LALITESHWAR PRASAD SAHI versus BATESHWAR PRASAD AND OTHERS
Supreme Court of India | Decided 7 October 1965 | [1966] 2 S.C.R. 63 | 1965 INSC 204
Key facts
- Decided
- 7 October 1965
- Bench
- P.B. GAJENDRAGADKAR*, K.N. WANCHOO*, M. HIDAYATULLAH, J.C. SHAH, S.M. SIKRI
- Bench size
- 5
- Case number
- CIVIL APPEAL No. 211/1965
- Disposal
- Dismissed
- Citation
- [1966] 2 S.C.R. 63
- Neutral citation
- 1965 INSC 204
Text of the judgment
LALITESHWAR PRASAD SAHi
v.
BATESHWAR PRASAD AND OTHERS
October 7, 1965
B
c
[P. B. GAJENDRAGADKAR, C.J., K. N. WANCHOO,
M. HIDAYATULLAH, J. C. SHAH AND S. M. S!KRI, JJ.]
Representation of the People Acr, 1951-S. 7(d)-Contract w;:h Governn1ent not coniplying lV~!h provision of Art. 299 of the ConstiturionNot subsequently ratified by Governn1ent-Whether disqualifies candi·
date.
In an election petition filed by the appellant, the respondent's election
to the Bihar Legislative Assembly was challenged, mainly on the ground.
that he was disqualified under s. 7(d) of the Representation of the
People Act, !951, as he had entered· into a contract with the State
Government which was subsisting on January 14, 1962, i.e. the date fixed
for filing nomination papers.
D
One S bad entered into a contract in 1951 with the State Government
[or certain construction work and the respondent was working as a sub~
contractor under him. As there was delay etc. in the completion of the work
by S, in exercise of a power reserved to the State GovernmenJ. in cl. 3(c)
of the agreement with S, whereby the Government could, under certain
circumstances, make alternative arrangements for the completion of the
work, the Executive Engineer of the Government approached the res-
E
pondent to ascertain if he would complete the work instead.
In a letter
addressed to the Executive Engineers, the respondent offered to do thework on certain terms and this offer was accepted. Thereafter, various
letters were exchanged with the respondent by the S.D.O. and the Executive
Engineer about the progress of the work. However, after most of the
work to be done by the respondent was completed,, S was restc>red as tho
contractor and further correspondence about the \vork done by the res-
F
G
pondent and regarding the payment for it was conducted by the concerned
officers of the State Government with S. The payment for this work remained
outstanding on the date for filing nomination papers in January J 962.
The Election Tribunal allowed the petition and declared the respondents•·
election to be void. But the High Court reversed this decision and held
that the respondent had at all relevant times continued to be a sub-contractor
of S, and that even assuming there was a contract bet\veen the respondent
and the State Government, the alleged contract was void in view of Art.
299 (I) of the Constitution.
On appeal to this Court,
HELD : (per majority)
No contract between the first respondent and the Stale Government
subsi9ted at the relevant time and the respondent was noot disqualified
under s. 7(d).
H
The correspondence in the case clearly disclosed an agreement for th.,.
execution of work between the Ex·zcutive Engineer and itfie respondent,
But the fact that by virtue of cl. 3(e) of the contract with S, the Government could, under certain circumstances,
enter into an agreement
SUPREME COURT REPO!tTS
(1966] 2 S.C.R.
with someone else to do the work, did not dispense with the requirement
.of compilance with !he provisions of Art. 29~. [70 E-F]
A
The evidence on record showed that the State Government had chosen
not to ratify the agreement with the respondent but to consider the original
conract with S as still standing and to treat the respondent as a subcontractor working under S. [73 HJ
The principle in Chatrurbhui Vithaldas Jasani's case ([1954] S.C.R. 817)
that although a contract may not comply with Art. 299, such contract,
being capable of ratification by the Government may still disqualify a
person under s. 7(d), cannot be extended to cover a case where the
Government has in fact not ratified the contract. To hold otherwise would
be to substitute "agreement" for "contract" in s. 7(d) .. A mere agreement entered into in contra;-ention of Art. 299 and in fact not ratified
.cannot be caled a "contract" within s. 7(d). [72 A-BJ
New Marz'ne Coal Co. (Bengal) v. The Union of India A.LR. 1964
S.C. 152; State of W. Bengal v. B. K.. Monda! A.I.R. 1962 S.C. 779;
referred to.
B
c
(per Hidayatullah and Shah JJ., dissenting);
The available evidence clearly supported the case that there was a
directl:Y between the firiJtl respondent and the State for the
exetution of certain construction work and not that the work was done
by the first respondent under a sub-contract from S. The court was only
required to determine whether there was such a contract and \Vas not
concerned with the question whether the contract was enforceable against
the State. [81 G]
oonlrac~
Although the contract was not in the form prescribed under Art. 299.
it was not for that reason unlawful. H was always open to the State,
notwithstanding informality in tho mode of execution of the contract, to
accept liability arising under the terms of the contract. Such a contract,
although not enforceable by action against the Government was still to
be regarded as disqualifying a person under s. 7(d). The first respondent
had performed his part of the contract but no payment had been made
to him. There was therefore a subsisting contract within the rrleaning of
s. 7(d). [79 A; 80 A-B; 91 BJ
Chaturbhuj Vithaldas Jasani's case [1954] S.C.R. 817 applied;
Bhikrai Jaipuria v. Union of India [1962] 2 S.C.R. 830 referred to.
D
E
F
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 211 of
1965.
Appeal by special leave from the judgment and decree dated
the April 25, 1964 of tho Patna High Court in Election Appeal
No. 11 of 1963.
G
Purshottam Trikumdas and D. Goburdnun, for the appellant.
Sarjoo Prasad, Nagendra Kumar Roy and K. K. Sinha, for the
respondent No. 1.
The Judgment of GAJENDRAGADKAR C.J., WANCHOO and H
SIKRI, JJ. was delivered by SIKRI J. The dissenting Opinion of
HIDAYATUI.LA!I and SHAH, JJ. was delivered by SHAH J.
LALITESHWAR V. BATESHWAR
(Sikri, J.)
65
Sikri J. This is an appeal by certificate granted by the High
Court of Patna, directed against the judgment of the said High
Court reversing the decision of the Election Tribunal, Muzaffarpur.
This appeal arises out of the election of the respondent, Shri
Bateshwar Prasad, to the Bihar Legislative Assembly from Lal
Ganj North Constituency. The appellant was one of the candiB dates. He filed an election petition No. 133 of 1962, alleging
inter a/ia that the election of respondent No. l, Shri Bateshwar
Prasad, was void as he was disqualified under s. 7(d) of the
Representation of the People Act, 1951, hereinafter referred to as
the Act. His complaint was that respondent No. 1 had entered
into various contracts with the Government and that these conc tracts were subsisting on January 14, 1962, the date fixed for
filing nomination papers. The Election Tribunal, after reviewing
both oral and documentary evidence, held that the respondent
had entered into contracts to do Mosaic flooring work in the
Rajendra Surgical Block of Patna Medical Hospital and that
these were subsisting on the date of the nomination, viz., January
D
14, 1962." The Election Tribunal further held that by virtue of
cl. 3 ( c) of the conditions embodied in the agreement, Ex. 'D',
it was not at a!J necessary for the Public Works Department to
have entered into a contract with the respondent's company,
called the Patna Flooring Company. In the result, the Election
E Tribunal declared the election of Respondent No. 1 to the Bihar
Legislative Assembly from the Lal Ganj North Constituency as
void, but refused the prayer of the petitioner before it to be
declared elected.
A
F
Both sides appealed to the High Court but we are only concerned with the election appeal No. 11 of 1963, filed by Bateshwar
Prasad, the returned candidate. Before the High Court three
points were taken :
G
( 1) The appellant was not a contractor under the
State Government for the mosaic work to be done in
the Rajendra Surgical Block, but that at all relevant
times, he was a sub-contractor under one G. P. Saxeaa,
who was a contractor under the State Government for
the purpose;
H
(2) Assuming that there was a contract within the
meaning of section 7 ( d) of the Representation of the
People Act, 1951 (Act 43 of 1951), sometime, there
was no subsisting contract when the appellant had filed
nomination paper in 1962 ~nd thereafter;
66
SUPREME
COURT
REPORTS
[1966] 2 S.C.R.
( 3) Assuming again that there was a contract
between the appellant and the State Government sometime, the contract alleged was void, in view of Article
299 ( 1) of the Constitution of India, so that the Tribunal
could not have held that the appellant was disqualified
to be chosen as a candidate.
The High Court reviewed the entire evidence and came to the
conclusion on point No. 1 above that the appellant was not a contractor under the State Govermnent but continued to be a subcontractor under Saxena for mosaic work. It also differed from
the Election Tribunal on the interpretation of cl. 3 ( c) of Ex. 'D'.
On the second point, the High Court felt that in view of its decision on the first point, the question was of mere academic interest
and there might be substance in the argument of the learned
counsel for the respondent that this question ought not to be
allowed to be raised at this stage. Regarding the third point, the
High Court held that Chaturbhuj's case ( Chatturbhuj Vithaldas
Jasani v. Moreshwar Parashram)(') was distinguishable because
in the instant case the State Government had not accepted the
performance of the contract by the appellant. It further held that
since the decision in Chaturbhuj's(') case the law had been
amended by the amendment of s. 7 ( d) and the effect of the
amendment was "that the candidate shall be disqualified for being
chosen as a member only if there still exists, in substance, at the
relevant time, a valid and binding contract between him and the
appropriate government." The High Court further observed that
"it is difficult to accept the contention of the learned counsel for
the respondent that a transaction may be void under the Contract
Act, but its factual existence may still be a disqualification under
present section 7 ( d) ." In conclnsion, the High Court held that
Bateshwar Prasad had not incurred a disqualification under s. 7 (d)
of the Act, and accordingly set aside the judgment and order of
the Election Tribunal.
A
B
C
D·
E
F
Mr. Purshottam, the learned counsel for the appellant, has G
urged before us that the High Court was wrong in holding that
the amendment had made any change in the law on the question
whether the contract which is void under art. 299 of the Constitution is or is not a contract within s. 7 ( d) of the Act. He says that
the reasoning of the decision of this Court in Chatturbhuj's(')
case still holds the field. He then says that the High Court came H
to a wrong conclusion on the question of fact in this case, namely,
(I) (1954] S.C.R. 817.
LALITESHWAR V. BATESHWAR (Sikri,
A
B
J.)
67
whether the contracts subsisted or not at the relevant date, and
that this Court should reverse the finding even though it is a finding of fact. Mr. Sarjoo Prasad, the learned counsel for the
respondent, controverts this point and he urges that this Court
should not go into the question of fact. On the question of law,
he says that the present s. 7 ( d) is quite difierent from the old
s. 7 ( d) and that the Supreme Court decision cannot be applied
to the wording of the present section.
Coming to the law point, it is necessary to set out the old
and the new statutory provisions, and these are as under :
c
D
E
F
G
H
"7. A person shall be disqualified for being chosen
as, and for being, a member of either House of Parliament or of the Legislative Assembly or Legislative Council of a State ....
(ct) if, whether by himself or by any person or body
of persons in trust for him or for his benefit or on his
account, he has any share of interest in a contract for
the supply of goods to, or for the execution of any works
or the performance of any services undertaken by the
appropriate Government;"
As amended
"7. A person shall be disqualified for being chosen
as, and for being, a member of either House of Parliament or of the Legislative Assembly or Legislative
Council of a State ....
(d) if there subsists a contract entered into in the
course of his trade or business by him with the appropriate Government for the supply of goods to, or for the
execution of any works undertaken by, that Government;".
Comparing the old section and the new section. there is no
doubt that there has been a change in the wording. One change
is quite clear and that is that the contract now must have been
entered in the course of his trade or business by a person with the
appropriate government. Previously it need not have been a
contract in the course of trade or business. The words were much
wider and included any contract entered into for his benefit or on
his own account or a contract in which he had any share or
intcres·r. To this extent the Legislature has clearly narrowed the
area of this disqualification. But is Mr. Sarjoo Prasad right in
contending that the change has gone further and that it only
"68
SUPREME
COURT REPORTS
[1966] 2 S.C.R.
embraces executory contracts but not executed contracts ? In A
our opinion, the Legislature has made no change in this respect
for under the old provision it was also necessary for a contract
to have subsisted at the relevant time. This Court had in Chaturbhuj's(') case included both executed and executory contracts
within the provision of s. 7 ( d) and had refused to follow the
English rulings to the contrary. We cannot go into the question B
whether this was rightly done or not for we are bound by that
-decision. Accordingly, following Chatturbhuj's(') case we hold
that a contract for the supply of goods or for the execution of any
works or the performance of any services undertaken does not
·cease to subsist only because the goods had been supplied or work C
had been executed or services performed. It continues to subsist
·till payment is made and the contract is fully discharged by performance on both sides.
But whether Chatturbhuj's(') case applies when a void con. tract has not been accepted or ratified by the Government, we
·will consider presently. Mr. Purshottam next contends that the D
respondent entered into two contracts and they were subsisting at
the date of the nomination as the respondent had not been paid for
his work and as a matter of fact a suit is pending against the
Government for recovery of the money. He has taken us through
the documentary evidence and it is now necessary to deal with it.
The documentary evidence may be conveniently divided into two E
groups. The first group relates to documents bearing on the
formation of the alleged contract. It appears that one G. P.
Saxena had entered into a contract, Ex. D., for the construction of
a surgical block in the Patna Medical College compound, Patna,
and this contract was entered into in 1951, and the respondent was F
working as a sub-contractor under him. It further appears that
there were some disputes between Saxena and the Public Works
Department and he was not completing the work in time or to
their satisfaction. Consequently, the Sub-Divisional Officer
enquired from the Patna Flooring Company whether they would
be willing to complete the work. Patna Flooring Company, on G
April 17, 1955, wrote to the Executive Engineer, through the
Sub-Divisional Officer, and gave their quotations and terms and
condiiions. It may be noted here that these terms were different
from the terms under which Saxena had taken the contract. This
is an important fact and it is necessary to bear this in mind. On
April 25, 1955, the Sub-Divisional Officer forwarded this letter H
to the Executive Engineer with the remarks that "the contractor
_(I) [1954] S.C.R. 817.
LALITESHWAR V. BATESHWAR (Sikri,
J.)
69
A is being asked to start work immediately as per your orders."
The Executive Engineer noted on this letter as follows : "It is
hoped necessary notice has been given by you to the defaulting
contractor." The S.D.0. noted that "the contractor had already
been served with a notice and a copy to your office vide T.O.
No. 497, dated 20th April, 1955. The ·P.F.C. has been ordered
B to start work and a copy of that submitted to you vide T.O. No.
504, dated 20th April, 1965". On April 20, 1955, the SubDivisional Officer wrote to the Patna Flooring Company to "start
immediately the remaining mosaic floor and dado work in the
R. S. Block and finish the work completely within a fortnight as
promised by you." He endorsed a copy of this letter to the
Executive Engineer. He also sent a notice to Saxena informing
him that as he had failed to do (in spite of repeated asking) the
remaining mosaic work of floor and dado in Surgical Block, the
remaining work was being got done by other agency and the cost
would be recovered from him. He endorsed a copy of this to
D the Executive Engineer noting that the remaining work was being
done by the Patna Flooring Company, as instructed by him. On
May 13, 1955, the Executive Engineer warned Patna Flooring
Company to finish the work within the stipulated time and that
no extension of time wonld be granted if the work would be left
unfinished. On May 23, 1955, the Sub-Divisional Officer again
wrote
to Patna Flooring Company saying that necessary instrucE
tions regarding slope etc. had already been given at the site, that
there was no canse for delay in work and asked them to push up
the progress of the work as it was a top priority work. It appears
that by May 25, 1955, 90% of the work had been done and the
Patna Flooring Company wrote to the Sub-Divisional Officer
F requesting that the S.0. Incharge of the said work be ordered to
submit an on account bill for making payment to them at an
early date.
G
H
Mr. Purshottam contends that on a perusal of the correspondence contained in this group it is quite clear that an oral contract for the construction of work was entered into between the
Executive Engineer and the Patna Flooring Company and that
the High Court had erred in holding that no such contract ever
came into being. He points out that under cl. 3 ( c) of the Contract, Ex. D, the Executive Engineer was entitled to ask the Patna
Flooring Company to do the work. Clause 3 ( c) reads as follows :
"Clause 3.-In any case in which under any clauses
of this contract the contractor shall have rendered himself liable to pay compensation amounting to the whole
SUPREME
70
COURT
REPORTS
[1966] 2 S.C.R.
of his security deposit in the hands of Government
(which whether paid in one sum or deducted by instalments) to Executive Engineer on behalf of the Governor
of Bihar, shall have power to adopt any of the following
courses, as he may deem best suited to the interests of
Government ....
A
B·
( c) To measure up the work of the contractor, and
to take such part of the work of the contract as shall
be unexecuted out of his hands, and to give it to another
contractor to complete, in which case any expenses
which may be incurred in excess of the · sum which
would have been paid to the original contractor if the
whole work had been executed by him (of the amount
of which excess the certificate in writing of the Executive
Engineer shall be final and conclusive) shall be borne
and paid by the original contractor and may be deducted
from any money due to him by Government under the
contract or otherwise, or from his security deposit or
the proceeds of sale thereof, or a sufficient part thereof."
c
D•
We are inclined to agree with Mr. Purshottam that the correspondence in this group clearly discloses an agreement for the
execution of work between the Executive Engineer and the Patna
Flooring Company, and the Election Tribunal was quite right in E
coming to this conclusion. But we may say that the Election
Tribunal was not right in holding that cl. 3 ( c) got rid of art. 299
of the Constitution. Any work which is given in exercise of the
powers under cl. 3 ( c) has also to comply with the provisions of
art. 299 of the Constitution. What the effect of this is we will
consider later.
F·
Mr. Sarjoo Prasad, however, says that assuming that a contnict was entered into, the contract did not subsist at the time of
the nomination because the Government had refused to ratify the
contract given under cl. 3 ( c) and that Chatturbhuj's(') case does
not Jay down that a contract which has not been ratified by the G
Government is a contract within s. 7 ( d) of the Act. It seems
to us that there is a great deal of force in the contention of the
learned counsel. It is truel that this Court has held in a number
of cases, the latest being New Marine Coal Co. (Bengal) v. The
Union of India('), that a contract entered into with the Government in contravention of s. 17 5 ( 3) of the Government of India H
Act, 1935, or art. 299 of the Constitution is void and unenforce(1) [1954] S.C.R. 817.
(2) A.I.R. 1964 S.C. 152.
LALITESHWAR V. BATESHWAR
A
B
D
E
F
(Sikri, J.)
71
able. But in State of West Bengal v. B. K. Monda/(') this Court
distinguished Chatturbhuj's( 2 ) case on the ground that in the latter
case "this Court was dealing with the narrow question as to
whether the impugned contract for the supply of goods would
cease to attract the provisions of s. 7 ( d) of the Representation of
the People Act on the ground that it did not comply with the
provisions of art. 299 (l), and this Court held that notwithstanding
the fact that the contract could not be enforced against the Government it was a contract which fell within the mischief of s. 7 ( d)."
This Court further observed that "all that this Court meant by
the said observation (of Bose J. in Chatturbhuj's( 2 ) case at p. 835,
quoted below) was that the contract made in contravention of
art. 299(1) could be ratified by the Goverm11ent if it was for its
benefit and as such it could not take the case. of the contractor
outside the purview of s. 7 ( d). The contract which is void may
not be capable of ratification, but, since according to the Court
the contract in question could have been ratified it was not void
in that technical sense. That is all that was intended by the
observation in question." But the question arises whether Chatturbhuj's(2) case can be extended to cover a case where the contract
Bose J. observed in Chatturhas in fact not been ratified.
bhuj's(') case as follows :
"In the present case, there can be no doubt that the
Chairman of the Board of Administration acted on
behalf of the Union Government and his authority to
contract in that capacity was not questioned. There can
equally be no doubt that both sides acted in the belief
and on the assumption, which was also the fact, that the
goods were intended for Government purposes, namely,
amenities for the troops. The only flaw is that the con1racts were not in proper form and so, because of thi!
purely technical defect, the principal could not have
been sued. But that is just the kind of case that s. 230
( 3) of the Indian Contract Act is designed to meet. ...
It only means that the principal cannot be sued; but
we take it there would be nothing to prevent ratification,
especially if that was for the benefit of Government.
There is authority for the view that when a Government officer acts in excess of authority Government is
bound if it ratifies the excess : see The Collector of
Masulipatam v. Cavalr,v Venkata Narrainapah (S
M.I.A. 529 at 554) ."
(1) A.I.R. 1962 S.C. 779.
(21 (19541 S.C.R. 817.
72
SUPREME
COURT REPORTS
[1966] 2 S.C.R.
It seems to us that the decision in Chatturbhuj's(.') case cannot A
be extended to cover a case where the Government has in fact
not ratified the contract. If we were to hold that this type of
transaction is covered then we would be giving no effect to the
word "contract" ins. 7(d) and we would be substituting the word
"a,,oreement" for it. The Legislature has not chosen to use the
word "agreement" but has used the word "contract". Therefore, B
a mere agreement entered into in contravention of art. 299 and
in fact not ratified cannot be called a "contract" within s. 7 ( d)
of the Representation of Reople Act.
The question then arises whether the Government did or did
not ratify the oral contract entered into between the Executive C
Engineer and the Patna Flooring Company. In this connection,
Mr. Sarjoo Prasad, relies on a number of documents. The first
document he refers to is Ex. A-2, dated July 12, 1955. The SubDivisional Officer wrote to the Patna Flooring Company as
follows:
))
"It is disappointing to note that in spite of my
repeated askings you have not submitted your final bill
for the mosaic work uptil now. I have been personally
explaining to you the whole position and you promised
to submit your final correct bill on Friday the 8th July,
1955 so that I may ask the contractor Shri G. P. Saxena
E
to pay you off finally and settle your accounts immediately."
It appears that something happened between May 25, 1955 and
July 12, 1955. According to the respondent, what happened
was that Saxena approached the Superintending Engineer and F
the Superintending Engineer ordered that Saxena would continue
to be the contractor as before and no contract would be given to
any firm. The respondent stated this in his evidence as R. W. 32.
It is objected that this is hearsay and this part of the statement is
not admissible. There is some force in this contention and we
omit this part of the statement from consideration. But apart from G
this oral evidence it is quite clear from this letter that something
happened, otherwise it was not necessary to use the words "personally explaining to you the whole position" in this letter, and it
is not understandable why the Patna Flooring Company was being
asked to submit the bill to Saxena. This inference is strengthened
by subsequent correspondence. By letter, dated July 13, 1955, H
Ex. A3, the S.D.0. acknowledged the receipt of the bill and said
(!) [1954] S.C.R. 817.
-
LALITESHWAR V. BATESHWAR
(Sikri, J.)
73.
that he had sent it to Saxena for making settlement. Ex. A-17,
dated July 20, 1955, is significant. The Sub-Divisional Officer
requested Saxena to issue orders to his contractors "to mend and
rectify all the cuttings and damages properly and nicely so that
the building is in a fit condition for handing over on 1-8-1955."
On July 23, 1955, Saxena endorsed it to the Patna Flooring ComJI pany for information and necessary action and with the request
to rectify the defects pointed out to the Patna Flooring Company
and complete the remaining portions of works and give final
polishes thereto by the schedule date. It is not understandable
why Saxena was endorsing this for action to Patna Flooring Company unless the Government had chosen not to ratify the contract
c with
the Patna Flooring Company and was still treating him as a
contractor. It is also significant that it has not been alleged or·
proved that any similar letter was written to Patna Flooring Company direct by the S.D.0. On July 21, 1955, a "statement show•
ing up to 21st day of July, 1955, correct amount for the mosaic
D work done by M/ s. Patna Flooring Co. in the Rajendra Surgical·
Block, Patna Medical College and Hospital, Patna-Transactions
between Shri G. P. Saxena, Prop. M/s. G. P. Saxena & Co. and
M/s. Patna Flooring Co." was made out and this statement of
account shows "Bill No. BP/1833/45/55, dated 13-7-55 through
the S.D.O. No. III Subdivision, Construction Division, PatnaE bill for Rs. 14,000/9/-" and Saxena agreed to seltle this bill, and·
a copy of that statement was forwarded to the ExecutivtJ Engineer
for record with reference to the discussion which was held between
Saxena and Prasad in his presence and the presence of the S.D.0.This statement shows that the Government Officer was acknowledging that the liability for work done by the Patna Flooring Company
}i
would be that of Saxena. If a direct contract between the Patna
Flooring Company and the Government still subsisted, all this ·
.arrangement seems to be uncalled for.
A
G
H
Mr. Sarjoo Prasad further points out an important· fact that
when Saxena submitted the bill to the Government, he not only
charged for the work done by the Patna Flooring Company but
he charged it at the rates contained in his own contract and not
in the quotations, dated April 14, 1955, given by the Patna Flooring Company. We agree with him that this is a very significant
fact and shows that as far as the Government was concerned, the
original contract stood and the Government had not chosen to
treat Patna Flooring Company as a contractor, l:iut only as a suo~
cootractor working under Saxena.
·74
SUPREME
COURT
REPOR rsc~
[1%6] 2 S.C.R.
Mr. Purshottam laid a great deal of stress on the pleadings in
·the money suit No. 53 of 1959. There is no doubt that the plaint
in the money suit filed by the Patna Flooring Company shows that
Bateshwar Prasad, plaintiff, was trying to make out that there was
a direct contract entered into between the P.W.D. and the plaintiff,
but even so, the plaint does not make them solely responsible. We
have also come to a finding that there was admittedly a contract
in the beginning .. The fact that the plaint does not allege any
subsequent non-acceptance or refusal to ratify by. the Government
·would not estop the respondent from proving in this case that on
the material on record it is' clear that the Government had not
ratified the contract with the respondent but confirmed the original
-contract with Saxena. The written statement filed by the Government in the money suit cannot be used to dest~oy the inference
·which clearly arises from the documents referred· to above. It
·is doubtful whether the written statement can be taken into con·sideration at all.
A
B
\
C
•
'
In the result we hold that no contract between respondent No. 1 D
and the Government subsisted at the relevant time, viz .• the date
of the nomination, and the respondent was not disqualified under .
s. 7 ( d). The appeal accordingly fails and is dismissed with costs.
.'
Shah J.. At the general elections held in February 1962 the
appellant Laliteshwar Prasad Sahi and the first respondent Batesh- E
war Prasad contested a seat from the Lalganj North constituency
in the Bihar Legislative Assembly. The first respondent was
declared elected. The appellant then filed a petition be'ore the
Election Tribunal, Muzaffarpur, for an order dedaring the elec. tion of the first respondent void on the ground that the first res:
·pondent was disqualified und_er s. 7 ( d) of the Representation of F
the People Act 1951-·h~reinafter called 'the Act'-for being a
member of the Bihar Legislative Assembly, and for an order that
the appellant be declared duly elected. The Election Tribunal
disqualified the first respondent under s. 7 ( d) of the Act because
in the view of the Tribunai" on the date on which the first respon- G
dent filed the nomination paper there was a subsisting contract
between him and the State of Bihar for execution of works undertaken by the Government. The Tribunal declined to declare the
appellant duly elected..
Against the order passed by the Tribunal, appeals were preferred to the High Court of Patna by the appellant and the ·first
· respondent under s. 116-A of the Act. In the view of the Hi.gh
'Court. the first respondent was 11ot di~qualified from being elected
II
•
.
LAL!TESHWAR v. BATESHWAR
(Shah, J.)
75
A a member of the Bihar Legislative Assembly because there was at
the date of nomination no subsisting contract for supply of goods
or execution of works between the first respondent and the Government of Bibar. The appeal filed by the first respondent was
accordingly allowed and the appeal filed by the appellant was dismissed. With certificate granted by the High Court, the appellant
B bas preferred this appeal.
Section 7 (1 )( d) of the Act as it stood at the r.elevant time
read as follows :
•
c
D
"A person shall be disqualified for being chosen as,
and for being, a member of either House of Parliament,
or of the Legislative Assembly or Legislative Council
of a State.
( d) If there subsists a contract entered into in the
course of his trade or business by him with the
appropriate Government for the supply of goods to, or
for execution of any works undertaken by that Govern1nent."
The appellant contends that the first respondent was disqualified
from being a member became there was betwe.en him and the
Government of Bihar a subsisting contract relating to execution of
E works for the Government. Two components of the issue to be
determined in this appeal are : whether at the relevant time there
was between the State of Bihar and the first respondent a contract
in the course of the first respondent's trade or business for execuc
tion of any work undertaken by that Government and whether at
the material time the contract was subsisting. The Trial Court
ll answered both the components in the affirmative. The High Conrt
was of the view that there was no contract at any time between the
State of Bihar and t t first respondent.
'
•
The appellant's case was that the first respondent and his son
Bhupendra Nath Prasad carried on business of executing mosaic
G flooring, plU111bing and sanitary works in the name of M/ s Patna
Flooring Company, that the first respondent on behalf of M / s
Patna Flooring Company·had obtained contracts from the Government of Bihar for doing "mosaic and dado works" at Rajendra
Surgical Block of Patna General Hospital, and that in connection
with the said contracts the first respondent had 'filed suit No. 53
H of 1959 in 'the Court of the Subordinate Judge, Patna, against the
State of Bihar the Executive Engineer, P.W.D. (Construction
Division No. 1) and others for a decree for Rs. 18,500/- and it
LlSup. C.T./66-'6
76
SUPREME
COURT REPORTS
[1966] 2 S.C.R.
wa~ claimed in the plaint in that suit that there was a "direct con-
A
traqt" between the first respondent and the State of Bihar, and on
tl).at account the first respondent was disqualified under s. 7(d) of
the Act from being a member of the Bihar Legislative Assembly.
The first respondent denied that he was looking after the business
o{ M/s Patna Flooring Company on the date of filing of the nomination paper and contended that the contract for doing mosaic B
work at Rajendra Surgical Block of the Patna Medical College
General Hospital was between G.P. Saxena and the Gove=ent
of Bihar, and that he-the first respondent-had never entered
into a contract with the Govermnent of Bihar for doing mosaic
work at Rajendra Surgical Block and that in any event there was C
no subsisting contract at the date of his nomination as a candidate.
..,
There is on the .record a mass of documentary evidence
which throws light upon the question in dispute. Saxena had
submitted in March 1951 ·his tender for the construction work
of the Rajendra Surgical Block at Patna, which was undertaken D
by the Gove=ent of Bihar. Items 39 & 40 of the contract
related to "mosaic flooring and dado". For "mosaic flooring" the
rat\) tendered and accepted was Rs. 2/4/- per sq. ft. and for
"mosaic dado" the rate was Rs. 2/8/- per sq. ft. By cl. 2 of tile
cQnditions of the contract, it was provided, inter alia, that the
contractor shall strictly carry out the work within the time stipu- E
lated with all due diligence and that the contractor shall pay as
compensation amounts equal to 1/3 per cent, on the estimated
cost of the whole work as shown by the tender for every . day
that the work remains uncommenced or unfinished after the agreed
dates. By clame 3 it was. provided that in any case in which the
contractor shall have rendered .himself liable to pay compensation F
all)ounting to the whole of his security deposit in the hands of the
Government, the Executive Engineer shall have power to adopt
anv of the following courses, as he may deem best suited to the
interests of Gove=ent :
;
(a) To rescind the contract;
G
(b) To emoloy labour paid by the P.W.D. to carrv
· out the work, or anv part of the work, debiting
the contractor with the cost of labour;
( c) To take away such part of the work of the contract as shall be u"executed out nf his hand<.
and to give it to another contractor for completion.
•
H
LAL!TESHWAR V. BATESHWAR
(Shah, J.)
77
A
•
.
<
The first respondent was working as a sub-contractor under
Saxena in certain sections of the work undertaken by the latter.
In April, 1956, Saxena was unwilling or unable to complete the
"mosaic flooring" and "mosaic dado" under his contract, and negotiations took place between the Executive Engineer, Construction
Division, and the first respondent regarding completion of that
B work by the first respondent. ·On April 17, 1955, the first respondent addressed a letter Ext I (g) to the Executive Engineer recording the conversation he had with the Executive Engineer relating
to the rates of mosaic work etc., and submitted his terms and conditions. The rates offered by the first respondent were substantiaUy lower than those under the contract with Saxena, but he
C requested that certain construction materials be supplied by the
Department on his account, and the price thereof may be debited
against his bill. The Executive Engineer made a note on this letter
"It is hoped, necessary notice has been given .... to the defaulting
contractor". On April 20, 1955, the Sub-Divisional Officer made
D a note that the contractor (Saxena) had "already been served with
a notice" and that the first respondent's firm had been ordered to
start the work. On April 20, 1955, the Sub-Divisional Officer
addressed a letter Ext. 1 (c) to M/s Patna Flooring Company as
under:
E
~
~-
"As ordered by the Executive Engineer, please start
immediately the remaining mosaic floor and dado work
in the R. S. Block and finish the work completely within a fortnight as promised by you."
F
Intimation about entrustment of the work to M/s Patna Flooring
Company was also given to Saxena by Jetter Ext. 1(j). It was
stated in that letter :
G
"As you have failed to do (in spite of repe1ted
askings) the remaining mosaic work of floor and d1do
in Surgical Block, the remaining work is being got done
by other agency and the cost will be recovered from your .
bill which please note."
Ml s Patna Flooring Company was called upon by letten dated
May 7, 1955 and May 13, 1955 and May 23, 1955 to complete
the work within the period stipulated. On May 25, 1055 M/s
Patna Flooring Company addressed a letter to the Sub-Divisional
Officer infom1ing him that his firm had finished ?bout 903 of the
H entire work entrusted to them, and requested that an "on account
payment" may be made to them. There is on the record no
further correspondence in regard to the mosaic flooring and dado
78
SUPREME
COURT
REPORTS
[1966] 2 S.C.R.
work in the Surgical Block. On December 23, 1955, the Sub- A
Divisional Officer addressed a letter to M/s Patna Flooring Company referring to an "oral order" of the Executive Engineer and
requested the Company to do mosaic work in "two bath rooms and
laboratory of the Lecture Theatre" and asked them "to do the work
as per instructions''. On April 4, 1956 M/s Patna Flooring Company submitted a bill for the "flooring and dado work" done in B
the bath rooms of the Lecture Theatre under the orders of the
Executive Engineer and of the Sub-Divisional Officer and requested that payment be made to them. A copy of that letter was sent
to the Sub-Divisional Officer along with a copy of the bill for the
work done, for information and for immediate payment, but no C
payment was made. The P.W.D. authorities, it appears, thought
that instead of making the payment directly to the first respondent,
Saxena should be called upon to pay the amounts due to M/s
Patna Flooring Company for work done by them. This is evidenced by several letters on the record to wh:ch we will presently
·
refer.
D
Interruptbg the narrative at this stage, it moy be observed that
the evidence set out leaves noA"oom for doubt that there w,ere negotiations between M/ s Patna Flooring Company and the Executive
Engineer for carrying out "mosaic flooring and dado work" which
was part of work Saxena had undertaken to do and which he had
failed to complete. The Executive Engineer asked M/s Patna
Flooring Company to carry out that work and the latter submitted
its own schedule of rates, and asked for certain facilities which did
not form part of Saxena's contract. In our view Ext. 1 (g) dated
April 17, 1955 and Ext. 1 (c) dated April 20, 1955 constitute an
offer to execute "the mosaic and dado" work and acceptance thereof on behalf of the Government of Bihar. The work o' "mosaic
flooring and dado" work in the Rajendra Surgical Block which was
part of the contract of Saxena was completed by M/s Patna Flooring Company in July 1955 after Saxena was intimated that the
work which remained to be done would be completed through other
agency. Similarly under the imtructions of the Executive Engineer
they did the. work of "mosaic flooring and dado work" in the b~th
rooms and the Lecture Theatre some time after January 1956.
These contracts were not in the form prescribed by s. 299 of the
Constitution. and the contracts not being expressed to be entered
into bv the Governor of the State and in the manner directed J>v
the Governor were unenforceable against the State: see B;khrai Jaipuria v. Union of India('). But the contracts were not, because
(I} [1962] 2 S.C.R. 880.
•
E
F
G
~
H
LALITESHWAR V. BATESHWAR
'
(Shah, ].)
7fJ
A they were not executed in the manner or in the form prescribed
by Art. 299 of the Constitution, unlawful. It is always open to the
State notwithstanding informality in the mode of execution of the
contract to accept liability arising under the terms of the contract.
There is no dispute that the Executive Engineer was competent on
behalf of the State to enter into contracts with M/s Patna flooring
B Company in respect of both the items of work. The contracts
resulted from offer by M/s Patna Flooring Company and acceptance by the Executive Engineer. It has been held by this Court
that in cases arising under the Act, a contract not enforceable by
action against the Government may still be regarded as a contract
which disqualifies a person from standing for election as a member
C of th~ legislature under s. 7 ( d): see Cha!turbhuj's case\"). In
Chatturbhuj's case no contract was executed in the manner prescribed by Art. 299 of the Constitution. The contract in that case
was one for supply of goods. The Court in considering whether
the existence of a contract not in the form prescribed by Art. 299
D of the Constitution disqualified a person under s. 7 ( d) observed at
p. 835:
E
F
G
~
H
"It would, in our opinion, be disastrous to hold that
the hundreds of Government offic.~rs who have daily to
enter into a variety of contracts, often of a petty nature,
sometimes in an emergency, cannot contract orally or
through correspondence and that every petty contract
. must be effected by a ponderous legal document couched
in a particular form. It may be that Government will
not be bound by the contract in that c1se, but that is a
very different thing from saying that the contracts as
such are void and of no effect. It only means that the
principal cannot be sued; but we take it there would be
nothing to prevent ratification, especially if that was for
the benefit of Government. There is authority for the view
that when a Government officer acts in excess of authority Government is bound if it ratifies the excess; <ee
The Collector of Masulipatam v. Cavaly Venkata Narrainapah-8 M.I.A. 529 at 554."
It was also held thats. 7(d) of the Act did not require that the
contracts at which it strikes, should be enforceable against the Government: alt that it requires is that the "contract should be for
the supply of goods to the Government." The pur;:ose of the Act
it was observed. is to maintain the purity of the legisla•ures and
to avoid a conflict betwe.en duty and interest, and that it is
(lJ [1954J s.c.R. s11.
80
SUPREME COURT REPORTS
[1966] 2 S.C.R.
obvious that the temptation to place interest before duty is great A
when there is likely to be some difficulty in recovering the money
from the Government. Absence of a formal contract in the
terms of Art. 299 of the Constitution will not therefore affect the
operation of disqualification prescribed by s. 7 ( d) of the Act.
The inference ad.sing from the documentary evidence, ·whi!;(h B
we have already set out, is further strengthened by the admissions
made by the first r.~spondent many years after execution of the
"mosaic and dado" work. In a notice served by him upon the
Government of Bihar under s. 80 of the Code of Civil Procedure
on January 3, 1959 for payment of the amount due to him for
"mosaic flooring and dado work" in the Rajendra Surgical Block C
and the bath rooms and lecture theatre in the year 1955-56,
M/s Patna Flooring Company stated that "suspension of the
work by Saxena made the P .W.D. authorities anxious" and they
called upon them to continue the work. It was then stated in
paragraph-11 :
D
"That the _P.W.D. authorities, when failed in their
attempt to persuade Shri G. P. Saxena to continue the
work approached Sri Bateshwar Prasad, one of my said
clients, to take up the work direct and assured full payment by deducting from the bills of Shri G. P. Saxena
or by preparing direct bills, in the nature of a contract
of guarantee."
E
In paragraph-12 it was stated :
"That as a result of the said approach and assurance, letter No. BP/1763/28/55 dated 17-4-1955
was addressed by the firm of my clients to the Executive
Engineer,. ....... quoting rates rather less than the
rates on which Sri G. P. Saxena got the work from the
P.W.D. Department which was confirmed in letter No.
504, dated 20-4-1955 from the S.D.0. No. III Subdivision, Construction Division, Patna, ........ wherein the department asked my clients to proceed with the
remaining work ............. "
F
G
In paragraph-13 it was stated :
"That on the receipt of the said letter dated
20-4-1955 ........ my clients started doing the work
and received materials ............ from the P.W.D.
Stores ............. from time to time."
H
•
LALITESHWAR V. BATESHWAR
(Shah, J.)
81
A In paragraph-14 it was stated :
"That the firm of my clients was in direct contract
with you and your department. ........... "
•
'
In paragraph-16, the letter dated June 5, 1955 informing the
11 Executive Engineer about the completion of the work is referred
to, and it is stated that on July 13, 1955 M/s Patna Flooring
Company had submitted their bill for Rs. 14,000/- to the Executive Engineer. By this notice the first respondent demanded from
the State of Bihar Rs. 22,947/07 nP and Rs. 5,000/- as damages
and loss sustained by M/ s Patna Flooring Company.
c
In the plaint in suit No. 53 of 1959 filed by M/s Patna Flooring Company by paragraphs 6, 7 and 8 substantially the same
averments were made. In paragraph-? of the plaint it was stated
"Thus it is clear the plaintiffs and their firm began the work under
a direct contract from the P .W.D. which also appears from Jetter
D No. 705 and 706 dated 23-5-55 addressed to the plaintiffs firm
by the S.D.0. No. III Sub-division ........ "., and in paragraph-8
it was stated that "the mosaic work done by the plaintiffs had been
done under a direct contract from the P .W.D. authorities and "Sri
G. P. Saxena had no interest in this mosaic work but if any how
it has been entered in the M.B. in the name of Sri G.P. Saxena then
E . the payment to the extent of the plaintiffs dues should be withheld
and the same should be paid to the plaintiffs by the P .W.D.
a111thorities.''
F
We are informed at the Bar that suit No. 53 of 1959 has as
yet not been disposed of.
We are called upon in this case to decide whether it is established that there was a contract between the State of Bihar and
the first respondent relating to construction work, which disqualified him from being a member of the Bihar Legislature. We are
not concerned to decide whether the contract was enforceable
G against the State. The evidence already set out in our view abundantly supports the case that there was a contract directly between
the first respondent and the State of Bihar relating to the execution
of work, and that the contract was made in the ccur!e of the first
respondent's trade or business.
H
The first respondent had pleaded in his written statement that
there was in fact no contract and that he (the first respondent)
had completed the "mosaic and dado work" in the Surgical Block,
82
SUPREME
COURT
jl.EPORTS
[1966] 2 S.C.R.
the bath rooms and the lecture theatre as a sub-contractor of A
Saxena: In so pleading he sought to ignore the letters Exts. 1 (g),
1 ( c) and the relevant correspondence. No explanation was
attempted before the Election Tribunal explaining that correspondence. It was merely urged that the two letters Exts. 1 (g) & 1( c)
between M/s Patna Flooring Company and the P.W.D. authorities and the other correspondence between the Executive Engineer B
and Saxena indicated that the "mosaic flooring and dado work"
was completed by the first respondent as an agent of Saxena. It
is urged in this Court for the first time that assuming that Exts.
l{g) & 1 ( c) amounted to an offer by the first respondent and
acceptance thereof by the Executive Engjneer, that offer and
acceptance thereof could amount to a binding contract between c
M/s Patna Flooring Company and the Government of Bihar,
only if the Superintending Engine~r accepted or ratified the contract and in the absence of any evidence to that effect, the offer
arid acceptance did not give rise to any contract disqualifying the
first respondent under s. 7 ( d) of the Act.
D
We may at once obs.~rve that the subsequent correspondence
and settlement of account> Ext. G contain at best ambiguous
statements which do not raise any inference in favour of the first
respondent. We may briefly refer to this evidence. On July 12,
1955 the Sub-Divisional Officer addressed a letter to M/s Patna
Flooring Company intimating that it was "disappointing to note
that in spite of repeated askings" the firm had not submitted their
final bill for the mosaic work till that date. The letter then proceeded "I have been personally explaining to you the whole position and you promised to submit your final correct bill on Friday
the 8th July, 1955 so that I may "ask the contractor Shri G. P.
Saxena to pay you off finally and settle your accounts immediately." This letter clearly indicates that in the view of the SubDivisional Officer the bill had to be submitted by the first respondent to the P.W.D. authorities and that they would persuade
Saxena on account of whose default the contract with the first
respondent was necessitated to pay the amount due to him. The
next letter is dated July 13, 1955 addressed by the Sub-Divisional
Officer to M/s Patna Flnoring Company intimating that the bill
of M/s Patna Flooring Company had been sent to Saxena for
immediate settlement and payment, and asking th.e Company to
settle the account with Sa.,.ena and to receive pavment from him
and to report to the P.W D. authorities .. On Julv 20, 1955 there
is another letter from the Sub-Divi,ional Officer forwarding a
copy of letter No. 949 dated July 20, 1955 which was addres~ed
•
•
*'
...
E
•
F
G
•
'
H
LALITESHWAR V. BATESHWAR (Shah, J.)
83:
A to Saxena asking the latter to issue orders to his contractors to
mend and rectify all the cuttings and damages properly so that the.
building may be in a fit condition for h3nding over on August 1,.
1955. A copy of this letter was forwarded to M/s Patna Flooring
Company for their infor~ation and necessary action, and they were asked to rectify all the defects pointed out to them and to
B complete the remaining work by the scheduled date. It may be
not'ced that Saxena's contract in its entirety was not tenninated :
only a part of the contract had been taken away from him. Direc-tions had therefore to be given to him to cJmplete the contract of
the building and to hand over the same by July 31, 1955, and_
to M/s Patna Flooring Company to rectify all the defects pointed.
C out of them. If M/ s Patna Flooring Company were merely a subcontractor, there is no reason why a copy of this letter should have.
been addressed to them and that they should have been asked
to rectify the defects. On July 21, 1955 a statement of
account was drawn up in respect of the mosaic work done by
D Ml s Patna Floming Company in the Raj~nd1 a Surgical B1ock'"
It is described as "a statement of account of mosaic work between
G. P. Saxena and Messrs Patna Flooring Cvmpany". On the.
credit side of the account are three items : Rs. 57,443 / 4/3 in
re5pect of bill dated November 2j, 19.)3; Rs. 4,719/9/3 in respect of bill dated March 31, 1955 and Rs. 14,000/- in respect of
E bill dated July 13, 1955 through the Sub-Divislonal Officer No.
Ill Sub,division, Construction Division, Patna. On the debit side.
are various· items of payments aggregating to Rs. 49,754/9/3leaving a balance of Rs. 26,408/ 13/3. Against that amount a
cheque for Rs. 15,000/- is recorded as given on July 21, 1955on the Bank of Bihar Ltd., leaving a balance of Rs._ 11,408/13/3 ..
F There are two notes at the foot of this account. The first part of
note No. (1) deals with the bill dated March 31, 1955 which is
not material. It then proceeds to record that M/s Patna Flooring
Company will be responsible for rectification of the defects in
mosaic work in bill No. BP/1838/35/55 and 93/55 dated July
13, 1955 and March 31, 1955 respectively. Note No. (2) states
G that M/ s Patna Flooring Company will reali e from Saxena im- mediately the amount of the claim for work included in the third
bill. Th's is signed by the first respandent. At the foot of these,
two notes there are two endorsements one signed by Saxena and
the other by the first re~pondent In the endorsement signed by
H Saxena it is stated that the acc0unt was c~rrect and he admitted
that Rs. 11,408/13/3 were due from him which he promised "topay very soon". It was also stated that the terms of the originar
agreement between Saxena and M/ s Patna Flooring Company
:114
.SUPREME
will also remain operative.
COURT
REPORTS
[1966] 2 S.C.R .
The endorsement signed by the first
respondent states :
"Agreed and accepted the cheque for Rs. 15,000/-.
We shall finish the final polish work within a very
.short time. As the account has been settled today, the
21st July, 1955 I am herewith returning the cheque
No. BZ/131 08046 dated 18-1-55 drawn on the
Imperial Bank of India, Patna for Rs. 12,000/- and
balance now stands as mentioned Rs, 11,408/13/3 as
per settlement, subject to encashment of to-day's cheque
No. G140696 dated 21-7-1955 on the Bank of Behar
Ltd. Patna."
A copy of this aceount was forwarded to the Executive Engineer,
Construction Division, through the Sub-Divisional Officer "for
information and record with reference to the discussion which
was held between" Saxena and the first respondent "in his presence
and the presence of the Sub-Divisional Officer No. III Subdivision." Strong reliance was placed upon this document by
<eounsel for the first respondent in support of his claim that there
was in truth no contract between the State of Bihar through its
P.W.D. authorities and the first respondent, but the contract continued at all material times to subsist between Saxena and the
State of Bihar. After carefully considering this argument, in
•our view, this document is not susceptible of any such interpretation The P.W.D. authorities had adopted the attitude that
even though they were liable to meet the bill of M/s Patna Floorlng Company for the work done under the arrangement arrived
at between them by Exts. 1 (g) and 1 ( c) they would procure
payment of the amount due from Saxena. The first respondent
had admittedly done the work in respect of two bills dated Nov-ember 25, 1953 and March 31, 1955 a.s sub-contractor for
Saxena. A third bill for Rs. 14,000 had been submitted for the
work done by the first respondent for which the bill was sent to
the Sub-Divisional Officer. Saxena was apparently refusing to
make the payment, and a meeting was arranged in the presence of
the Executive Engineer and the Sub-Divisional Officer in which
a consolidated account was made and Saxena agreed to pay the
balance of Rs. 26,408/13/3 and against which he gave a cheque
for Rs. 15,000/-. This statement of account cannot conceivably
·be utilised in suport of the case of the first respondent that there
was no contract between him and the P.W.D. authorities reore-,
1lenting the State of Bihar: it is merely a settlement arrived at between the first respondent an:! Saxena in the presence of the
A
B
c
D
E
F
G
H
LALITESHWAR V. BATESHWAR (Shah, J.)
.85
A Executive Enaineer and the Sub-Divisional Officer under which
Saxena agreed to pay the amount of Rs. 11,408/13/3 re!Ilaining
due on the consolidated account. The sett1")ment at the mstance
of the Executive Engineer and the Sub-Divisional Officer does
not purport to wipe out the contract which was previously arrived
at and the construction work done in pursuance of that contract,
B and the mere endorsement under the signature of Sailena that the
terms of the original agreement between him and M/ s Patna
Flooring Company will also remain operative only indicates that
M/ s Patna Flooring Company may continue to work as subcontractor of Saxena, le;t it might give an impression that the
sub-contract between Saxena and M/ s Patna Flooring Company
C was terminated.
For the work which Saxena failed to complete, he was liable
to compensate the Government under the terms of his contract.
The Executive Engineer had informed Saxena that the amount
payable to the first respondent would be deducted from his bill,
D and had on diverse occasions called up:m Saxena to pay the
amount due to the first respondent. The first respondent was concerned to receive the money due to him, and it was a matter of no
consequence to him whether the Government paid it directly or
the authorities got it paid by Saxena. The desire of the first respondent not to imperil his p ·sit'on as a contractor with the GovernE ment in P.W.D. contracts may well be understood. It is difficult
to appreciat."l how this settlement made in the presence of the
Executive Engineer, whereby Saxena agreed to discharge the liability of the Government, in consideration of discharge of his own
liability under his contract, negatives the existence of the contract
F between the Government of Bihar and the first respondent.
There is on the record correspondence relating to the demands
for payment by the first respondent. A letter dated March 28,
1956 was addressed by Saxena to the Executive Engineer informing him that M/s Patna Flooring Company had not sent their bill
to him and that they niay be directed to furnish a copy of their bill
G to enable him to check the same and arrange payment. This letter
refers to the payment for the work done after December 1955,
because the bill in respect of the work done in July 1955 had
already been submitted and was the subject-matter of the settlement of account Ext. G. There are letters dated August 21, 1957.
December 7, 1957 and March 8, 1958 in which the Executive
H Engineer called upon Saxena to settle the claim of M/ s Patna Flooring Company. There is draft of a Jetter of the Executive Engineer
dated March 16, 1958 reciting that Saxena was requested several
86
SUPREME
COURT
REPORTS
[1966] 2 S.C.R.
times to settle the claim amicably "but he was not in a mood to do
so and wanted to drag the department into litigation". The .second
paragraph of that letter is important. It states :
"As a matter of fact when Shri Saxena failed to complete the particular item of work M/ s Patna Flooring
Co., were engaged at the instance of the then Departmental Officer. Materials were also issued to them, the
cost of which are still outstanding against them. And
as such the department will have to pay the amount in
question to M/s Patna Flooring Co. for the work done
by them. It may be added here that the work done here
by this time has already been billed for in favour of
of Shri G.P. Saxena. The correct proc~dure in this case
would have been for the department to make paym~nt
to M/s Patna Flooring Co."
A
B'
c
By the last paragraph it is recJrded that Saxena may be advised
to settle the matter amicably and to obtaain a c1earance certificate D
from M/s Patna Flooring Company. The Sup.~rintending Engineer also addressed a letter to Saxena on May 26, 1958 calling
upon him to settle the matter amicably with M/ s Patna Flooring
Company within a month and threatening that the amount due
will have to be deducted from his final bill. A copy of this Tetter E
was forwarded to M/s Patm Flooring Company.
It appears that on July 25, 1958, Saxena submitted a statement about the construction work done by him and included therein the work done by M/s Patna Fiooring Company. At the foot
of the bill is a 1i1emorandum relating to p1ymcnts made from time F
to time and the last item shown therein is Rs. 13,897/- due to
M/s Patna Flooring Company. Saxena not having paid the
amount to M/ s Patna Flooring Company, a letter d.ated September 10, 1958 was addressed to Saxena by the Executive Engineer
in which it was recorded that the contractor's (Saxena's) representative had seen the Executive Engineer in his office at the time G
of refund of the security deposit kept back on account of incometax dues and had promised that hf) would settle up the account
with M/s Patna Flooring Company and pay their dues immediately, and that although the "refund of the amount had already been
given the dues of M/s Patna Flooring Crmpany had not been
cleared''. Saxena was once more requested to clear off the dues H
of M / s Patna Flooring Company so that the refund of the amount
kept in deposit may be given to him.
'
LALITESHWAR v. BATESHWAR
(Shah, J.)
87
A
This is all the material correspondence on wh'ch the first respondent has relied. The correspondence makes it abundantly clear
that the primary liability for payment of the dues was of the State
of Bihar and they accepted that liability. The Bill of Mis Patna
Flooring Company was received by the P.W.D. authorities and
they called upon Saxena to satisfy the claim because under the
B terms of the contract the liability for payment would ultimately be
enforced against Saxena. None of these letters even indirectly
suggests that the contract for work done by Ml s Patna Flooring
Company in the matter of "mosaic flooring and dado work" was
done in execution of the sub-contract which that Company had
obtained from Saxena. The anxiety evinced by the Superintending
C Engineer, the Executive Engineer and the Sub-Divisional Officer
that the claim of Ml s Patna Flooring Company be settled by payment through Saxena is consist..,nt with the case that the primary
liability was of the State of Bihar and the P.W.D. authorities wanted to avoid litigation. The conduct of the authorities in the conD text of the documents to which we have already referred to is in
our view consistent only with the infer.ence that the construction
work was done by Ml s Patna Flooring Company under a contract
directly with the P.W.D. authorities.
Ml s Patna Flooring Company """re approved contractors and
if they were made to believe that Saxena will be induced to pay the
amount due to them, it was not expected that they would incur
the displeasure of the authorities, by insisting upon payment
directly by the State. The offer and acceptance incorporated in
Exts. l(g) and l(c) the construction work done by Mis Patna
Flooring Company, thereaft,.,r the submission of the bills by Mis
F Patna Flooring Company for payment, the anxiety of the P.W.D.
authorities that payment should be made to Ml s Patna Flooring
Company and their intervention in securing payment and anxiety
to ~void litigation clearly establish that the contract pursuant to
which the work of "mosaic flooring and dado" was done was between Mis.Patna Flooring Company and the Government directly .
G Th~ co~tract _was not unauthorised and therefore no question of
ratificat10n anses. It may also be noticed that the contract required to be ratified and was not ratified was never raised in the trial
Court or in the High Court.
The argument that after the contract was entered into the
Superintending Engineer had countermanded the arrangem~nt. is
H in our judgment without substance. On the letter dated May 'i6
1958.there_is ~n .endorsement presumably by the Executive Engi'.
neer m which It IS recorded that Ml s Patna Flooring Company
·E
.
'
•
88
SUPREME
COURT
REPORTS
[1966] 2 S.C.R.
were engaged at the instance of the then Departmental Officers A
for completing the work left incomplete by Saxena, and it is followed by a query "Was the sanction of S.E., S.B.C. taken to this
arrangement, if so, copies of the correspondence may please be
furnished ?" Th.ere is no record of the reply, if any, g:ven to this
query. There is, however, at the foot of the letter an endorsement
dated May 17, 1958, made by some one "w:rite to the contractor". B
It is true that the Superintending Engineer was in overall charge
of the construction work and by the terms of the tender itself the
authority of the Executive Engineer to accept the tender is limited: cl. 9 of the form of tender Ext. D. But there is no evidence
on the record that the Superintending Engineer had at any time C
countermanded the arrangement between the Executive Engineer
and M/ s Patna Flooring Company. The first respondent in his
examination before the Trial Court stated that :
"I had sent Ext. 1(g) to S.D.O., P .W.D. No. 3
mentioning the rates and terms that my firm had with
G. P. Saxena for construction of mosaic and Dado work
in Rajendra Surgical Block. No direct contract was
ever entered with between P.W.D. department and my
firm even after this letter Ext. 1 (g). Saxena went to
Superintending Engineer and objected.
The Superintending Engineer ordered that Saxena will continue to
be the contractor as before and no direct contract will
be given to any firm."
n
E
But it is not suggested that there was any such arrangement in the
presence of the first respondent. The Superintending Engineer
has not been examined, and there is on the record no evidence F
to support this part of the case, which was never set up in the
Trial Court and the High Court.
The admissions made by the first respondent in his notice and
the plaint in suit No. 53 of 1959 were sought to be explained by
him on the plea that he had signed the plaint and the verification G.
without reading the plaint of the suit as the plaint was required
to be filed in great hurry. A similar explanation was also given
in respect of the contents of the notice. It is difficult to accept
this explanation which was invented with a view to get out of the
inconvenient admissions. The Executive Engineer Mukteshwar
Prasad in his evidence stated that the Sub-Divisional Olficer had H
given a warning to Saxena that his contract would be terminated
and a part of the. work wunld be done through anotl1er agency
LALITESHWAR V. BATESHWAR
A
B
c
D
E
•
•
(Shah, J.)
89·
and that thereafter M/ s. Patna Flooring Company were engaged
to complete the work. Rameshwar Prasad Singh, who succeeded
Mukteshwar Prasad as the Executive Engineer also said that the
unexecuted part of the mosaic work was taken away from Saxena
and was entrusted directly to Ml s. Patna Flooring Company and'
that M/ s. Patna Flooring Company were directed to complete the
work. It was never sdggested to either of these witnesses that
the arrangement was countermanded by the Superintending Engineer.
The first respondent approached the Court denying that therewas a contract between him and the State of Bihar relating to the
construction work. That denial is falsified by letters Exts. 1 ( g)
and 1 (i) and is further falsified by his statements made by him on·
oath in his plaint. On his own admissions, the first respondent is
a person who is willing to trim his sails as his interest demands.
The explanation given by the first respondent regarding th0 admissions made by him in the plaint cannot be accepted as truthful.
On a careful consideration of all the circumstances, we are unable
to agree with the High Court that there was no contract between
the first respondent and the P.W.D. authorities representing theState of Bihar in respect of the "mosaic and dado work" by Exts.
l(g) and J (c) pursuant to which the first respondent carried out
the work independently of Saxena.
It now remains to consider whether there was a subsisting
contract at the date of filing of the nomination paper. The work
of construction entrusted to the first respondent was completed in
July J 955 and in respect of "bath rooms and the lecture theatre"
F was completed sometime before April 1956. The first resnondent had not been paid the amounts due to him. It cannot be
said that in view of the attitude adopted by the State of Ribar
there has been a breach of the contract. The expression "there
subsists a contract" in s. 7 ( d) of the Act includes cases in which
one p~rty has performed his part of the contract and part performG able by the other party remains. It was so held by this Court
in Chatturbhuj's case('). The first paragraph of the head note·
in that case states :
I'
~
H
"A contract for the supply of goods does not terminate when th~ goods are supplied, it continues into being:
ull payment 1s made and the contract is fully discharged
by performance on both sides."
(1) [1954] S. C.R. 817.
90
SUPREME
COURT
REPORTS
[1966] 2 S.C.R.
In that case pursuant to an oral request made on behalf of the A
State of Madhya Pradesh, Chatturbhuj Jasani had supplied
·"canteen stores" between October 8, 1951 to January 23, 1952,
and had submitted invoices in respect thereof. Payments were
made in respect of those invoices between November 15, 1951
and March 20, 1952. Elections to the Parliament were held in
.December I 951, and Jasani stood as a candidate for one of the B
two seats before payment for the stores supplied was made. The
Court refused to accept the plea raised on behalf of the elected
candidate that the moment the contract is fully executed by the
candidate, the contract is at an end and· a new relationship of
'debtor and creditor takes its place. It is true that the material
words of s. 7(d) of the Act which fell to be considered in that C
,case were somewhat different. They stood as follows :
"A person shall be· disqualified for being chosen as,
and for being, a member of either House of Parliament or of the Legislative Assembly or Legislative Council of a State . . . ..
( <l) If, whether by himself or by any person or body
of persons in trust for him or for his benefit or on his
account, he has any share or interest in a contract for
the supply of goods to, or for the execution of any works
or the performance of any services undertaken by the
appropriate Government;"
,.
D
E
'The conditions under which disqualification was incurred were
wider under the section as it then stood. Any share or interest
·in a contract for the supply of goods, or for the execution of any
works or the performance of any services undertaken whether by F
himself or any person or body of persons in trust for him or for
·his benefit or on his account, disqualified a candidate from being
e!eeted as a member of the Legislature. The Act as amended has
now restricted the conditions which import a disqualification. The
two conditions now are that the contract must be in the course of
'the candidate's trade or business, and it must be for supply of G
goods or for execution of any works undertaken by the Govem·ment. Contrrrcts Jn respect of services undertaken for the appropriate Government are apparently not within s. 7 ( d) as amended.
·The amended section again requires that there must be a contract
·entered into bv the candidate. Mere interest in a contract, unless
the candidate has entered into the contract directly or through an H
agent, would apparently not disqualify him. But ~·
d) before
·it was amended was attracted, if there was a subs1stmg contract
7(
•.
•
LALITESHWAR V. BATESHWAR (Shah, J.)
A
B
J
91
and the application oi the clause after it was amended also is subject to the same condition. If there was no subsistip.g contract,
neither under s. 7 ( d) before it was amended, nor after it is amended, would the disqualification be incurred. In the present case
the first respondent performed his part of the contract, and no
payment has been made by the Government of Bihar to him. In
the circumstances, relying upon Chatturbhuj Jasani's case( 1 ), we
are of the view that the contract was a subsisting contract.
Mr. Sarju Prasad appearing on behalf of the first respondent
contended that by s. 116-B of the Act, the decision of the High
Court is made "final and conclusive" and interference by this
c Court with that decision, even if it appears that an error has been
committed by the High Court, will not be justified. But by
s. 116-B the jurisdiction conferred upon this Court by Arts. 133
and 13 6 of the Constitution is not, and cannot be restricted. If
the circumstances of the case justify, this Court has the' power, and
is indee)l. under a duty, to set aside the verdict of the High Court.
D The Court is dealing with a case in which a question which vitally
concerns the purity of elections arises. A person who has a contractual relationship between him and the executive would, on
getting elected, be able to bring pressure to bear upon the executive to settle his claim or to secure advantage for himself to which
he may not be lawfully entitled. This appears to be the scheme
E underlying s. 7(d) which disqualifies a person from being chosen
as a member of the Legislature if there subsists a contract entered
into the course of his trade or business by him with the appropriate
Government for the supply of goods or for execution of any works.
If, on the evidence, subsistence of the contract which disqualifies
a candidate is established, the Court would not be justified in refusF ing to give effect to its conclusion especially when the question
vitally concerns the public in keeping out of the Legislature persons who have claims arising out of subsisting contracts against
the Government.
·'
G
In our view the appeal ought therefore be allowed, and the order
passed by the High Court set aside and the order of the Election
Tribunal restored with costs in this Court and the High Court.
ORDER
'
H
In accordance with the opinion of the majority the appeal is
dismissed with costs.
(I) [1954] S. C.R. 817.
L!Sup . .C.I.{66-7
Report an error or ask for masking: grievance@lawgrids.org