of the
contract giving complete details of the goods imported shall be communicated to the
jurisdictional Central Excise Office to confirm whether the same have been installed at the
registered plant site in time. It has been decided by Board that jurisdictional Central Excise
Commissionerate should ensure that Plant Site Verification, where ever applicable, is
completed within 15 days of submission of relevant documents by the importers. However,
in cases of Government Departments and Public Sector Undertakings, the requirement of
PSV under project imports can be fulfilled by means of issuing appropriate Certificate by the
Head of PSU / Government Undertaking in the rank of Chairman / Executive Director.
7. On the recommendation of C&AG for developing appropriate accounting and
monitoring modules and integrating these with the EDI system to facilitate effective
monitoring of project imports, the matter has been taken up with the Directorate General of
Systems for further action. However, in the meantime the existing facility for processing the
Bill of Entry, Bond module system under Customs EDI System shall be followed so as to
monitor the validity of bank guarantees, bonds and to ensure that they are renewed
periodically. Further, proper records of the Contracts registered under Project Imports along
with requisite particulars, amendments to contracts, if any, as required under Regulation 5 of
PIR shall be maintained by the respective Custom Houses for the purpose of monitoring.
8. The C&AG has further recommended that the Board should strengthen the internal
control and monitoring mechanism in respect of Project Imports to reduce the risk of
irregularities. In order to ensure compliance of PIR, 1986 and to provide an institutional
mechanism to monitor the pendency of project imports on a monthly basis, the Board hereby
further directs that the concerned Commissioner of Customs should monitor the pendency of
project imports cases and submit a monthly report to the Chief Commissioner of Customs in
charge of the Zone, in the prescribed format enclosed along with this circular as
in Annexure-I. The Chief Commissioner of Customs will monitor the pendency and send a
quarterly consolidated report of the Zone by 15th of next month to the Directorate General of
Inspection (Customs & Central Excise), New Delhi in prescribed format as in Annexure-II.
The DGIC&CE will in turn monitor the pendency at All India level, in centralized manner
and will report to the Board on a quarterly basis about the progress made in finalization of
project imports, trend of compliance etc. and suggest corrective measures to be taken, if any.
9. Board's Circular No.12/2011-Customs dated 1.3.2011 stands modified to the above
extent.
10. These instructions should be brought to the notice of all the concerned by way of
issuance of instructions / trade notice.
11. Difficulty faced, if any, may be brought to the immediate notice of the Board.
Yours faithfully,
( R. P. Singh )
Director (Customs)
Encl: As stated above.
ANNEXURE - I
Chief Commissioner Customs (Zone)
Pending Project Finalization Report
Sl.No. Project
Registration
No. & Date
Name of
Importer
Value of
the Project
registered
Security
Deposit /
Bank
Guarantee
amount
taken
Date of
submission of
reconciliation
statement
Action
Taken
Estimated
period / time
required for
finalisation
1.
2.
3.
4.
5.
6.
7.
ANNEXURE - II
Chief Commissioner Customs (Zone)
Pending Project Finalization Report
Sl.No. Year Total no.
of Project
contract
registered
No. of Project
contracts
where last
consignment
is cleared
No. of
project
contracts
where
documents
are
submitted
No. of project
contracts where
documents are
not submitted
and
adjudication
proceedings
started
No. of project
contracts where
documents are
not submitted
and
adjudication
proceedings not
started.
Reasons
for
no
action
1.
2.
3.
4.
5.
6.
7.