Rule 9, The National Highways Rules, 1957: Inspection of works
The National Highways Rules, 1957 - Rule 9
Text of rule 9
Inspection of works
9. Inspection of works—The Consulting Engineer to the Government of
India (Road Development) or any officer authorised by him in this behalf may
62 The National Highways Rules, 1957
inspect at any time any approved work in progress or completed. A report of
every such inspection Shall be submitted to the Central Government.
L[10. Utilisation of space beneath the road, overbridges or flyovers.—The
Central Government, where it deems tit, may accord permission to the State
Government or the Government of a Union Territory, as the case may be, for
utilisation of space beneath the road, overbridges or flyovers on national
highways for which an yearly licence tee which shall be either——
(i) a percentage of capital cost; consisting of the cost of land and the cost,
if any, incurred by the Central Government for covering or enclosing
the space beneath the approach spans of road, overbriclges or flyovers
and for providing sanitary, water supply and electric installations,
equal to such rate of interest as may from time to time be fixed by the
President under FR 45A plus an addition for house or property tax, if
any, payable by Government in respect of the covered space and for
maintenance and repairs of the covered structure, or
(ii) six per cent. per annum of such capital cost, whichever is less, shall
be fixed and levied on the terms and conditions as may be laid down
by the Central Government in this respect. The rate of licence fee to be
levied as above, shall be subject to revision after every five years to take
into account any change in the market value of the land]
2[THE SCHEDULE
[Sue rule 3(2)]
Conditions for the issue of technical approval and financial sanction to plan and
estimate for execution of any original work on a national highway costing an amount
not exceeding Rs. 10 lakhs by the executive agency concerned.
(l) The executive agency shall forward to the Central Goirernment for approval
rough cost estimates along with detailed information in respect of the particulars given
below according to the tentative details given in the annual plan works programme
for a particular year, within a period of 3 months after the receipt of annual plan
works programme for the year:
(a Proposal in brief with a rough plan of the area in which the work is to be
executed.
(b) Exlent of preliminary survey and investigation done.
(c) Broad features showing the existing position and the improvements desired.
(d) Traffic data,
L
(e) Duration of execution.
(f) Phasing of expenditure and also physical performance.
(3) Rough quantities and estimated cost under broad headings such as:
(1) Road works (2) Bridge works
Land acquisition; earth work; Foundation, superstructure,
road material. guide bunds, etc.
1. Added by 5,0. 699 (E), dated 17th September, 1993 (WILL 17-91993).
2. Ins. by 5.0. 680 (E), dated 15th October, 1076.
The National Highways Rules, 1957 63
(h) Detailed specification.
(i) List of equipments required for speedy execution of the work.
(1) Alignment plan and longitudinal section in case of roads; hydraulic data and
outline deSigns of structures in case of bridges.
(k) Particulars for comparison of the similar works carried out in the same
region.
(1) Special features, if any.
(2) (a) Permissible )ob sizes shall be regulated according to description given in the
annual I’lan works programme mentioned under condition (1) and the work shall not
be split up.
(b) in the case of items saving lump sum provision (such as improvement of
geometrics, stabilising, slipping reaches, raising roads in submersible sections, each
specific location supported by requisite details shall be treated incliVidually.
(3) Technical approval and financial sanction shall be accorded only in respect of
such items of work for which specific provision has been made in the budget during
the year for the indivtdual work on the basis of the approval given under condition
(1)-
(4) While sanctioning detailed estimates, the executive agency shall ensure that the
rough cost estimate for the work appearing in the budget estimates accepted by the
Central Government for presentation to Parliament is not exceeded by more than 15
per cent. or the total cost of detailed estimate to be sanctioned by that agency, in no
case exceeds Rs. 10 lakhs, whichever is less.
(5) Abstract of cost of sanctioned detailed estimates in all cases shall be submitted
by the executive agency in respect of the works sanctioned by that agency and in the
case of bridge estimates, in addition a general outline drawing shall also be submitted.
Abstract of cost of sanctioned detailed estimates shall give justification for excess, if any,
referred to under condition (4).
((3) Progress reports in respect of all works sanctioned by the executive agency
shall be submitted to the Central Government, in such form and at such periodicity
as may be required by the Central Government from time to time.
(7) Technical approval and financial sanction~to plans and estimates for execution
of any original work on a national highway shall be accorded by the executive agency
only after the approval of an officer of the rank of Chief Engineer or Additional Chief
Engineer or Principal Engineer in charge of national highway works has been obtained.
(8) In case the executive agency considers it necessary to accord technical approval
and financial sanction after the approval of officers of the rank of Superintending
Engineers possessing reqtiisite technical, administrative and financial powers, the prior
approval of the Central Government shall be obtained but in all such cases they shall
have to consult the Regional Officer concerned at the Ministry of the Central
Government dealing with the national highways.
(9) 1n the case of projects, concerning byepasses, realignment and improvement of
geometrics as also designs for bridges of length up to 100 metres and of individual
spans not exceeding 30 metres even where cost may be within Rs, 10.00 lakhs, no work
shall be sanctioned by the executive agency without prior approval of the Regional
Officer concerned of the Ministry in the Central Government dealing with national
highways.
(10) in the matters relating to technical approval and financial sanction, the
following procedure shall be followed, namely:—
The National Highways Rules, 1957
(i) In case of the works where standards and designs adopted in the estimates
are in accordance with the Indian Roads Congress Code and specifications
and any other relevant instructions, guidelines, standard bridge designs, etc,
issued by the Central Government from time to time, copies of the sanctions
accorded by the executive agency shall invariably be endorsed to the
Regional Officers concerned of the Ministry in the Central Government
dealing with national highways along with complete copy of the estimate so
that even after sanction, they could examine the matter and bring to the
notice of executive agency deviations from such Code, specifications,
instructions, guidelines, standard bridge designs, if any,
(ii) Where for any work, deViations, from approved standards, specifications,
instructions, guidelines issued by the Central Government have to be made
clue to local conditions, nu work shall be sanctioned by any executive agency
unless a complete copy of the estimate is furnished to the Regional Officer
concerned of the Ministry in the Central Government dealing with national
highways and his approval has been obtained in accordance With the general
instructions issued by them from time to time governing the disposal of such
cases. A brief mention of these deViations shall also be made by the executive
agency in the abstract estimates to be sent to the Central Government
quoting the reference of approval of the Regional Officer concerned.
(iii) in all other cases where proposed deviations do not fit in With the general
instructions issued by the Central Government or are not necessitated due
to local conditions, technical and financial sanction thereto may be accorded
by the executive agency with the prior approval of the Central Government
on a reference being made in this behalf along with a copy of the detailed
estimate through the Regional Officer of the Ministry of the Central
Government dealing With the national highways who shall forward the same
to the Central Government with his comments thereon.
(iv) After the budget estimates have been accepted by the Central Government,
the funds likely to be available for the work shall be intimated to the
executive agency concerned. Work-wise allotment of funds shall be made by
the Central Government and the same shall also be communicated to the
executive agency concerned for further necessary action as soon as the
budget is passed by the Parliament. Sanction for entering into financial
commitments may be accorded by the executive agency only after the
budget is passed by the Parliament and the same is intimated to the
executive agency. All other actions including technical sanction to the project,
calling and receipt of tenders, negotiation for their settlement, etc, may,
however, be taken by the executive agency as soon as the acceptance of the
budget estimate by the Central Government has been intimated to it.