Rule 5, The National Highways Rules, 1957: Revised detailed estimate
The National Highways Rules, 1957 - Rule 5
Text of rule 5
Revised detailed estimate
1[5. Revised detailed estimate.——Where the expenditure upon any original
work on a national highway for the detailed estimate of the cost for which the
Central Government has accorded technical approval and financial sanction,
under sub—rule (1) of rule 3, is likely at any time to exceed, or exceeds, the
amount of such estimate by more than fifteen per cent. thereof or by a sum of
one crore rupees, whichever is less, the executive agency shall forward a revised
detailed estimate of the cost for such work to the Central Government in such
form as that Government may specify in this behalf, and the. Central Government
may accord technical approval and financial sanction to the revised detailed
estimate subject to such conditions as it may think fit to impose.
(2) Where the expenditure upon any original work on a national highway
to the detailed estimate of the cost for which the executive agency concerned has
accorded technical approval and financial sanction, under sub-rule (2) of rule 3,
is likely at any time to exceed, or exceeds, the amount of such estimate and the
revised cost of the original work, including the excess, is likely at any time to
exceed, or exceeds by more than fifteen per cent of the original estimate or
Rs. 10 lakhs, the executive agency shall forward a revised detailed estimate of
the cost for such work to the Central Government in such form as that
Government may specify and the Central Government may accord technical
approval and financial sanction to such revised estimate subject to such
conditions as it may think fit to impose,
(3) Notwithstanding anything contained in sub~rule (2), where the
expenditure upon any original work on a national highway to the detailed
estimate of the cost for which the executive agency concerned has accorded
The Nationa/ Highways Rules, 1957 61
technical approval and financial sanction, under sub-rule (2) of rule 3, is likely
at any time to exceed, or exceeds, the amount of such estimate and the revised
estimate of the cost for the original work, including the excess is likely at any
time to exceed, or exceeds, by more than fifteen per cent. of the original estimate
but by not more than fifteen per cent. of the rough estimate of the costs for the
original work which the executive agency had submitted to the Central
Government and obtained the approval of that Government, technical approval
and financial sanction to such revised estimate may be accorded by the executive
agency concerned subject to the conditions specified in the Schedule annexed to
these rules:
Provided that the amount of the revised estimate is not likely to exceed, or
does not exceed Rs. 10 lakhs:
Provided further that the excess of expenditure is caused only by routine
factors such as increase in the cost oi labour or material and not due to revision
in the scope or enlargement of the work or specifications already approved.
(4) Where the expenditure upon any original work on a national highway
is likely at any time to exceed, or exceeds, the amount of the estimate of the cost
for such work no funds shall be allotted to the work by the Central Government
in the cases provided for in sub-rule (1), (2) or (3), unless the provisions of those
suberules are complied with except in cases where the Central Government
directs otherwise.
ExplanationiFor the removal of doubts, it is hereby declared that in cases
where the excess of expenditure is less than the percentage or amount specified
in sub-rule (1) or sub—rule (2), it is not necessary to obtain technical approval and
financial sanction of the Central Government for the revised estimate in
accordance with those sub-rules only if the excess of expenditure is caused by
routine factors such as increase in the cost of labour or material and not due to
revision in the scope or enlargement of the work or specifications already
approved]
6. Application for allotment of fundsgAn application for the allotment of
funds for meeting expenditure on any original work on a national highway or
on the maintenance of a national highway during any financial year shall be
made by the executive agency to the Central Government in such form as that
Government may require and the Central Government shall communicate its
decision to the executive agency on such application as soon as possible after
such application is received.