Rule 2, The National Highways Rules, 1957: Definitions
The National Highways Rules, 1957 - Rule 2
Text of rule 2
Definitions
2. Definitions—In these rules, unless the context otherwise requires,—
(a) ”Act” means the National Highways Act, 1956 (48 of 1956);
(b) “approved work” means any original work on a national highway in
respect of which the Central Government has accorded technical
approval and financial sanction;
(c) ”Completion report“ means a report required to be furnished under
rule 8;
(d) “executive agency” means;—
(i) in the case of a Union Territory the Administrator thereof to whom
the functions of the Central Government in relation to the execution
of works pertaining to national highways are delegated under
article 239 of the Constitution; and
2[(ia) in the case of a national highway or part thereof in respect of
which such functions are delegated to the Border Roads
Organisation, the Border Roads Development Board;
(ib) in the case of a national highway or part thereof in respect of
which such functions are delegated to the National Highways
Authority of India;]
(ii) in any other case the State Government to which such functions are
delegated under section 5 of the Act; and
(e) ”progress report“ means a report required to be furnished under rule
“[3. Detailed estimate of the original work—(1) Where the estimate of the
cost for the execution of any original work on a national highway exceeds
Rs. 10 lakhs/ a detailed estimate of the cost for the execution of the work shall
be forwarded by the executive agency to the Central Government in such form
as the Central Government may specify in that behalf and that Government may
accord technical approval and financial sanction to such estimate subject to such
conditions as it may think fit to impose.
(2) Where the estimate of the cost for the execution of any original work on
a national highway does not exceed Rs. 10 lakhs, technical approval and
financial sanction to the plan and estimate for the execution of such work may
be accorded by the executive agency concerned subject to the conditions specified
in the Schedule annexed to these rules.
l. Vidc SRO. 1182, dated ~llh April, 1957.
2. ins, by .R. 417 (E), dalt‘d Illst July, 1998 (w.c.f. 31771998).
3. Subs. by $0. 680 (E), dated 15th October, 1976.
59
60 The Nationa/ Highways Hu/es, 1957
(3) No original work on any national highway shall be undertaken by the
executive agency until technical approval and financial sanction to the estimate
for the execution of the work have been accorded by the Central Government or
the executive agency, as the case may be, except in cases of emergency, such as
flood, earthquake or any other force 'rt’lfljettfl’ which shall be immediately reported
to the authority competent to sanction the estimate and the Audit Officer
concerned indicating the approximate amount of liability involved]