Rule 34, The Rubber Rules,1955: Budget Estimate
The Rubber Rules,1955 - Rule 34
Text of rule 34
Budget Estimate
34. Budget Estimate.-—(1) The Board shall in each year prepare a budget
for the General Fund for the ensuing financial year and shall submit It for the
sanction of the Central Government on or before such date as may be appointed
by that Government.
S E C . 3] THE GAZETTE OF INDIA EXTRAORDINARY 1621
(2) The budget shall be in such form as the Central Government may direct
-and shall include a statement of—
(i) estimated opening balance;
(ii) estimated receipts by way of grant from the Central Government
under sub-section (7) of section 12;
(iii) proposed expenditure classified under the following heads or such
other heads as the Central Government may direct:
(a) Administration
(b) Research
(c) Statistics
(d) Others.
(3) The proposed expenditure under each head shall be further classified
*under the following sub-heads:
(i) Pay of officers,
(ii) Pay of Establishment
(iii) Allowances, Honoraria etc.
(iv) Other charges, contingencies etc.
(4) Supplementary estimates of expenditure shall be submitted for the sanc
tion of the Central Government in such form and on such dates as may be
•directed by it.
Previous and next
Questions people ask
Is rule 34 of the Rubber Rules,1955 still in force?
No repeal of the Rubber Rules,1955 is recorded.