PROCEDURE FOR FILING CAPITAL INVESTMENT AND CAPITALISATION PLAN
Regulations made under THE ELECTRICITY ACT, 2003
- Made under: THE ELECTRICITY ACT, 2003
This text is shown as one document.
Full text
The Bihar GazetteThe Bihar GazetteThe Bihar GazetteThe Bihar Gazette
EXTRA ORDI
PUBLISHED BY AUTHORIT
(NO.PATNA 661) PATNA,
BIHAR ELECTRICITY REGULATORY
PROCEDURE FOR FILING CAPITAL INVESTMENT AND
No. BERC-SMP-35/2017
Section 181 of the Electricity Act, 2003
enabling it in this behalf, the Bihar Electricity Regulatory Commission hereby
makes the following Regulations on Capital investment Plan and Capitalisation
of assets by Distribution & Transmission Licensees in the State.
1. Short Title Extent and Commencement
1.1 These Regulations shall be called Bihar Electricity Regulatory
Commission (Procedure for filing Capital investment and
Capitalisation plan) Regulations, 2018.
1.2 These Regulations extend to the whole of the State of Biha
1.3 These Regulations shall come into force from the date of their
publication in the official gazette of Government of Bihar.
2. Definitions
2.1 In these Regulations, unless the context otherwise requires:
(i) “Act” means the Electricity Act,
(ii) “CERC” means the Central Electricity Regulatory Commission
constituted under Section
REGISTERED NO. PT.
The Bihar GazetteThe Bihar GazetteThe Bihar GazetteThe Bihar Gazette
XTRA ORDINARY
UBLISHED BY AUTHORITY
26 Asadha 1940(S)
PATNA, TUESDAY, 17TH JULY 20
BIHAR ELECTRICITY REGULATORY COMMISSION, PATNA
PROCEDURE FOR FILING CAPITAL INVESTMENT AND
CAPITALISATION PLAN
————
NOTIFICATION
The 13th July, 2018
35/2017-09—In exercise of powers conferred under
Section 181 of the Electricity Act, 2003(36 of 2003) and all other powers
enabling it in this behalf, the Bihar Electricity Regulatory Commission hereby
makes the following Regulations on Capital investment Plan and Capitalisation
of assets by Distribution & Transmission Licensees in the State.
tle Extent and Commencement
These Regulations shall be called Bihar Electricity Regulatory
Commission (Procedure for filing Capital investment and
Capitalisation plan) Regulations, 2018.
These Regulations extend to the whole of the State of Biha
These Regulations shall come into force from the date of their
publication in the official gazette of Government of Bihar.
In these Regulations, unless the context otherwise requires:
“Act” means the Electricity Act, 2003 (36 of 2003);
“CERC” means the Central Electricity Regulatory Commission
constituted under Section-76 of the Electricity Act, 2003;
REGISTERED NO. PT.-40
The Bihar GazetteThe Bihar GazetteThe Bihar GazetteThe Bihar Gazette
2018
COMMISSION, PATNA
PROCEDURE FOR FILING CAPITAL INVESTMENT AND
In exercise of powers conferred under
and all other powers
enabling it in this behalf, the Bihar Electricity Regulatory Commission hereby
makes the following Regulations on Capital investment Plan and Capitalisation
These Regulations shall be called Bihar Electricity Regulatory
Commission (Procedure for filing Capital investment and
These Regulations extend to the whole of the State of Bihar.
These Regulations shall come into force from the date of their
publication in the official gazette of Government of Bihar.
In these Regulations, unless the context otherwise requires:-
“CERC” means the Central Electricity Regulatory Commission
76 of the Electricity Act, 2003;
2 BIHAR GAZETTE (EXTRA) 17TH JULY 2018
(iii) “Commission” means the Bihar Electricity Regulatory
Commission;
(iv) “Conduct of Business Regulations” means the Bihar
Electricity Regulatory Commission (Conduct of Business)
Regulations 2005 as amended from time to time;
(v) “Current Year” means the financial year in which the power
procurement plan is filed by the Licensee;
(vi) “Ensuing Year” means the financial year immediately following
the current year;
(vii) “Licensee” means a person who has been granted a
distribution or transmission licence under the Act and shall
also include a deemed Licensee;
(viii) “Long term procurement of power” means procurement of
electricity for a period exceeding one year;
(ix) “Previous Year” means the financial year immediately
preceding the current year;
(x) “Power Purchase Agreement (PPA)” means the agreement
entered into between the Procurer(s) and the Seller pursuant
to which the Seller shall supply power to the Procurer(s) as
per the terms and conditions specified therein;
(xi) “Procurer(s)” means the Distribution Licensee(s), or the
representative of the Licensee(s) authorized by the
Distribution Licensee(s) to perform all tasks of procurement of
power in accordance with these regulations;
(xii) “Short term procurement of power” means procurement of
electricity for a period less than or equal to one year;
(xiii) “Year” means financial year beginning 1st April and ending on
31st March of following year.
2.2 The words and expressions used and not defined in these
Regulations but defined in the Act, shall have the meanings
assigned to them in the Act.
3. Scope of Application
These Regulations shall apply to all Transmission & Distribution
Licensee(s) in the state of Bihar.
4. Assessment of Distribution & Transmission Licensees
Infrastructure Requirements
4.1 The Distribution Licensee(s) shall make an assessment of
Distribution Infrastructure Requirement to meet the demand (MW)
and energy requirement (MU) forecasted in accordance with BERC
(Power Purchase and Procurement Process of Licensee)
Regulations, 2018. The assessment shall be made in such a way
that unrestricted 24 hours supply of adequate and uninterrupted
power can be ensured to all categories of consumers by 2021-22
or earlier. While making assessment, Distribution licensee(s) shall
also take into consideration the following along with other
relevant factors –
(i) Duties and Obligation of Distribution Licensee provided in
the Act;
(ii) Prescribed limits of loading of Lines, Cables, Transformers etc;
(iii) Prescribed performance parameters of equipments such as
Voltage regulation, Reactive energy flow, Power factor etc. by
Central Electricity Authority (CEA)/CERC/BERC
3
BIHAR GAZETTE (EXTRA), 17TH JULY 2018
(iii) Implementation of T&D loss reduction initiatives and other
improvement programmes;
(iv) Different schemes of Government for capacity addition
/improving operational efficiency/Electrification/ System
strengthening.
(v) Load growth of consumers and prospective consumers/Open
access consumers
(vi) Assets which are going to complete their useful life
(vii) The impact of the provisions of the Act and possible switch
over of consumers to open access and captive generation
4.2 The Transmission licensee(s) shall make assessment of
Infrastructure Requirement to meet the demand (MW) and energy
requirement(MU) referred in 4.1 above so that demand forecasted
by the Distribution licenses are met uninterruptedly and reliably.
While making assessment, Transmission licensee(s) shall also take
into consideration the following along with other relevant factors –
(i) Duties and Obligation of Transmission Licensee provided in
the Act;
(ii) Prescribed limits of loading of Lines, Cables, Transformers etc;
(iii) Prescribed performance parameters of equipments such as
Voltage regulation, Reactive energy flow, Power factor etc. by
Central Electricity Authority (CEA)/CERC/BERC
(iii) Implementation of Technical loss reduction initiatives and
other improvement programmes;
(iv) Different schemes of Government for capacity addition/
improving operational efficiency/Electrification /System
strengthening.
(v) Assets which are going to complete their useful life
(vi) Demand of prospective Open access consumers
(vii) The impact of the provisions of the Act and possible switch
over of consumers to open access and captive generation.
5. Capital investment plan
On the basis of Infrastructure requirement assessed in accordance
with the provisions of these Regulations, the Distribution and
Transmission Licensee(s) shall prepare a rolling plan of ten years
for Capital investment Plan and capitalization for capacity
addition/improving operational efficiency/electrification/system
strengthening with an overall objective of supplying unrestricted,
uninterrupted and quality power to the consumers (including open
access consumers) in the State. While planning for capacity
addition/system strengthening the Licensees shall also consider
the following along with other relevant factors prevailing in
the state:
(i) Different schemes of Government for capacity addition
/improving operational efficiency/Electrification /System
strengthening.
(ii) Capital investment plan shall clearly show the scheme wise
objective of the investment plan and cost benefit analysis of
the investment along with the yearly capital expenditure
and capitalization schedule.
(iii) Capital investment plan shall clearly show the scheme wise
source of funding under the heads Equity, Loan, Grant,
consumers contribution and internal resources;
4 BIHAR GAZETTE (EXTRA) 17TH JULY 2018
(iv) The Capital investment plan shall be the least cost plan
(least financial cost to the licensee) with ultimate objective
being to make available unrestricted, uninterrupted and
reliable power supply at economically viable tariffs to all
consumers while satisfying power supply planning and
security standards.
(v) In case the Commission issues guidelines and formats,
from time to time, the same shall be adhered to by the
Distribution and Transmission Licensee(s).
6. Approval of Capital investment plan
6.1 The rolling capital investment plan shall be integral part of the
ARR to be filed every year. The first such capital investment plan
for next 10 years shall be submitted by the licensee(s) along with
the Multiyear ARR for third control period starting from financial
year 2019-20.
Provided that under special circumstances Licensees may also file
capital investment plan separately seeking approval thereon if it
warrants so and not included in its earlier filing. Such application
must contain all supporting documents inter-alia justification for
filing separate petition, purpose of investment, capital structure,
DPR, capitalization schedule, financing plan and cost benefit
analysis etc
6.2 The Licensee(s) shall submit the Capital investment Plan every
year with the ARR/Multiyear ARR petition and it should inter-alia
contain:—
(a) Scheme wise Source wise actual capital expenditure and
capitalization for previous year vis-a-vis projected in the
investment plan for that year;
(b) Scheme wise Source wise actual capital expenditure and
capitalization for first six months of current year vis-a-vis
projected in the investment plan for that period;
(c) Scheme wise Source wise capital investment plan
containing year wise schedule of capital expenditure and
capitalization for next ten years starting from ensuing
years. Based on actual expenditure and capitalization the
rolling plan may get revised in subsequent filings. The
capital investment plan should show scheme wise objective
of the investment.
Provided that such capital investment plan seeking
regulatory approval shall be supported with Detailed Project
Report (DPR) duly approved by the competent authority.
Provided further that if DPR duly approved by the
competent authority is not available till finalization of the
capital investment plan, the licensee(s) may include such
investment in the capital investment plan as mentioned
above. However the licensee shall submit the approved DPR
to the Commission in its immediate next filing following
approval of such DPR.
Provided also that the Capital investment (made out
of internally generated fund) for which no DPR is prepared
shall also be a part of capital investment plan as mentioned
above. However the licensee shall submit such
5
BIHAR GAZETTE (EXTRA), 17TH JULY 2018
statement/report to substantiate the purpose and nature of
investment duly approved by the competent authority.
6.3 The Commission may, call for such additional information or
particulars or documents as the Commission may consider
necessary for approving the investment Plan;
6.4 The Commission may, at its discretion, direct the licensee(s) to
publish the main details of the investment Plan in such manner as
the Commission may direct, so as to enable public/stakeholders
to file objections, comments or suggestions, in the manner
indicated in the Conduct of Business Regulations of the
Commission. The Commission shall consider such representations
before approval of the plan;
6.5 The Commission shall approve such investment Plan with such
modifications or such conditions as may be mentioned in that
order or reject the same after giving the Licensee(s) ample
opportunity of being heard with reasons to be recorded in writing.
6.6 Notwithstanding anything contained in these Regulations, the
licensee(s) shall normally get prior approval of every capital
investment.
Provided that the Distribution and Transmission Licensee(s)
may invest up to Rs 5 crore and Rs 20 crore respectively without
prior approval of the Commission to meet emergency conditions
arisen due to unforeseen circumstances. Such investment should
be certified as emergent nature by the Board of Directors or by the
Authority delegated by the Board of Directors. However in such
cases the licensee(s) shall submit detailed justification along with
supporting documents for emergent nature of expenses within 15
days of occurrence of cause for such investment.
7. Power to Remove Difficulties
If any difficulty arises in giving effect to any provisions of these
Regulations, the Commission may by general or specific order, do
or undertake or direct the Distribution Licensee to do or
undertake things which in the opinion of the Commission are
necessary or expedient for removing the difficulties.
8. Power to Amend
The Commission may at any time, vary, alter, modify or amend
any provisions of these Regulations.
By order of the Commission,
NIRAD PRAKASH,
Secretary.
————
PUBLISHED AND PRINTED BY THE SUPERINTENDENT,
BIHAR SECRETARIAT PRESS, PATNA.
Bihar Gazette (Extra) 661—571+400—Egazette