SSA- MANUAL ON FINANCIAL MANAGEMENT AND PROCUREMENT
Rules made under RTE ACT 2009
- Made under: RTE ACT 2009
This text is shown as one document.
Full text
1
SAMAGRA SHIKSHA
AN INTEGRATED SCHEME FOR SCHOOL EDUCATION
MANUAL
ON
FINANCIAL MANAGEMENT AND PROCUREMENT
DEPARTMENT OF SCHOOL EDUCATION AND LITERACY
MINISTRY OF HUMAN RESOURCE DEVELOPMENT
GOVERNMENT OF INDIA
2018
2
3
SAMAGRA SHIKSHA
MANUAL ON FINANCIAL MANAGEMENT AND PROCUREMENT
2018
Table of contents
Chapter
Chapter Name
Page
No.
Annexure No. Para. No.
Chapter-1 Introduction
Chapter-2
Planning Process and Financial
Planning
Chapter-3
Financial Management, Fund
Flow & Reporting
Annexure-I 3.4.3
Annexure-II 3.4.4
Chapter-4 Accounting
Annexure-III 4.1.2
Annexure-IV 4.2.2
Annexure –V 4.2.2
Chapter-5
Monitoring, Internal Control and
Internal Audit
Annexure -VI
5.8 Annexure-VII
Annexure-VIII
Annexure-IX 5.9.3
Annexure-X 5.10
Chapter-6 Auditing
Annexure-XI 6.14
Annexure-XII 6.15
Annexure-XIII
6.6.4
Annexure-XIV
Annexure-XV
Annexure-XVI
Annexure-XVII 6.6.1
Annexure-XVIII 6.6.5
Chapter-7 Procurement Annexure XIX to XXI 7.15
Chapter-8 Capacity Building
Chapter-9
Role and Support to Central
Institutions under the New
Integrated Scheme – Samagra
Shiksha- NCERT, NIEPA,
NCPCR TSG AND NIC
Annexures I to XX
4
CHAPTER-1
INTRODUCTION
1.1 Background:
In the Budget Speech of 2018 of Hon’ble Finance Minister mentioned an
integrated scheme for secondary education stating that:
“We now propose to treat education holistically without segmentation from pre-
nursery to Class 12”.
In accordance to the aforesaid announcement, a Scheme was envisaged to treat
education holistically without segmentation by merging the centrally sponsored
schemes of Sarva Shiksha Abhiyan (SSA), Rashtriya Madhyamik Shiksha
Abhiyan (RMSA) and Teacher Education (TE). Accordingly, the Scheme has
been developed and launched to form an Integrated Scheme on School Education-
Samagra Shiksha from Pre-school* to Senior Secondary schools of the country.
1.2 Vision, Aim & Objectives:
1.2.1 Vision- The vision of the Scheme is to ensure inclusive and equitable quality
education from Pre nursery (Pre-school) to Senior Secondary Stage by 2030 in accordance
with sustainable Development Goals for Education.
1.2.2 Aim - The Aim of the scheme is to universalize quality School Education. It also
aims to support States in universalizing access to School Education from classes Pre
nursery (Pre-school) to class XII.
1.2.3 Objectives -The major objectives of the programme are:
(i) Provision of quality education and enhancing learning outcomes of
students;
(ii) Bridging Social and Gender Gaps in School Education;
(iii) Ensuring equity and inclusion at all levels of school education;
(iv) Ensuring minimum standards in schooling provisions;
(v) Promoting vocationalization of education
(vi) Support States in implementation of Right of Children to Free and
Compulsory Education (RTE) Act, 2009;
(vii) Strengthening and up-gradation of State Councils for Educational
Research and Training (SCERTs)/State Institutes of Education and District
Institutes for Education and Training (DIET)s as a nodal agency for
teacher training
* Note : Pre- Nursery or Pre-school or Pre- primary are deemed synonyms
5
1.2.4 The main outcomes of the Scheme are envisaged as Universal Access, Equity and
Quality, promoting Vocationalisation of Education and strengthening of Teacher
Education Institutions (TEIs). The Scheme will help to improve the Transition rates
across the various levels of school Education and aid in promoting universal access to
Children to complete School Education. It would also enable in reaping the benefits of
Technology and widening the access to good quality education across all States and UTs
and across all sections of the society.
Output-Outcome Framework of the Scheme
Elementary
Indicators Output/Deliverables
2015-16 (Baseline
data)
2018-19 2019-20
Net Enrolment Ratio (NER) 89.0% 93.0% 96.0%
Gender Parity Index (GPI) 0.94 0.96 0.97
Annual Drop-out Rate 4.1% 3.6% 3.5%
Transition Rate from primary to
upper primary level
90.14% 93.0% 95.0%
Retention Rate at elementary
level
70.70% 75.0% 80%
Number of Out of School
children
60 lakh 45 lakh 35 lakh
Increase in the % of children
who achieve subject-wise grade-
wise Learning Outcomes.
To be set after analysis of the baseline NAS
conducted in November, 2017
Secondary
Indicators Output/Deliverables
2015-16 (Baseline
data)
2018-19 2019-20
Gross Enrollment Ratio (GER) 80.01% 83.30% 84.98%
Gross Access Ratio (GAR) 86.48% 89.92% 91.13%
Annual Average Dropout Rate 17.06 14.06 13.06
Transition Rate (Class VIII to
IX)
90.62% 94.50% 95.00%
Retention Rate at secondary
level
57.4% 60.0% 62.00%
Gender Gap in enrolment 5 4 4
Increase in the % of children
who achieve the desired
achievement levels.
To be set after analysis of the baseline NAS
conducted in February, 2018
Senior Secondary
Indicators Output/Deliverables
Gross Enrollment Ratio (GER) 56.16% 62% 64%
Transition Rate (Class X to XI) 69.04% 74% 76%
Gender Gap in enrolment 5% 4% 4%
6
Output-Outcome Framework of the Scheme
Teacher Education
Sl.
No.
Action Outcome/Deliverables
1. Strengthening of SCERTs i. Re-structured SCERT
ii. Allotted funds utilized for in-service teacher
training
2. Strengthening of DIETs Number of States and UTs who have adopted this
Guideline
3. Innovative Pedagogy Use of innovative pedagogic methods in In-service
teachers training
4. Creation, curation and
translation of Digital
Learning Material
Development of Digital Materials on specific subjects
to be used for in-service teacher training
6. Training of Teacher
Educators
25% Teacher Educators per year
7. Training of In-service
Teachers
30% In-service Teachers per year
8. Establishment of new
DIETs
15 new DIETs per year for 2018-19 and 2019-20
9. ICT in in-service training Number of in-service teachers training conducted on
use of ICT and use of digital resource materials.
1.3 Interventions: The major interventions under the scheme are:
I. Universal Access
(i) Sanction of new schools which would include new primary schools, up-
gradation of primary school to upper primary schools, up-gradation of
upper primary school to secondary schools and up-gradation of secondary
schools to higher secondary schools. This would also include sanction of
new composite schools i.e. from Classes-I to XII and buildings for
building-less schools.
(ii) Residential Schools and Hostels in inaccessible areas ranging from
Classes I-XII.
(iii) Strengthening of existing residential schools and facilities for classes I-
XII.
(iv) Transport and Escort facility to children in Classes I-VIII and for Children
with Special Needs (CWSN).
(v) Strengthening of existing infrastructure and major & minor repair of
schools from classes I-XII.
(vi) Residential quarters for teachers, especially female teachers in
remote/difficult areas.
(vii) Support for out of school children
7
II. Gender and Equity
(i) The existing Kasturba Gandhi Balika Vidyalayas (KGBVs) at upper
primary level and Girls Hostels at secondary level would be extended to
provide residential and schooling facilities upto Class-XII, so as to have
at-least one residential school for girls upto class XII in every
educationally backward block.
(ii) Physical/Self Defence Training for girls
(iii) Other interventions like Environment Building Programme, Inspiration/
Motivation Camp for SC/ST children, enrolment/retention drives etc. at all
levels in classes I-XII
III. Inclusive Education
(i) Supporting Children with Special Needs (CWSN) in schools at all levels
in Classes-I to XII.
(ii) Supporting home based education for CWSN who are unable to go to
schools. This will be for education in Classes-I to XII.
IV. Quality
(i) Conduct student assessments at National or State level
(ii) Research studies on factors effecting access, equity and quality.
(iii) Composite school grants including maintenance grant, school grant, and
library grant etc.
(iv) Project based proposals for quality improvement
(v) Guidance and counselling services and aptitude testing.
(vi) Learning Enhancement Programmes/remedial teaching programmes to
achieve Learning Outcomes
(vii) Bridge courses for Out of School Children.
(viii) Support for Science, Technology, and Engineering and Mathematics
(STEM) education such as Rashtriya Avishkar Abhiyan.
(ix) Support for early reading initiatives like Padhe Bharat Badhe Bharat.
V. Financial support for Teacher Salary
(i) Support for teachers in upgraded schools.
(ii) Support of special teachers in schools/clusters of schools.
VI. Innovation
(i) Innovation for promoting access, equity, quality and gender equality.
VII. Digital initiatives
(i) Sanction of new ICT projects in schools which would include
hardware/software support.
(ii) Development of E-content and digital resources
8
(iii) Central initiatives to promote use of digital technology such as Shala
Kosh, Diksha etc.
(iv) Creation of digital learning material, innovative pedagogy and capacity
building, etc.
VIII. RTE Entitlements
(i) Free Uniforms.
(ii) Free Textbooks.
(iii) Re-imbursement towards expenditure incurred for 25% of admissions
under Section 12(1)(c) of the RTE Act, 2009.
(iv) Special training for age appropriate admission of out of school children.
(v) Community Mobilisation
(a) Section 21 of the RTE Act, 2009, provides for a School
Management Committee (SMC) in every school and envisages dynamic
role of the community in effective monitoring of schools. States and UTs
have been advised to have a single SMC in a composite school. This
intervention will support training of SDMC, SMC and PRI members for
carrying out the roles and responsibilities envisaged in the RTE Act, 2009.
(b) In addition activities for creating awareness about RTE Act, 2009
and strengthening the role of community and monitoring the schools at all
levels will also be supported.
IX. Pre-primary Education
(i) Support to States for Pre-primary level for training, co-location of
Anganwadis in Primary Schools and curriculum development in
convergence with Ministry/Department of Women and Child
Development
(ii) Support States in their efforts to set up pre-primary schools
X. Vocational Education
(i) Vocational Education as an integral part of general education at Secondary
and Higher Secondary level to enhance the employability of youth.
(ii) Introduction of Vocational subjects at secondary level which would
include Tools, Equipment and manpower costs.
(iii) Exposure to vocational skills at upper primary level
XI. Sports and Physical Education
(i) Increased convergence with Department of Sports.
(ii) Provision of sports and physical education facilities in all schools.
XII. National Component (1% of total budget)
(i) Support to National Institutions like NIEPA, NCERT, NCPCR, NIC etc.
for National level programmes related to quality of education,
assessments, data management, digital education.
9
(ii) Technical Support Group for monitoring of the Scheme
(iii) Establishment of National Institute of Teacher Education
XIII. Infrastructure Development
Construction of schools, additional classrooms, strengthening of BRCs and CRCs,
toilets and drinking water facilities, Science and Math labs, major repairs to
school buildings, etc.
XIV. Strengthening of Teacher Education and Training
(i) Strengthening of State Councils of Educational Research and Training
(SCERTs); District Institutes of Education and Training (DIETs); Block
Institutes of Teacher Education (BITEs);Colleges of Teacher Education
(CTEs) and Institutes of Advanced Studies in Education (IASEs)
(ii) Support for Salary of Teacher Educators/ Academic Faculty working in
TEIs.
(iii) Teacher Training and professional development including in-service, pre-
service, induction and refresher training to be provided under the aegis of
SCERTs and DIETs etc.
(iv) Leadership Training for Principals/Head Teachers
(v) Support for Infrastructure Development
(vi) Programme and activities in Teacher Education Institutions (TEIs)
(vii) Establishment of Special Cells
(viii) Establishment of New DIETs in new districts Setting-up of National
Institute for Teacher Education.
(ix) Development of National Teachers Platform(DIKSHA)
(x) Technology support to TEIs
(xi) Residential Training Programmes of Teacher Educators, DIET Principals,
Head Masters and Master Trainers
(xii) Academic support of Block Resource Centres (BRC) and Cluster
Resource Centres (CRC) to schools at all levels.
XV. Programme Management
1.4 Implementation Structure: At the national level, the composition of Governing
Council would be as mentioned at Appendix 1. The composition of Project
Approval Board has been incorporated at Appendix 2. In case of States/UTs, the
composition of Governing Council/Body and Executive Committee would be as
far as possible be as at Appendix 3 and Appendix 4 respectively.
1.5 Financial Management: Financial management brings together planning,
budgeting, accounting, financial reporting, internal control, audit, procurement,
disbursement and the physical performance of the Scheme with the aim of
managing Scheme resources properly and achieving the scheme’s objectives.
Sound financial management is a critical input for decision making and for
Scheme success. Timely and relevant financial information provides a basis for
10
better decisions, thus speeding up the physical progress of the Scheme and the
availability of funds and reducing delays and bottlenecks.
1.6 The Financial Management system should produce timely, relevant and reliable
financial information that would allow Scheme managers and State/Central
governments to plan and implement the scheme, monitor compliance with agreed
procedures, and appraise progress toward its objectives. To meet these
requirements, the system should include the following features:
(a) Planning – A system to identify the needs to achieve the Scheme
objectives, evolve strategies and approaches to address them and take up
suitable interventions and activities.
(b) Budgeting – A system to identify the short-term activities necessary to
achieve the Scheme objectives and express these activities in financial
terms.
(c) Accounting – A system to track, analyze, and summarize financial
transactions.
(d) Funds flow arrangements – Appropriate arrangements to receive funds
from all sources and disburse them to the agencies involved in Scheme
implementation.
(e) Reporting – A system that would produce sufficient detailed information
to manage the Scheme, and provide each level of scheme management
with regular consolidated financial Statements for decision making.
(f) Internal control – Arrangements including internal audit, to provide
reasonable assurance that (i) operations are being conducted effectively
and efficiently and in accordance with financial norms (ii) financial and
operational reporting are reliable; (iii) laws and regulations are being
complied with; and (iv) assets and records are maintained.
(g) External audit- Arrangements for conducting annual external audit of the
Scheme on Terms of Reference agreed upon with the Government of
India, through a statutory audit. Audit through Comptroller and Auditor
General of India is also envisaged in terms of the provisions of
Comptroller and Auditor General of India (Duties, Powers and Conditions
of Service) Act, 1971 as amended from time to time.
(h) Procurement – A system to carry out procurement of goods, works and
services keeping in mind the considerations of economy, efficiency,
transparency and equal opportunities to all.
(i) Financial procedures manual – A manual that sets forth the Scheme
financial policies and procedures for the guidance of all personnel charged
with financial responsibilities, with the aim of ensuring that Scheme
resources are properly managed and safeguarded.
(j) Financial management staffing – Appropriately qualified financial
management staff, including accounting and internal audit staff, with
clearly defined roles and responsibilities to conduct financial management
activities.
11
1.7 Applicability:
The manual is mandatory for all the activities under the Scheme at all levels of
implementation. No deviation from the manual is permitted. While the provisions
outlined in this Manual are mandatory, the State Implementing Society shall
formulate well-defined Financial Rules and Regulations including the delegation
of financial powers for effective implementation. Rules, Regulations and
procedures outlined in this document should be formally adopted by the
Executive Committee and Financial Rules and Regulations framed in accordance
with the provisions of this Manual.
Further, the Scheme Manual strictly follows the GFR 2017 and in case of any
contradiction, GFR 2017 will prevail.
12
CHAPTER-2
PLANNING PROCESS AND FINANCIAL PLANNING
2.1 Planning may be termed as a continuous process that helps us to reach a particular
goal or objective in the shortest and the best possible way. Plans are not static.
They look at progress of the previous years and adapt to change themselves to the
current situation. Planning, therefore, helps to achieve better results within the
limited resources.
2.2 Objectives of Planning: The main objective of the planning process is to provide
an insight into various aspects of planning and provide assistance and guidance for
the preparation of need based plans. It should be ensured that these provisions are
strictly followed while preparing the plans.
Planning must:
Take into account the local conditions of the area for which the plan is to be
made;
Help in expanding access to education;
Be able to provide an effective strategy to retain enrolled students till
completion of schooling;
Help students graduate with the knowledge, skills, attitudes, and experiences
needed to exercise their choices beyond secondary education, and
Ensure equity with respect to gender, CWSN, SCs, STs, OBCs and minority
communities.
2.3 Steps in Planning:
The planning process shall be carried out through the following steps:
Formation of core planning teams at district and school level.
Training and orientation of these teams.
Assessment of need for information and preparatory exercises for micro
planning and household surveys.
Collection of various data, undertaking surveys and baseline studies.
Visits of core teams to habitations/schools, interaction with community and
consultative meeting ensuring participatory planning.
Draft District plan formulation by consolidating the habitation/school plans,
costing as per norms and discussions in the consultative meetings.
Appraisal of the District Plan at the state level and their consolidation to prepare
the State Plans.
2.4 Perspective Plan and Annual Plan:
2.4.1 There would be a State component plan, both perspective and annual, for
universalization of education within the stipulated time frame. The District level
Plans should be consolidated at State level and furnished in the State component
plan along with the analysis to show inter-district variations on various items.
13
2.4.2 The profile of the State should be so comprehensive so that it gives a clear picture
of the State. It is necessary that the information contained in the State plans has
adequately covered all the important aspects of the State.
2.4.3 Annual plans need to be seen as a complement to the Perspective Plans.
AWP&Bs should detail out for each year, in the context of the goals of the
Perspective Plans, what is the progress and what are the future strategies.
Therefore, to prepare annual plan, it is necessary to know the Perspective Plans of
the district well. District planning teams need to understand and discuss the
Perspective Plans of their districts before planning for the AWP & B.
The Annual Work Plan should be realistic and correlate in financial and physical
terms.
2.5 Methodology of Planning
2.5.1 Identification of Planning Teams: The selection of suitable persons for
inclusion in the planning teams is perhaps the most crucial element in the plan
formulation. Programme envisages constitution of core planning teams at village,
block and district levels. The grassroots level team in each village/habitation has
to provide wider representation to grassroots level structures including PRIs and
VEC, community leaders, teachers and parents. The aim of constituting this team
is to involve all the stakeholders in the education of the children. Similarly, there
should be a core planning team at the block level. There should be a core team of
dedicated persons at the district level to formulate the plans to be supported, if
possible, by a larger team at the district level. This advisory body at the district
level should have representatives of various Departments like - Education, Health,
Public Works, Social Welfare, Women and Child Development, Tribal Welfare,
PHED, NGOs, etc. This will ensure "convergence" and help remove bottlenecks,
if any, not only in collection of information but also at the time of
implementation.
It will be the responsibility of the core district team to develop the plans as per the
procedure laid down in the Scheme framework by prioritising the various
proposals emanating from various levels. At least one person each in the Core
Team should be well acquainted with finance and procurement procedures, and in
Government functioning especially in the field of education. Other members of
the team should have an adequate knowledge of socio-educational scenario
prevailing in the districts.
2.5.2 Participatory Planning Process: Scheme envisages a bottom-up approach of
planning as opposed to the top-down approach, as it reflects the reality at the
grassroots level. The planning process has to be participatory in nature, as
planning not only creates a sense of ownership among the stakeholders but also
creates awareness and helps in the capacity building of personnel at various
14
levels. The plans so developed should reflect local specificity and educational
needs and aspirations of the people based on consultative meetings and interaction
with the community and target groups. It is necessary that there should be
documentation of the process of the preparation of habitation level plan as
evidence of the fact that they have been prepared at the habitation level through
participatory planning.
2.5.3 Interaction with community and target groups: The process of bottom-up
planning will not only help the planning team to acquaint themselves with various
problems, but will also provide various solutions. The commonality of problems
across such meetings will help the planning teams to propose interventions
accordingly. Such interactions with community and target groups not only
provide an opportunity to be familiar with the problems of target groups and help
in devising strategies to deal with these but also mould the opinions of
communities with the help of the good offices of community leaders.
2.5.4 Consultative meetings: The consultative meetings with the officials at block and
district levels would facilitate the core teams in formulating strategies to address
the problems. These meetings would also help in bringing about “convergence”
and establish linkages with various interventions proposed by different
departments. As the responsibility of implementing the programme rests with the
educational administration of the district, it is essential to involve them from the
planning stage itself.
Documentation of consultative meetings and community interaction would enable
the persons at the district and State levels as well as the appraisal teams to know
about planning processes.
2.6 Educational profile
2.6.1 The objective of presenting the State education scenario is to undertake a
diagnosis of the educational situation in the State, so the data presented in this
section should aim at understanding the educational scenario and present the
strengths and weaknesses as well as problems and constraints of the State with
regard to all stages of education.
2.6.2 The State educational profile section should contain write-ups on (i) educational
administration in the state; (ii) educational facilities at various levels; (iii) State
and centrally sponsored schemes implemented in the state; (iv) details of
externally funded schemes; (v) District Institute of Education and Training; (vi)
problems and issues of school education in the state.
2.6.3 The presentation of education scenario in the state should contain information on
the following items for proper diagnosis of the educational situation:
15
(i) District-wise number of schools/sections for education.
(ii) District-wise access position on education in the state.
(iii) District-wise number of teachers in the schools with the following
categorization:
(a) Trained/untrained teachers
(b) Male/female teachers
(c) SC/ST teachers
(d) Teacher-pupil ratio
(e) Number of sanctioned posts and vacant posts (for rationalization
and requirement of additional teachers)
(iv) District-wise Enrolment at schools in the state
(a) Grade-wise enrolment
(b) Enrolment by gender and social categories i.e. boys, girls, S.C., S.T.
etc.
(c) Gross and Net Enrolment Ratio: boys, girls, S.C., S.T. etc.
(v) District-wise dropout, repetition and transition rates disaggregated as per
levels of education and for boys, girls, SC, ST. etc.
2.7 Mode of Submission of Plans: AWP&B will be submitted online through Project
Monitoring System (PMS) by respective States/UTs. Each State/UT will enter the
proposed Budget of each activity under various components online.
States/UTs to ensure that uploaded AWP&B along with the other supporting
documents are duly signed.
2.8 Budgeting: Preparation of proper budget plays an important role in timely
implementation of any project. Budgeting involves identifying specific tasks and
objectives of the project to be achieved in a time frame and express these
activities in financial terms. Budgeting without planning or planning without
budget estimation has no meaning. So, planning and budgeting are interrelated
with each other.
2.8.1 Each district shall prepare an Annual Work Plan of action indicating, inter-alia,
the physical targets and budgetary estimates in accordance with the approved
pattern of assistance under the scheme covering all aspects of the project
activities for the period from April to March each year.
2.8.2 The budget proposals under Scheme has to be prepared in the form of AWP&B,
covering all the interventions specified in the Scheme norms. The AWP&B
proposals have to be in two parts, the plan for the current financial year (fresh
Proposal) and the balance of the approved activities proposed to be carried over to
the current year from the previous year.
2.8.3 The Costing sheet / Budget for AWP&B are to be prepared online through Project
Monitoring System (PMS) for all activities under various components of Scheme.
16
2.9 Progress Overview: Since AWP&B proposals are part of a continuing
programme they have to be based on progress made as well as the goals that
remain to be achieved. Therefore, a progress over view of each intervention under
all components of Scheme is extremely important. The activity wise progress
overview includes the progress made during the previous year, which is a tool for
the district to understand its strategies, the positive and negative aspects that will
enable the district to plan better for the forthcoming year. The progress may be
submitted online through Project Monitoring System (PMS) on monthly basis
under various components of Scheme.
2.10 Outlay Saved/Spill Over: In a particular year, if an allocation approved is not
spent fully, the same becomes outlay saved. Normally, outlay saved under non-
recurring heads for preceding year is taken as spill over activities in the
subsequent year. Outlay Saved allows a State to continue activities of non-
recurring nature such as construction of new schools, strengthening of existing
schools (civil works), construction of Girls Hostel, construction of
Workshops/Laboratory under Vocational Education, etc., which could not be
completed during the year. Every year, each State needs to prepare an outlay
saved/spill over plan along with the AWP&B and accordingly grant of fresh civil
works would be considered taking into account progress of works in the previous
years.
2.11 Fresh Proposal: To achieve the targets set by each district, a certain set of
strategies / interventions are planned. These are reflected in the budget sheet with
details like unit cost, physical targets and the budget estimate under the head of
fresh proposal.
2.12 Total Proposal / Allocation: In a particular year, the total allocation for the State
is sum of fresh proposal/allocation and Spill Over budget.
Total Proposal/Allocation of AWP&B= Fresh Proposal+ Spill Over
2.13 Budgeting under different Components:
2.13.1 The present manual should be read with:
(i) The Scheme framework for implementation;
(ii) Planning and Appraisal Manual for Education
(iii) Manuals / guidelines/ frameworks for different functional areas brought out
from time to time; and
(iv) Policy decisions taken at Project Approval Board meetings from time to
time. All manuals and guidelines under the Scheme are available on
mhrd.gov.in.
2.13.2 States/UTs to Plan their Budgets, activity wise, based on the activities prescribed
from time to time under various components of Scheme.
17
2.14 Convergence:
Planner should look into different sources of funds that may be utilised to fund
different strategies planned for school. Before budget is prepared for the Scheme,
a detailed convergence plan should be prepared. Activities which could be funded
from other sources may be budgeted under the scheme. Different sources of funds
that may be available from different departments of the State government,
different schemes run by State and Central government, public-private partnership
opportunities, corporate social responsibility initiatives, MP’s / MLA’s funds etc.
Dovetailing of funds should be encouraged. Budgeting process should indicate
the amount of extra funds for secondary schools coming from other schemes of
the Central and the State government.
18
CHAPTER-3
Financial Management, Fund Flow & Reporting
3.1 Financial Management
Allocation of Resources:
Budget allocation to the States and UTs under the Scheme would be made
considering the annual budget allocation for the scheme at central level and the
viable proposals received from the States and UTs as per norms. The State Plans
will be appraised and placed before Project Approval Board for approval of
State’s target along with the budget for that year. The budget allocation to
States/UTs would mainly depend on all these factors:
(i) Commitment from the State Government with regard to the State Plan, its
institutional pace and financial share;
(ii) Performance of the State in previous years;
(iii) Reports of supervision teams regarding the quality of programme
implementation;
(iv) Availability of financial resources in a particular year.
(v) Districts with huge gaps to get priority
(vi) Non recurring fund allocation would be estimated on the basis of
Enrolment in Government Schools.
(vii) Performance of the States/UTs on learning outcomes and steps taken for
improving the quality of education.
(viii) Preference in the interventions would be given to Educationally Backward
Blocks (EBB), Border Areas and the Aspirational Districts identified by
NITI Ayog, time to time and LWE Districts would also be considered.
3.2 Perspective Plans and Annual Work Plan and Budget
3.2.1 Each district has to prepare a Perspective Plan up to 2019–2020 based on the data
collected through household survey through a micro planning exercise. Keeping
the Perspective Plan in view, AWP&Bs will be prepared every year. There is a
need each year to take stock of achievements as well as constraints and then plan
ahead. It follows that annual planning is a step in the process of continuous
assessment of the situation and identification of appropriate strategies and
activities for achieving goals of the scheme.
3.2.2 Annual plans need to be seen as a complement to the Perspective Plans.
AWP&Bs detail out for each year, in the context of the goals of the Perspective
Plans, what is the progress and what are the future strategies. To make annual
plans therefore, it is necessary to know the Perspective Plans of the district well.
District planning teams need to understand and discuss the Perspective Plans of
their districts before planning for the AWP&B. The AWP&B proposals are
envisaged in two parts, the plan for the current financial year and the progress
19
overview of the previous year including the spill over activities proposed to be
carried over to the current year.
3.2.3 District Plan Proposals covering all the interventions specified in the norms of
Scheme would be submitted to the concerned State implementing society (SIS).
The State Implementing Society would consolidate all district Perspective Plans
as well as Annual plans and forward the consolidated State Plan to the National
Mission after getting approval of the Executive committees. The Plans would be
submitted online along with the e-costing on Project Monitoring System (PMS).
3.2.4 Costing of AWP&B for the interventions, its progress overview, spill over of the
previous year, physical and financial target proposed, can be generated from the
Project Monitoring System (PMS).
3.2.5 The Technical Support Group of National Mission will appraise the Plans. The
Project Approval Board (PAB) of the National Mission will approve the Annual
Work Plan & Budget (AWP&B) on the basis of the Proposal of the State
Government, Appraisal Report, the availability of Central Plan funds, and the
commitment of the State government regarding financial resources. The Central
Government will release the funds to the State Government for further release to
the State Implementation Society, alongwith the State share as per prevailing
sharing pattern.
3.3 Preparation of Perspective Plans and Annual Work Plan and Budget
3.3.1 The scheme Framework envisages financial norms under various interventions.
While proposing outlays under various interventions in the plans, these financial
norms should be strictly adhered to. Upper limit for unit costs for most of the
interventions have been prescribed in the financial norms, and it should be
ensured that outlays proposed for each intervention are based on these prescribed
unit costs. The States/UTs can priorities the interventions as per their
requirements and adjust the unit costs also accordingly within the overall ceiling.
3.3.2 Outlays proposed under each intervention are to be supported by relevant data to
determine the physical targets. It should therefore be ensured that relevant data in
support of the physical targets for each intervention is provided in the plans.
3.3.3 The State/UT Governments to ensure that the Central funds are transferred to the
SIS within fifteen days from the date of receipt of funds. Each State/UT is also
required to ensure that the corresponding State share is released within 30 days
from the release of central share, as per the approved sharing pattern. The States
would also ensure that the funds allocated to Scheme would not be used for any
other purposes under any circumstances.
20
3.4 Procedure for Release of Funds
3.4.1. It would be the endeavor to complete the appraisal and approval of Plans in time
for the first installment, to meet the proposed expenditure for the first six months,
to be released in the 1st quarter. However, it will depend upon the preparation of
annual plan proposal by the State Governments/UTs and holding of the PAB
Meetings.
Government of India would release adhoc grant during the month of April-May
upto 25% of the expenditure incurred under the Scheme against recurring
activities of the previous year. However, the amount would be released after
adjusting unspent balance of recurring grant of the previous year. The States/UTs
may utilize the unspent balance of previous year for the recurring activities
approved during the current year.
3.4.2 There would be two installments each year and the adhoc release would be
considered as part of the first installment. First installment would cater to the
expenditure from April to September and the second installment for expenditure
from October to March.
3.4.3. First installment for recurring grant would constitute upto 75% of the total amount
sanctioned for the year. The First installment would be released after receipt of
the Utilisation Certificates on provisional basis for the preceding year (proforma
at Annexure-I). For releases in excess of 75% of total amount sanctioned
(recurring grant) in the subsequent financial year shall be done only after the
Utilisation Certificate and the annual audited statement relating to the preceding
year are submitted to the satisfaction of the Ministry. Monthly progress report and
previous year expenditure statement should be submitted online on Project
Monitoring System (PMS).
3.4.4 In case of non-recurring grants, the sanctioned funds would be released after
receipt of expenditure statement commensurate to the physical progress made
upto last month. First installment for non-recurring grant would constitute upto
50% of the total amount sanctioned for the year. The First installment would be
released after receipt of the Utilisation Certificates on provisional basis for the
preceding year (proforma at Annexure-II). However, the release would depend
upon the physical progress of civil works sanctioned in previous financial years
and the availability of unspent balance. Also, priority would be given for
completion of works in progress than starting of new works. In this regard,
detailed activity wise Physical progress and expenditure Statement would be
submitted online through PMS by the respective States/UTs. After the period of
12 months from the preceding year, if the Utilisation certificate is not received,
there shall be no release of funds, till receipt of the annual audited statement and
Utilization Certificates.
3.4.5 The Expenditure Statement from school/SMDC/SMC for all the expenditure
incurred till 31st March should be submitted to their respective DPOs within 1
month of closure of the financial year. On the same line, the DPOs shall have to
21
submit the expenditure Statement based on the expenditure statement received
from SMDC/SMC or other fund receiving agencies within 15 days of receipts of
such certificates.
3.4.6 After utilizing at least 50 per cent of the funds released in the first installment of a
financial year and after the approval of Executive Committee of the SIS, the State
Implementing Society may apply to the Ministry of Human Resource
Development for the second installment of the financial year under intimation to
the State Government. The tranche release arrangements will be as per the Table-
1 below. The release will be subject to the following conditions:
(i) Submission of expenditure statement showing that at least 50 per cent of
funds/resources already released have been utilized at the time of submission of
the proposal for the second instalment in a financial year.
(ii) Submission of certificate regarding the release and receipt of the State
Share against the amount of the Central funds released so far. This must be
accompanied with a copy of the order sanctioning the State share.
(iii) Any other condition indicated from time to time.
3.4.7 Unspent balance of funds under central share of Recurring Grant lying with the
implementing agencies at the end of the financial year, if any, shall be carried
over to the next financial year for utilization against recurring activities
sanctioned by PAB during the next year. The carried forward amount will be
adjusted against the Central share of recurring grants due for the next year.
3.4.8 With regard to the reimbursement claims against recurring grant, The General
Financial Rule (GFR) No. 230 (15) provides that “Grants-in-aid may be
sanctioned to meet the bona fide expenditure incurred not earlier than two year
prior to the date of issue of the sanction.” Therefore, no reimbursement of
recurring expenditure older than two years will be funded by the Central
Government. As PAB considers fresh proposals and spill over both in Annual
Work Plan & Budget, reimbursement would be provided subject to approval of
PAB at the time of consideration of AWP&B.
Table 1: Tranche Release Arrangements
Tranche Timing
Conditions Precedent
1. Release of Adhoc Grant (Recurring):
Adhoc release upto 25% of the expenditure
incurred under the Scheme against recurring
activities of the previous year after adjusting
unspent balance of GoI share (Recurring)
available with the State/UT as on 31st March.
The States/UTs may utilize the unspent
balance of GOI share (recurring) of previous
Financial Year for the approved recurring
activities of subsequent financial year.
Beginning
of financial
year
There would be no conditions precedent to
the adhoc releases. However, the
expenditure incurred during the previous
Financial Year and unspent balance as on
31st March be uploaded on PMS latest by
10th of the April of the next Financial year.
22
Tranche Timing
Conditions Precedent
Release of First Installment
(A) Recurring Grant: First installment would
be considered upto 75% depending upon the
availability of the central budget and the
requirements of the States
However, the adhoc releases and closing
balance of GoI share of the previous FY as
on 31st March would be adjusted in the first
installment.
After PAB
Approval
Regarding release of first instalment, the
following are conditions precedent
Proposal for release of first installment to
be received from State Government
Approval of Annual Plans by PAB;
Transfer of GOI share of previous year
to SIS from State Treasury;
Release of commensurate State share
for previous year; and release of full
GOI share of ad-hoc release of Central
Government to SIS along with
matching State share by State
Government.
Submission of provisional UC for
previous year. The utilization
certificate should be duly
countersigned by the Administrative
Secretary/ Finance Secretary
Confirmation of state towards
provisions of matching State share in
the State Budget
Provisional Expenditure Statement of
the current year
Statement of Outstanding advances
Accrued ,adjusted and pending till date
(B) Non-Recurring Grant: First installment
would constitute upto 50% of the grant
sanctioned during the Financial Year (FY).
However, the closing balance of GoI share
of the previous FY as on 31st March would be
adjusted in the first installment.
After PAB
Approval
Regarding release of first installment, the
following are conditions precedent
Proposal for release of first installment
to be received from State Government.
Physical Progress report for previous
year (upto 31st March)
Approval of Annual Plans by PAB
Release of GOI share of previous year
to SIS from Treasury and
commensurate State share for previous
year and release of full GOI share of
ad-hoc release of Central Government
to SIS along with matching State share
by State Government. .
Submission of provisional UC for
previous year. The utilization
certificate should be duly
countersigned by the Administrative
Secretary/ Finance Secretary
23
Tranche Timing
Conditions Precedent
Confirmation of state towards
provisions of matching State share in
the State Budget
Provisional Expenditure Statement of
the current year
Statement of Outstanding advances
accrued adjusted and pending till date
Release of Second Installment
(A) Recurring Grant: Balance of funds
eligible for release after adjusting the adhoc
releases, first instalment releases and unspent
balance of previous FY.
Regarding release of Second installment,
the following are conditions precedent:
Proposal for release of second installment
to be received from State Government
Request letter from State Govt./UT for
release of 2nd installment.
At least 50% utilisation of the
cumulative fund available under GoI
releases.
Release of GOI share from previous
installment to SIS from Treasury.
Release of commensurate State share
release of full GOI share of 1st
installment release of Central
Government share to SIS along with
matching State share to SIS by State
Government.
Submission of Annual report of one
year prior to previous financial year.
Submission of Audit report of Previous
FY- alongwith Separate audited UC
for Recurring (General Head) is
mandatory The utilization certificate
should be duly countersigned by the
Administrative Secretary/ Finance
Secretary.
Submission of provisional UC upto
previous month of the concerned year.
Expenditure statement of the current
FY.
Statement of Outstanding advances
accrued adjusted and pending till date.
(B) Non-Recurring Grant: Balance of funds
eligible for release after adjusting the first
installment release and unspent balance of
previous FY.
Regarding release of Second installment,
the following are conditions precedent:
Request letter from State Govt./UT for
release of 2nd installment.
24
Tranche Timing
Conditions Precedent
At least 50% utilisation of the
cumulative fund available under GoI
releases.
Release of GOI share from previous
installment to SIS from Treasury.
Release of commensurate State share.
Submission of provisional UC upto
previous month of the concerned
current year and Expenditure statement
of the previous releases during the FY.
Submission of Annual report of one
year prior to previous financial year.
Submission of Audit report of Previous
FY alongwith Separate audited UC for
Non-Recurring (Capital Head) is
mandatory The utilization certificate
should be duly countersigned by the
Administrative Secretary/ Finance
Secretary.
Physical progress upto the preceding
month of the month of submission of
request for 2nd installment.
Apart from the above conditions precedent
for release of Grants it may be noted that
any provisions of GFR 2017, as amended
from time to time may have be fully
complied at the time of release of any
installment as grant in aid.
3.5 State Government to State Implementing Society
3.5.1 The financial norms of the programme envisage that the participating State would
contribute its agreed ratio of the programme cost within 30 days of the receipt of
the central contribution as per the approved sharing arrangement. It would
therefore be necessary to make suitable provision in its budget to facilitate the
release of its share of programme cost to the State Implementing Society.
Similarly, now that central funds are routed through the State Treasury, it would
be necessary to make suitable provision in the budget of the State Governments to
facilitate release of Central share by the State Government to the State
Implementing Society. The release of funds by the State Government to the State
Implementing Society from out of provision in the State Government’s budget
would also be deposited in the same joint signatory bank account of the Society in
which the funds of the Government of India are deposited under the Scheme. Any
unspent balance from out of the Central or State Government’s share of funds
25
shall be carried forward by the Society for utilization in the next financial year
with the approval of the State Government. In case of delay in transfer of funds to
State Implementing society further installments could be released only on transfer
of GOI grants to SIS including proportionate state share by the State Govt. and
Moreover, GFR 2017 would be invoked in case-to-case basis regarding penalty to
be imposed.
3.5.2 The State Implementing Society shall open a joint signatory savings bank
accounts with any Nationalised or Scheduled Commercial Banks. Funds would be
transferred to district and schools level bank accounts from this account only.
Separate accounts/records for funds earmarked for SCSP and TSP plans be
maintained by the States/UTs with the objective to monitor utilization of funds
under SCSP and TSP Heads.
3.5.3 The expenditure from the State Implementing Society account for the financial
year under different budget heads would be assigned on the basis of the final PAB
approval.
3.5.4 The recurring grants such as annual school grant, shall be transferred directly to
the school account immediately after the receipt of the first instalment by the
State Implementation Society. The MMER for the district office should also be
transferred from the first instalment.
3.5.5 Civil works at the school level would be approved by appropriate authority and
information will be sent to the State Implementing Society. Funds would be
transferred to the school electronically for full or part payment of completion of
approved works from the State Scheme account.
3.5.6 Teacher training and other activities under the AWP&B carried out by district
level office would be approved at the state level and funds would be transferred
from the State Implementing Society account on receipt of the demand.
3.5.7 The Financial Management Information System would have an electronic
repository where all budget heads from the school level upwards would be
aggregated as per the AWP&B, and expenditure will be booked against them at
the school, district and state levels.
For the accountability of transactions of funds under Scheme, registration of all
the agencies should be done on Public Financial Management System (PFMS) at
State/District and School/SMDC/SMC level. The State/UT should strive to adopt
PFMS at the earliest and MHRD would provide capacity building if required.
26
3.6 Funding Pattern
3.6.1 The current fund sharing pattern for State governments and UTs with legislature
is 60(Centre):40(State). In case of North Eastern States (Arunachal Pradesh,
Assam, Manipur, Meghalaya, Mizoram, Nagaland, Sikkim, and Tripura) and the
Himalayan States (Himachal Pradesh, J&K and Uttarakhand), sharing pattern
between Centre and State would be 90(Centre):10(State). For Union Territories
without legislature, 100% share will be given by the Centre. Any subsequent
changes in this regard will be notified by MHRD from time to time.
3.6.2 Fund flow arrangement for various activities:
(a) Civil Works upto Rs. 30 lakh may be undertaken through
SMCs/SMDCs
GOI →State Govt.→ SIS → SMDC/SMC → Community or contractor
Or
GOI →State Govt.→ SIS → DPO → SMDC/SMC → Community or contractor
(b) Major Civil works beyond Rs. 30 lakh, could be executed through an
external agency (which could be PWD or a State level agency or contractors at
state level selected through competitive bidding).
GOI →State Govt. →SIS → DPO → External Agency
Or
GOI →State Govt. → SIS → External Agency
For activities at school level which are contracted at State or district level, the
SMDC/SMC should be provided a copy of the contract as well as copy of the
work order in order to be able to monitor the works effectively. The feedback
provided by the SMDC/SMC shall include (a) a confirmation that they have been
provided with a copy of the contract; (b) a copy of the latest Measurement Book
and whether it has been finished as per specifications; (c) comments on
commencement and completion of the work; (d) shortcoming perceived by the
SMDC/SMC in the work, if any. Except 1st instalment as advance, all further
instalments will be released on the receipt of the written feedback from
SMDC/SMC. Further, the fund flow mechanism will be effectively monitored
through PFMS which includes intervention-wise details and there would be no
possibility of diversion of funds.
27
3.7 Financial Reporting:
3.7.1 Project expenditure will be reported on monthly basis by State Implementation
Society on PMS.
3.7.2 The reports to be prepared and submitted are summarized at Table 2 below.
Table 2: Type and Date of Reports for States/UTs
S.
No.
Report Date on which to be
sent
Remarks
1. Monthly
Financial
Report
By 5th of next month The Consolidated Financial Report of the
States/UTs shall be uploaded on PMS on
due date to GOI without fail. The reports
of the districts not received by SIS on time
would be excluded and will be included in
the financial report of the next month. The
timelines of submission would be
monitored and entered in the evaluation
sheet of state Finance in charge/TSG by
the SIS.
Provisional UC to be submitted online
through PMS.
2 Audited
Statement
of
Accounts
and Audit
reports of
SIS
By1stNovember
following the end of the
relevant financial year
The timelines of submission will be
monitored and entered in the evaluation
sheet of State Project Director by the SIS.
Action taken report on the deficiencies
pointed out by the Audit to be submitted to
the MHRD within a period of three months
from the date of receipt of the report.
After submission of Audited Statement of
Accounts, States/UTs should update the
audited figures on PMS for the month of
March.
3 Utilisation
Certificate
By1stNovember along
with the
Audited statements
There would be separate Utilisation
Certificate (UC) for the funds released
under the head grant-in-aid and grant for
creation of assets during a particular year.
4 Annual
Report
Till 30th Nov. A progress report will be submitted
detailing the status of physical and financial
progress as per the Annual Work Plan and
audit report. The annual report should also
detail the critical issues that should be
addressed to ensure efficiency in fund flows
and implementation of scheme in the State.
28
CHAPTER-4
ACCOUNTING
4.1 Complete accounts in respect of the monetary transactions of the State
Implementation Society in the Headquarters as well as in the Subordinate Offices
shall be maintained. However, the “Double Entry Method Based on
Mercantile System” of accounting shall be followed under Scheme.
4.2 The following books of accounts and registers shall be maintained by the Society:
(a) Cash Book
(b) Ledger
(c) Journal
(d) Register for Journal / Magazines / News Papers
(e) Register of Advances
(f) Register of Bank drafts received
(g) Cheque issue register
(h) Register of remittances made into the Bank
(i) Bank Pass Book/Bank statement
(j) Register of bank drafts dispatched
(k) Bill Register
(l) Establishment Register
(m) Stock Register
(i) Capital Goods
(ii) Non-consumable articles
(iii) Consumable articles
(n) Register of works
(o) Register of grants of advances to mobilizing agencies/NGOs/Voluntary
Agencies
(p) Fixed Assets Register
(q) Register of Investments
(r) Classification accounts of the Project
(s) Monthly accounts of Receipts and Payments
(t) Temporary Advance Register
(i) staff
(ii) contractors/suppliers/VEC
(iii) TA/DA advance
(u) Despatch Register
(v) File Register
4.3 Any other books and accounts which may be considered necessary for the day to
day working of the Society shall also be maintained with the approval of the State
Project Director.
4.4 The Name of the district should be indicated against each entry in the cashbook
for the purpose of preparation of district-wise accounts.
29
4.5 At the end of the month, the District-wise abstract should be prepared showing
monthly expenditure in respect of each district.
4.6 A consolidated Register shall also be maintained indicating the progressive
expenditure from month to month in respect of each district.
4.7 Monthly reporting of Physical progress and Component wise Expenditure may be
done on the online portal of Project Monitoring System (PMS).
4.8 Ledgers and receipts / invoices should be maintained at all levels of expenditure.
4.9 Where VECs or other village organisations are receiving and utilizing funds,
records shall be maintained there as well as at district level.
4.10 These records and receipts / invoices shall be available for inspection by the
Auditors, State Implementing Society, State Government and Government of
India.
4.11 Consolidated records of receipts and expenditures shall be kept at district and
State levels.
4.12 The Society should maintain Register of Assets in the format given in Annexure-
III for the assets acquired wholly or substantially out of Government of India
grants and Stock Register separately for capital goods, consumable and non-
consumable articles and shall arrange for their physical verification at least once a
year. These should be maintained at school, CRC, BRC, DPO and SPO levels as
the case may be. The relevant abstract of Register of Assets should be appended
to the annual statement of accounts submitted by the Society to the Government
of India. The register of abstract shall contain progressive figure both stores and
value.
4.13 The maintenance of accounts of the Programme should be governed by the
principle that no expenditure is incurred by the Society which is repugnant to the
objectives of the Programme and every item of expenditure which is incurred is in
accordance with the prescribed procedures, and the canons of Financial Propriety.
4.14 In accordance with these Canons of Financial Propriety, it shall be the duty of
each official of the SIS to ensure that:
(i) Every Government servant is expected to exercise the same vigilance in
respect of expenditure incurred from Public Money as a person of ordinary
prudence would exercise in respect of expenditure of his own money;
(ii) The expenditure should not be prima-facie more than the occasion
demands;
(iii) No authority should exercise its powers of sanctioning expenditure to pass
an order which will be directly or indirectly to its own advantage;
(iv) Public moneys should not be utilised for the benefit of particular persons
or section of the people unless: -
A claim for the amount could be enforced in a Court of Law, or
The expenditure is in pursuance of a recognised policy or custom.
30
(v) The amount of allowances granted to meet expenditure of a particular type
should be so regulated that the allowances are not on the whole a source of
profit to the recipients.
4.15 It shall be the duty of the Accounts Wing in the State Society to ensure strict
observance of these Accounting Principles.
4.16 It shall also be necessary for every Society to establish adequate and satisfactory
Internal audit functions.
4.17 Any grant or portion thereof given by the Government of India or the State
Government to the Society for a specific purpose shall not be re-appropriated,
without the previous sanction of the granting authority to a purpose other than that
for which it was originally approved.
4.18 Grant Received by the State Societies from State Government both Central and
State share under the Scheme will be deposited in a Joint Signatory Savings Bank
Account established by the State Implementing Society in any nationalised or
scheduled bank.
4.19 The Executive Committee of the State Society would be empowered to open Joint
Signatory Savings Bank Accounts in any nationalised or scheduled bank,
authorise a Drawing and Disbursing Officer to operate the accounts and delegate
financial functions to State, District, Block, Village and School levels.
4.20 In respect of releases by the State Societies to the districts, Joint Signatory
Savings Bank Accounts would be opened in any nationalised or scheduled bank at
the district level and in any such banks or Post offices at the block and village
level.
4.21 Advances
(i) All funds released to the districts and sub-district level units are initially
classified as advances and the same indicated as such in the books of
accounts. These advances shall be adjusted based on the expenditure
Statements/utilisation certificates received in State Implementation
Society of having spent the funds. Advances, if not actually spent for
which accounts have not been settled, should be shown as advances and
not as expenditure. Similar procedure shall be followed for funds released
at district and sub-district level.
(ii) The adjustment of advances should be included in the financial year to
which the grant relates.
(iii) The advances released to SMDCs/SMCs for undertaking Non Recurring
activities which remains unspent at the end of the year shall be carried
over to next year as spillover activities/unspent balance based on the
approval of the PAB.
31
4.22 Advance Register
(i) All advances are to be entered in the advance register to be maintained as
per specimen given in Annexure-IV.
(ii) The adjustment of the advances is also to be entered promptly in this
register. It should be ensured that no personal advance is outstanding for
more than one month. In case, adjustment claims for personal advances
are not submitted in time, penal action including charging of interest
should be taken.
(iii) A Statement showing outstanding advances of previous years will be
submitted with the audited accounts as per format at Annexure-V
4.23 Account Head
The Account head and account code should be similar to the Budget Head
and Budget Code. This should correspond to the interventions and the
norm number prescribed in the framework. If any sub-head or sub-code is
considered necessary, the same shall be operated accordingly.
4.24 Cash Book
(i) Cash book is the principal record of all money transactions which take
place every day and all other registers are subsidiary to it.
(ii) Cash book should be maintained under Double Entry System. However, as
an exception, single entry system shall be followed at Cluster and
VEC/School level.
(iii) It has two sides, “Receipts” and “Payments”. The amount column in each
side is sub divided into “Cash” and “Bank”.
(iv) Separate cashbook should be maintained at State/District/Block level for
each financial year.
(v) Each entry of receipt and expenditure should be descriptive but brief in
nature.
(vi) Each voucher should be assigned a serial number and Ledger Folio
number, which should be noted against each entry in the cashbook.
(vii) Each entry in the cashbook should be attested by the Head of
Office/Drawing and Disbursing Officer (DDO).
(viii) Cash book should be closed daily and total cash balance struck and
attested by the Head of Office / DDO after verification of the totals.
(ix) All cash/cheques/Demand Drafts etc. received should be deposited into the
bank as far as possible on the same day itself or next day positively so as
to avoid cash in transit for long periods. If any cash is retained on hand
that should be verified physically by the Head of Office/DDO and
recorded in the cash book and the cash in hand deposited into bank next
day itself.
(x) When cash/cheque/DD is paid into the bank, the counterfoils of the pay-
in-slip should be verified with the cashbook by the Head of Office/DDO.
32
(xi) Over writing should be avoided and corrections, if any, should be attested
by the Head of Office/DDO under his dated initial.
(xii) Crossed Account Payee cheque alone should be issued to third
parties/firms etc.
(xiii) The issue of bearer cheques should be avoided as far as possible.
(xiv) If no transactions have taken place in a day/s the entry “No transaction”
has to be noted in the cash book on that day/s and balances carried over to
next day and attested by the Head of Office / DDO.
(xv) When payments are made through cheque, the number of the cheque
should invariably be noted in the cash book for cross checking.
(xvi) During the absence of Head of Office/DDO, the responsibility of attesting
the entries in the cash book shall be entrusted to a sub-ordinate officer but
on his return the Head of Office/DDO should satisfy himself that there is
no irregularity and in token of this check, he should sign the cash book
immediately on return.
(xvii) In case computerized accounting software is in use, the cash book need
not be maintained manually. However, print out of the daily cash
transactions should be taken and pasted in cash book after attesting each
entry by the Head of Office/DDO.
4.25 Verification of cash balance
4.25.1 The contents of the cash chest / cash box should be counted by the Head of Office
/DDO or the senior most official in-charge at least once in a month and the
account compared with the cash book balance.
4.25.2 The result of verification should be recorded in cash book each time as under:
“Cash balance verified by me today and found to be Rs. …………. (in figures)
(Rupees ……………………………(in words) on actual count as correct”
Date ………………..
Signature
(Designation of the Officer)
4.25.3 In case the cash balance is not found to be as per cash book, the fact should be
recorded in the cash book and report submitted to the next higher authority
unless the error can be set right at once.
4.26 Correction of errors
4.26.1 If any item of receipts or cheques belonging to one head has been wrongly
classified under another head, the error shall be corrected in the following
manner: -
33
(a) If the error is discovered before the close of the day’s accounts, necessary
correction should be made in the original entry before the accounts of the
day are closed.
(b) If the error is discovered after the close of the day’s accounts but before
31st March, the correction should take the form of a fresh entry in the
cashbook.
Note: Errors affecting only classification i.e. receipts or payment on one
side of the cash book without any change in monetary value shall be
corrected in the manner prescribed at (a) above, if the same has been
detected before the close of the month’s account.
(c) If the error is detected after the account for March has been closed, the
correction should be carried out through a journal entry.
(d) In all such cases, the correcting entry should be supported by a transfer
entry memo approved by the Head of the office and a note of correction
shall be made against the original entry in red ink.
4.27 Journal
Journal is one of the important account books. Its use is restricted to only
recording adjustment entries other than cash transactions. Vouchers shall support
each adjustment entry passed through a Journal. Brief narration of each entry
shall be given in the voucher and it shall be signed by the Head of Office. The
Accountant will check each entry of the Journals with the vouchers and put dated
initials against the entries checked.
4.28 Ledger
(i) The Ledger is a register in which all transactions recorded in the cashbook or
Journal shall be classified under different heads of accounts or objects of
expenditure or any sub-unit thereof.
(ii) The Ledger should be kept in the prescribed form. Separate pages are to be
opened for each item of expenditure.
(iii) The Ledger accounts shall be arranged and grouped in such a manner that the
desired information is promptly secured.
(iv) Combined Ledger accounts can be maintained for various detailed heads.
The contingent Register may be maintained in such a manner that it is used
as Ledger for recording expenditure under miscellaneous items.
(v) Every Ledger account is divided into two sides, the left-hand side being the
“debit side” and the right hand side the “credit side”.
(vi) All items of debits and credits of the cashbook and Journal shall be posted on
the same day in the respective Ledger account.
(vii) Daily totals shall invariably be given and progressive totals shown wherever
necessary.
(viii) Bank account shall be posted from the daily totals of cheques issued and
challans / remittances made into the Bank.
34
(ix) After the Ledger accounts have been written up and completed in respect of
cash and adjustment items, the daily total of each Ledger account should be
carried into the appropriate classified account and the classified account
should then be totaled up and from the gross total the amount of adjustment
should be deducted to bring out the net totals of receipts and payments as per
cash book.
(x) All the Ledger accounts shall be closed at the end of the month. Totals shall
also be struck in the classified account.
(xi) Monthly totals of various Ledger accounts shall then be tallied with the totals
of classified abstract and discrepancy, if any, rectified and reconciled.
(xii) Monthly account of receipts and payments shall be prepared immediately
after closing of the accounts for the month.
4.29 Bank Reconciliation
(i) Monthly bank reconciliation should be carried out on a regular basis.
(ii) Bank Pass Book should be sent regularly to the bank for making up-to-date
entries of credit and debit in a month.
(iii) In case Bank Pass Book is not issued, monthly Bank Statement should be
obtained from the Bank regularly.
(iv) Entries shown in the passbook / Bank Statement will be tallied monthly with
the entries in the cash book.
(v) Any discrepancy will be rectified and difference explained in the Bank
Reconciliation Statement in the manner explained below:
Balance as per Cash Book ……………………………
.
Add:
(i) Cheque issued but not cashed ……………………………
.
(ii) Credit entries made in the bank but not shown
in the cash book
……………………………
.
Total ……………………………
.
Less:
(i) Amount sent to Bank but not credited in Bank
Account
……………………………
.
(ii) Bank charges debited in the bank account but
not accounted for in the cash book
……………………………
.
Total ……………………………
.
Balance as per Pass Book/Bank Statement ……………………………
.
35
4.30 Staffing Structure
4.30.1 An indicative staffing structure at State level and district level of Finance &
Accounts and Internal Audit is given below: -
Name of the Post No. of Posts at
State level
(SPO)
No. of Posts
at
District level
(DPO)
Qualification and Experience
Finance and Accounts
Controller Finance 1 - Preferably on deputation from
Finance and Accounts department
with sufficient accounting
background. In case, suitable
candidate is not available on
deputation basis, qualified and
experienced candidates may be
considered on contract basis.
Finance and
Accounts Officer
1 1 Preferably on deputation from
Finance and Accounts department
with sufficient accounting
background. In case, suitable
candidate is not available on
deputation basis, qualified and
experienced candidates may be
considered on contract basis.
Senior Accountant 3 2
Junior Accountant
Deputy Accountant
or Sr. Accounts
Clerk
Cashier 1 1 Preferably on deputation from
Finance and Accounts department
with sufficient accounting
background and knowledge of cash
management. In case, suitable
candidate is not available on
deputation basis, qualified and
experienced candidates may be
considered on contract basis.
Internal Audit
Audit Officer 1 - Preferably on deputation from Audit
department with sufficient auditing
background. In case, suitable
candidate is not available on
deputation basis, qualified and
experienced candidates may be
considered on contract basis.
Sr. Auditor 2 -
4.30.2 Although the above staff structure is indicative, in small States and districts the
requirement of staff may be suitably reduced to the extent required. In larger
States, if the above staffing structure is inadequate, the Executive Committee shall
appoint more staff for finance & accounting and internal auditing. The Executive
36
Committee may consider appointing an Accountant at block level or for a group
of blocks based on the quantum of accounting work involved. These Accountants
would provide resource support in accounting to cluster and school level.
4.31 Capacity building of accounts and audit staff
4.31.1 Orientation training on Planning, Budgeting, Accounting, Procurement, Internal
Audit etc. of Samagra Shiksha should be given to all accounts and audit staff at
periodical intervals so as to equip them with sufficient knowledge of the area of
their work for the smooth and efficient day to day functioning of the tasks
assigned to them.
4.31.2 A minimum of 5 days training to accounts and audit staff is mandatory in a year.
The accounts staff so trained at district level will provide training to block level
staff, who in turn will provide training to staff at cluster and school level.
4.32 Control of Expenditure
4.32.1 Persons authorised to incur expenditure must ensure that financial order and strict
economy are enforced at every step and see that all-relevant financial rules,
orders, directions and instructions are observed.
4.32.2 It should be seen that not only the total expenditure is kept within the limits of the
budget provision but also the funds allotted / transferred are spent in the interest
and service of the programme and upon objects for which provisions have been
made.
4.32.3 They will also see that items of expenditure are of obvious necessity and are at
fair and reasonable rates, sanction of the competent authority obtained and that
calculations are correct.
4.32.4 In order to exercise proper control, they should keep themselves closely
acquainted with the progress of receipts/expenditure, commitments and liabilities
incurred but not paid.
4.33 Re-appropriation of funds
4.33.1 Funds of the Society shall not be diverted or re-appropriated to meet any
expenditure which has not been sanctioned by the Competent Authority;
4.33.2 Funds shall not be diverted or re-appropriated to expenditure on any item not
provided for or contemplated in sanctioned budget estimates;
4.33.3 Re-appropriation of funds shall be made only when it is known or anticipated
that funds to be transferred from one sub-head to another sub-head will not be
utilised in full and savings under that sub-head of accounts are likely to become
available. The re-appropriation in such cases shall be made only with the
approval of State Executive Committee.
4.33.4 Re-appropriation of fund from Capital (Non-recurring) to General Head
(Recurring) and vice versa is not permissible under the Scheme.
37
Chapter: 5
MONITORING, INTERNAL CONTROL AND INTERNAL AUDIT
5.1 Introduction
5.1.1 Monitoring is considered to be the systematic collection of specific indicators and
other relevant information, in order to inform management and the key
stakeholders about the progress and the achievement of objectives, and use of
available resources. Monitoring focuses on the short to medium-term outputs that
can be used to adjust certain aspects of the Scheme if considered necessary.
5.1.2 In this context, large-scale inputs in terms of additional schools, additional
classrooms, teachers and other facilities need to be provided to meet the
challenge. It inter-alia requires assessment/ provision of educational needs,
physical infrastructure, human resource, academic inputs and effective monitoring
of implementation of the Scheme.
5.1.3 Internal Control: In the scheme Internal control is a process effected by the
management of implementing agencies and other personnel designed to provide
reasonable assurance that the objectives of the Scheme are being achieved in the
areas of (a) effectiveness and efficiency of operations, (b) reliability of financial
and operational reporting and, (c) compliance with the provisions of the scheme
frame work and other orders issued from time to time. Monitoring and
supervision of the implementation of the Scheme and internal audit are the main
controls exercised in internal control.
5.2. Supervision and Monitoring
5.2.1 Monitoring has to be a continuous process with both Scheme implementation and
outcome indicators required to be monitored on a regular basis.
5.2.2 Monitoring under the scheme is envisaged as four tiered:
(i) Monitoring at school /Community level,
(ii) District level
(iii) State level and
(iv) National level.
5.3 School/Community Level Monitoring
5.3.1 Community based monitoring is one of the strengths of the Scheme which can
become a major weakness if not implemented properly.
5.3.2 In order to make the financial flow transparent at the school level, every school
should display all the grants received and spent on civil & other than civil by the
school as well as enrolment, attendance, performance, incentive and the details
38
thereof. All reports of information should be sent to district project offices
(DPOs) by Schools and shall be displayed on the school notice board.
5.3.3 In addition to these, SDMC/SMC members have to inspect the Scheme regularly.
Parent teachers association / Community /local body members can also inspect
the school.
5.4 Composition of the School Level Committee:
5.4.1 While the specific composition of SMDC/SMC may be decided by the States, the
suggested composition of SMDC/SMC may be as follows,
(i) Principal, Chairman of the Committee
(ii) Vice Principal, Member
(iii) One teacher related to Social Science,Member
(iv) One teacher related to Science, Member
(v) One teacher related to Mathematics, Member
(vi) One gentleman from parents, Member
(vii) One lady from parents, Member
(viii) Two members from Panchayat or Urban Local Body
(ix) One member from SC/ ST community
(x) One member from Educationally Backward Minority Community
(xi) One member from women groups
(xii) One member from Education Development Committee of each village
(to which the school concerned caters)
(xiii) Three experts as members, each from Science, Humanities and
Art/Craft/ Culture background to be nominated by the District
Programme Coordinator through due process.
(xiv) One officer from Education Department to be nominated by the District
Education Officer as Member
(xv) One member from Audit and Accounts Department
5.4.2 The SMDC/SMC will be assisted by two sub-committees, School Building
Committee and Academic Committee, headed by the Principal and Vice
Principal respectively.
5.4.3 The School Building Committee will be responsible for all the activities
including planning, estimation, management, monitoring, supervision,
reporting, maintenance of Accounts, monthly squaring up of accounts,
presenting accounts before the School Management Committee or Panchayat or
Urban Local Bodies etc. relating to construction, renovation, repairing and
maintenance and other related civil works. The Civil Works will be undertaken
either on Contract Basis as per rules or by the Community. These works may
also be integrated with the appropriate Rural Development Schemes. While the
composition of the Sub- Committee can be decided by the State Government,
the suggested composition is as under,
39
(i) One member from Panchayat or Urban Local Body
(ii) One member from parents
(iii) One member from experts in Civil Works like Civil Engineer/ consultant
(iv) One member from Audit and Accounts Department
5.5 District Level Monitoring
A District Level Committee comprising public representatives would be
constituted to monitor the implementation of the scheme in that district as per
the following provisions:
5.5.1 Composition of the District Level Committee:
(i) All Members of Parliament, Members of the State Legislature and members
of the Zilla Parishad (wherever duly constituted), elected from that
district/and/or urban bodies (duly constituted) as applicable.
(ii) The District Magistrate/ Collector/ Deputy Commissioner/ Chief Executive
Officer of the Zilla Parishad/Urban local body.
(iii) District Education Officer in-Charge of the scheme, will be the Member-
Secretary.
(iv) District Officers in-charge of Drinking Water Mission/Total Sanitation
Programme/ Handicapped Welfare/Social Welfare/Minority Welfare etc.
(v) Two NGO’s working on secondary education for the scheme in the area, to
be nominated by the District Magistrate/ Collector/ Dy. Commissioner/
CEO Zilla Parishad.
(vi) The senior-most Member of Parliament present in the meeting will chair the
Committee on the day it meets.
5.5.2 Terms of Reference of the District Level Committee
(i) The Committee will be apprised of the progress of the scheme
implementation in the district, both in terms of key targets and achievements
thereof, and also on outcome indicators, inter-alia, Gross Access Ratio,
Enrolment, GER, NER, Gender Parity Index, Dropout, Transition rate, Pass
Percentage, PTR, SCR, Learning achievement levels of students etc.
(ii) Suggestions of the members may be taken into consideration, within the
parameters of the scheme guidelines and framework of implementation and
the approved Annual Work Plan & Budgets of the district, for improving the
scheme implementation at the local level.
(iii) The Committee may also examine the synergy and convergence of other
related Government Departments/Schemes in improving school infrastructure
and other support services for benefit of students.
(iv) The Committee will meet once a quarter.
(v) Committee should ensure community participation in monitoring and data
should be open for social auditing.
40
5.5.3 Monitoring by District Project Offices (DPOs):
(i) Component wise details of approved funds and the district level programmes
intended to carry out through this fund and copies of all sanction orders for
project activities would be uploaded on the web-site of the department and must
be published in the website of the district.
(ii) Publication of information material about the programmes and civil works and
the financial requirements needed for conducting the programmes.
(iii) The progress of civil works received from the school must be entered by the
district month wise.
5.5.4 Updated data on- progress of each components of the programme, school wise
physical progress (Stages of construction), progress of expenditure & utilization
including funds received and spent, payments made, works sanctioned and
works started, cost of works and details of expenditure on it, duration of work
etc. should be made public in a pre-designated format outside all offices of all
agencies involved in implementing the programme. All these information
should also be shared with the Gram Panchayats/ ULBs and should be discussed
in their meetings.
Other monitoring tools at district level are conducting field visits by the District
team. Schools should give monthly reports to the district so that district officers
can assess the progress of each school. District officers should conduct meeting
of the Headmasters of Government schools for assessing the progress of each
school in the district.
5.5.5 Financial Indicators to be monitored at the District Level
(i) Actual amount spent on civil work: The amount spent on civil work in
each financial year is to be calculated and to be monitored.
(ii) Actual amount spent on other than civil work: The amount spent on
other than civil work in each financial year is to be calculated and to be
monitored.
5.6 State Level Monitoring
5.6.1 The State Government shall prepare an annual Report on the implementation
including involvement of PRIs in the programme. This report will be laid before
the State Legislature.
5.6.2 All School wise physical progress in line with financial progress will be
monitored by State as submitted by districts. Expenditure against approved
AWP&B will be monitored through the information submitted on PMS on a
monthly basis by respective districts. The receipt of funds from various sources
and their subsequent releases to district level and school level should be
monitored on a monthly basis.
41
5.6.3 State level officers have to visit Districts to see whether the financial utilization
is carried out on time.
5.6.4 State should also develop a monitoring system so as to enable the monitoring
and supervision of the entire programme through e- governance
5.6.5 The State Implementing Societies (SIS) will also undertake intensive
monitoring. Representatives of national level institutions like NCTE, NIEPA
and NCERT will also undertake periodic monitoring and provide resource
support to the SIS to strengthen appraisal and monitoring systems. Efforts to
associate autonomous institutions willing to take up State specific
responsibilities for research and evaluation will also be made. Many
independent institutions would also be associated in developing effective tools
for conducting achievement tests, monitoring quality aspects of programme
implementation, evaluation and research studies.
5.6.6 Since quality is a major concern under the scheme, its monitoring will be a
priority. Monitoring of quality will require an understanding of the processes of
the programme implementation. Process and quality indicators would have to
be developed as per felt needs in order to track the quality of programme
implementation. Such efforts would require partnership with institutions, PRIs,
School Committees, etc. Training and orientation programmes to develop
appropriate monitoring formats, qualitative monitoring through process
documentation and case studies to understand issues comprehensively will be
required.
5.6.7 Financial Indicators to be monitored at the State Level
1. Guidelines issued: Guidelines should be issued to the district by the SIS on
how to conduct the programmes and to utilize the amount they have received.
2. State Government allocation: State Government will allocate funds to the
district as well as to the schools for the project according to their plans. This
will be based on the amount approved by the PAB.
3. Total amount received (GOI+ State+ other): Here entire amount received
for education sector including the scheme, State programme, Interest and
other receipts are to be included
4. Total expenditure: The expenditure incurred during programme
implementation is to be considered.
5. Salary expenditure as % of school education: Total Salary expenditure of
the state is to be calculated and the percentage of this amount is to be
calculated in respect of school education expenditure in the state.
42
6. Average per student expenditure by the State: The average expenditure
incurred per student for school education is to be calculated.
5.7 National Level Monitoring
5.7.1 Government of India will monitor financial management issues of the States on
a monthly basis related to the scheme. The strengthened Financial Monitoring
Unit of the Technical Support Group will assist for this purpose. The review
will include SPOs particularly the Finance officers of the State Implementing
Society.
5.7.2 All School wise physical progress in line with financial progress will be
monitored at National level as submitted by States/UTs through Project
Monitoring System (PMS). Expenditure against approved AWP&B will be
monitored through the information submitted on PMS on a monthly basis
submitted by respective States. The receipt of funds from various sources and
their subsequent releases to State level will be monitored on a monthly basis.
5.7.3 National level officers may visit the States to review/monitor the financial
management system in the States on regular basis. The case report/study can be
shared during the Quarterly Review meetings on financial management at
national level with other States/UTs for disseminating best practices prevalent
in the states.
5.8 Indicators for Financial Management Checks by Government of India
The Indicators of Financial Management checks by Government of India are as
follows:
a. Expenditure: The expenditure against approved AWP&B will be
monitored on a monthly basis. For this purpose, the information must be
updated on Project Monitoring System (PMS).
b. Funds Flow: The receipt of funds from various sources and their
subsequent releases to district level and sub-district level will be
monitored on a regular basis.
c. Staff for Financial Management: The position of financial management
staff at State and district level will be monitored on a quarterly basis. The
position of staff in the Statement as per Annexure-VI should be furnished
to Government of India within 20 days after the close of each quarter.
d. Training Programme for Financial Management Staff: Initial training
and orientation training on financial management covering planning,
budgeting, accounting, procurement, internal audit etc. under the scheme
should be given to all financial management staff at periodic intervals. In
order to monitor the position, the information as per Annexure-VII should
be furnished to Government of India on a quarterly basis within 15 days
after the close of each quarter.
43
e. External Audit: It is mandatory to conduct an external audit of the
accounts of the Societies on an annual basis. In order to monitor the
progress of audit, the information as per Annexure-VIII should be
furnished to Government of India on a quarterly basis within 15 days after
the close of each quarter.
5.9 Other Monitoring mechanisms:
5.9.1 Project Monitoring System (PMS) In a significant step towards leveraging
technology to enhance efficiency and manage the implementation of scheme, an online
Project Monitoring System (PMS) has been developed. The core objective of Project
Monitoring System is:
(i) To ensure an end to end information sharing system
(ii) To obviate the need for sending hard copies
(iii) To have transparency and accuracy w.r.t Approvals, Releases, Financial Status.
(iv) To streamline the Financial Management system.
(v) To monitor real time movement of funds to lower levels of Program
Implementation.
Main modules of PMS include:
(i) Online retrieval of Sanction Order of GoI Releases
(ii) Online Monthly Progress Reports (Physical and Financial)
(iii) Online Generation of UCs
(iv) Online submission of AWP&B
(v) Online Submission of School/unit wise Physical Progress of Civil works and
other than Civil Works.
(vi) Online submission of School/unit wise implementation/ Functional Status.
In PMS, States/UT are required to submit monthly Physical and Financial Progress of
Scheme.
5.9.2 Public Financial Management System (PFMS)
Public Financial Management System (PFMS) has been implemented for all the
Centrally Sponsored schemes by the Controller General of Accounts (CGA),
Ministry of Finance. This system provides MIS reports indicating availability of
funds in bank accounts at various tiers/levels of programme implementation. The
reports provide online balances lying in the bank accounts of such agencies.
Availability of this information at the Department (Ministry level) will help in
better financial management, more accurate assessment of actual requirement for
implementation and decision making on fund release. All states/UTs are required
to be PFMS compliant for release of funds.
5.9.3 Concurrent Financial Review and Monitoring by Government of India
The implementing agencies at all level are required to keep proper accounts of the
funds received by them and the expenditure incurred from these funds. They must
44
also ensure that the expenditure is incurred for the purpose for which it was
sanctioned and it is covered by relevant financial regulations / rules. In order to
ensure that the accounts are kept properly and the funds are utilized for the
purpose for which they were sanctioned, a Concurrent Financial Review and
monitoring shall be carried out by Government of India at periodic intervals. This
will be taken up in a phased manner considering the progress of implementation
of the scheme including various components in states.
The accounts of the State Implementing Society shall be opened to inspection by
Government of India/State Government and the audit party deputed by them.
Government of India may hire the services of reputed institutions to undertake
concurrent financial review of the scheme.
The State may consider the engagement of similar credible organizations or firms
of Chartered Accountants to undertake internal audit of their accounts only in the
absence of in house Internal Audit wing. The Terms of Reference for such an
internal audit shall be in the format as per Annexure-IX.
5.10 Internal Audit
5.10.1 Internal Audit is a control that functions by examining and evaluating the
adequacy and effectiveness of other controls throughout the organisation. The
internal audit activities should include all payment audit as well as independent
appraisals of the financial, operational and control activities of the programme.
The responsibilities of the internal auditor should include reporting on the
adequacy of internal controls, the accuracy and propriety of transactions, the
extent to which assets are accounted for and safeguarded, and the level of
compliance with the scheme financial norms and State Government procedures.
5.10.2 The State Implementing Society should introduce proper internal audit system and
strengthen internal checks and the in-house internal audit system to ensure proper
utilization of funds approved in the AWP&B.
5.10.3 In States where an in-house internal audit team is not available, qualified
Chartered Accountants/Cost Accountants firm may be engaged for carrying out
internal audit also as per the TOR provided in Annexure IX.
5.10.4 The internal audit of SPO and District Project Coordinator Offices shall be carried
out every year. Internal audit of Schools is conducted on a percentage basis, so as
to cover 5 per cent of schools in each district. It should be ensured in the internal
audit that the prescribed accounting system including regular bank reconciliation
is strictly followed by all.
5.10.5 The monthly expenditure Statement submitted by the districts indicating the
approved budget provision and expenditure during the month, cumulative
expenditure against the activity / sub-activity during the year should be reviewed
in the internal audit.
45
5.10.6 The Procurement Procedure adopted for civil works, goods and consultancy
services should be reviewed by the internal auditors and it should be ensured that
correct procedure has been followed for each procurement.
5.10.7 It should be ensured that the records of all Procurement, Agreements,
Work/Purchase Orders, Invoices, Receipts, Stock Registers etc. are properly
maintained, duly linked and retained.
5.10.8 Discrepancies noticed in the Internal Audit should be reported to the State Project
Director for taking necessary remedial measures. Records of all internal audit
objections should be kept in the Internal Audit Unit and pursued to finality.
5.10.9 The report of the internal audit shall also be placed before the Executive
Committee.
5.10.10In order to maintain the Internal Audit mechanism, state to give information as
per Annexure X.
5.11 Audit of School bodies
5.11.1 Internal audit by the auditor appointed by SIS should cover at least 5 per cent of
schools in each district.
5.11.2 The District Project Office of the scheme will keep a record of such audits and
ensure compliance by such bodies.
.
46
CHAPTER-6
AUDITING
6.1 Audit by the Chartered Account Firm
6.1.1 The State Implementing Society registered under the Societies Registration Act
1860 (21 of 1860) is responsible for the maintenance of proper accounts and other
relevant records, as well as preparing annual accounts comprising the receipts and
payments accounts and Statement of liabilities in such a form as may be
prescribed by the Registrar of Societies in keeping with the Rules in force under
the said Act. Accordingly, it is mandatory that a Chartered Accountant appointed
for this purpose should audit the accounts of the Society annually and submit an
annual audit report.
6.1.2 The State Society shall maintain proper accounts and other relevant records and
prepare annual accounts comprising the receipts and payments account and
Statement of liabilities in such form as may be prescribed by the Registrar of
Societies of the State Government in keeping with the Rules in force under the