The Rajasthan Enterprises Single Window Enabling and Clearance Rules, 2011
Rules made under The Rajasthan Enterprises Single Window Enabling and Clearance Act, 2011
This text is shown as one document.
Full text
INDUSTRIES (GR-I) DEPARTMENT
NOTIFICATION
The Rajasthan Enterprises Single Window Enabling and Clearance Rules, 2011
(Along with Insertions / Deletions incorporated in, Amendment Rules 2014 and Amendment Rules 2016)
May 24, 2016
In exercise of the powers conferred by section 21 of the Rajasthan Enterprises Single
Window Enabling and Clearance Ordinance, 2010 (Ordinance No.04 of 2010), the State Government
hereby makes the following rules, namely:
(1) Short title and commencement: (1) These rules may be called The Rajasthan Enterprises
Single Window Enabling and Clearance Rules, 2011 (and Amendment Rules 2014 and
Amendment Rules 2016).
(2) They shall come into force on and from the date of their publication in the Official
Gazette (May 24, 2016).
(2) Definitions - (1) In these rules unless the context otherwise requires:
(a) "Acknowledgement" means the acknowledgement issued for receipt of application
under these rules;
(aa) ”Act" means the Rajasthan Enterprises Single Window Enabling and Clearance Act,
2011 (Act No.07 of 2011);
(b) "Application Form" means the form either in physical or electronic format as
prescribed under any Rajasthan Law/Order/Guide lines or as notified by the State
Government;
(c) "Authorized Officer" means General Manager, District Industries Centre or an officer
authorized by him not below the rank of District Industries Officer, in case of Nodal
Agency for the District Empowered Committee and an officer authorized by
Commissioner, Investment and NRI (Bureau of Investment Promotion) in case of Nodal
Agency for the State Empowered Committee;
(d) "District Empowered Committee" means the committee constituted under sub-
section (3) of section 3 of the Ordinance;
(e) "Fee" means the fee prescribed under any Rajasthan Laws/Orders/Guidelines or as
notified by the State Government, for submitting application for permissions/ no
objection certificate/ clearance/ allotment/ consent/ approval/ registration/ License
and the like;
(f) "Form" means Form appended to these rules;
(g) "Nodal Agency" means the agencies notified under sub-section (1) or (2) of section 5,
as the case may be, of the Ordinance;
(h) "Official" means any employee of the department or agency of the Government,
Local Authority, Statutory Body, State owned Corporation, Gram Panchayat,
Municipality, or any other authority or Agency constituted or established under any
Rajasthan law or under administrative control of the Government;
(hh) "Portal" means website that serves as gateway for electronic operation and
processing of applications specified in these rules;
(i) "Register of Applications" means register of applications received by the authorized
officer either in physical form or electronic form;
(j) "Schedule" means Schedule appended to these rules;
(k) "Section" means a section of the Ordinance;
(|) "State Empowered Committee" means the committee constituted under sub section
(1) of section 3 of the Ordinance; and
(m) "Time Limit" means the number of working days specified in Schedule-I or
Schedule-II, as the case may be.
(2) Word or expression used in these rules but not defined in these rules have the same
meaning as assigned to them in the Ordinance.
(3) Application:-
(1) Every application for seeking Permissions specified in Schedule-I shall be filed
electronically on the Portal. The Application Form shall be duly filled and accompanied
with required documents. However, in case of failure of electronic system due to
unforeseen circumstances, the applicant may submit application in physical format to
the Nodal Agency."
(2) Applicant shall furnish the self certification in Form-I at the time of registering on the
Portal and it shall be deemed to have been furnished with every application for the
Permissions within the meaning of sub-section (3) of section 8 of the Act."
(4) Processing and monitoring of applications at the level Nodal Agency-
(1) An automated acknowledgement shall be generated on the Portal for every
application submitted electronically and the application shall be auto forwarded to the
Competent Authority concerned under intimation to the Nodal Agency.
(2) All the applications auto forwarded on the Portal to the Competent Authority shall
be deemed to have been forwarded by the Nodal Agency within the meaning of clause
(i) of section 6 of the Act.
(3) In case the application is submitted to Nodal Agency in physical format as specified
in sub-rule (1) of rule 3, the Nodal Agency shall issue the acknowledgement and forward
the application to the Competent Authority concerned, within the time specified in
Schedule-2 of these rules.
(4) The Nodal Agency shall maintain a Register of Applications in electronic or physical
form and the particulars of all the applications shall be entered in the Register of
Applications.
(5) The Nodal Agency shall monitor the disposal of applications within the time limit
specified in these rules and keep a record of the communication between applicant and
the Competent Authority.
(6) The Application on which the Competent Authority has taken a decision within the
prescribed time limit, the decision so taken shall be entered into the Register of
Applications and the status of the applications shall be submitted by the Nodal Agency
to the State Empowered Committee or the District Empowered Committee, as the case
may be in the next meeting of the concerned Empowered Committee.
(7) The Application on which the Competent Authority has failed to take a decision
within the prescribed time limit, the Nodal Agency shall place the application before the
State Empowered Committee or the District Empowered Committee, as the case may
be, for consideration in the next scheduled meeting of the concerned Empowered
Committee within the prescribed time limit. In case the concerned Empowered
Committee is unable to meet or otherwise unable to consider application, placed before
it by the Nodal Agency, immediately, the Nodal Agency shall submit the application to
the Chairperson of the concerned Committee. The Chairperson of the Committee, after
recording the reasons in writing, may decide the application and such decision shall be
placed before the concerned Committee in its next meeting. The decision taken by the
Chairperson on the application shall be final subject to the decision of the Committee.
(8) The Nodal Agency of State Empowered Committee shall receive Application for
relaxations, exemptions and concessions for grant of customized package and seek
comments of the concerned Departments or Authorities. The Nodal Agency shall submit
the application for the customized package before the State Empowered Committee
after the expiry of the period as specified in these rules for the comments from the
concerned departments or authorities along with the comments received and even
when the comments are not received.
(5) Processing and monitoring of applications at the level of Competent Authority:-
(1) The Competent Authority, after receipt of the application for Permission, shall
consider and take decision on the application within the time limit specified in these
rules. If the application is incomplete and/or any additional information is prescribed in
rules for taking a decision on the Permission, the Competent Authority may obtain such
additional information from the applicant. The time taken by the applicant in submitting
required information to complete the application or additional information shall not be
counted in counting the time limit. In case the applicant fails to submit the required
information to complete the application within thirty days, the registration for
application shall be dropped from the Portal.
(2) The decision on the application within the specified time limit by the Competent
Authority shall be communicated to the applicant and the Nodal Agency.
(3) In cases of applications in which the Competent Authority has failed to take a
decision within the specified time limit, the record of processing of the application shall
be forwarded to the concerned Nodal Agency."
(6) Time Limits for processing and disposal of applications:-
(1) The time limits for processing and disposal of applications shall be as specified in
Part A and Part B of Schedule-I or Schedule-II, as the case may be. The time limits for
the State Empowered Committee/District Empowered Committee for processing the
application for Permissions, in case the Competent Authority has failed to take a
decision in the specified time limit, shall be thirty working days counted from the last
date of the time limit prescribed in Part A and Part B of Schedule I, for the Competent
Authority to take the decision:
Provided that any decision by the State Empowered Committee/District Empowered
Committee or Chairperson of State Empowered Committee/District Empowered
Committee, in exercise of power conferred to it in sub-section (4) of section 3 of the Act
and sub-rule (7) of rule 4 of these rules, shall be communicated to concerned
Competent Authority within seven days and it shall be binding on the Competent
Authority and the Competent Authority shall issue all the necessary orders for
Permission within three days.
(2) The State Government may be notification in the Official Gazette, add to or omit
from, or otherwise amend or modify the Schedules appended to these rules and
thereupon the Schedule shall be deemed to have been amended accordingly.
(6A) Monitoring of applications for Permissions specified in Part C of Schedule-l.-
(1) The Permissions specified in Part C of Schedule-I shall be provided through Portal of
Single Window System to ensure online filing, payments, tracking of status, approvals
and issuance of certificates. The time limits for disposal of such applications shall be as
prescribed in Part C of Schedule-I.
(2) The Applications on which the Competent Authority has failed to take a decision
within the prescribed time limit, the applicant shall appeal to appropriate authority,
specified in relevant law:
Provided that the Rajasthan State Pollution Control Board shall explicitly publish
the provisions of deemed consent under the applicable Acts and procedure of appeal
against the decision of Competent Authority on its Web Portal.
(3) Notwithstanding anything contained in the Rajasthan Enterprises Single Window
Enabling and Clearance Act, 2011 (Act No.7 of 2011), the State Empowered Committee
or the District Empowered Committee shall not take any decision in the cases where the
Competent Authority of Rajasthan State Pollution Control Board has failed to take a
decision within the specified time limit, but the State Empowered Committee shall be
empowered to monitor the applications submitted on Portal for the Permissions
specified in Part C of Schedule-I and redress the grievances of applicant.
(7) Monitoring:— Status report of processing of the application for permissions and/ or
customized packages, concessions, exemptions or relaxations, shall be placed before the
District Empowered Committee and the State Empowered Committee, as the case may be by
the respective Nodal Agency.
(8) Jurisdiction of the State Empowered Committee and the District Empowered
Committee-
(1) The District Empowered Committee shall be competent to consider and dispose of
the application for permissions for investment proposals from Rs. 1 crore to Rs. 10.00
crores.
(2) The State Empowered Committee shall be competent to consider and dispose of the
application for permission for investment proposals above Rs.10.00 crores.
(3) All applications for customized packages, concessions, exemptions or relaxations
shall be considered by the State Empowered Committee and this committee shall
submit its recommendations to the Council of Ministers.
(9) Grievance Redressal Mechanism.-
(1) An Grievance Redressal Cell shall be constituted in Industries department consisting
of the following, namely:-
(1) Commissioner, Industries, Rajasthan Chairperson
(2) Two officers of the Industries department, Member
not below the rank of Deputy Director,
Industries department, nominated by the
Secretary incharge of the Industries department,
Government of Rajasthan.
(2) Any aggrieved person or applicant shall register his grievance on the Portal in Form-
2. All grievances registered on portal shall be received and processed by the Grievance
Redressal Cell and take appropriate measures for addressing the grievances within forty
five days of registration of grievance:
Provided that in all such cases where Competent Authority has failed to decide the
application for Permission within time limit specified in these rules, shall be processed
by the Nodal Agency for decision as specified in sub-rule (7) of rule 4 and shall be
communicated to the aggrieved applicant.
(3) All grievances received shall be presented in the next meeting of State Empowered
Committee by the Grievance Redressal Cell and the decision of State Empowered
Committee shall be final and shall be binding on all concerned. However if the grievance
refers to any order of State Empowered Committee, it shall be submitted to the State
Government and the decision of State Government shall be final and shall be binding on
all concerned.
(4) In cases where State Empowered Committee finds that any Official has failed to
comply with the provisions of the Act and these rules, the State Empowered Committee
may recommend the Disciplinary Authority concerned to initiate appropriate action or
disciplinary proceedings against the official for imposing penalties specified in rule 14 of
the Rajasthan Civil Services (Classification, Control and Appeal) Rules, 1958:
Provided that official who fails to comply with the provisions of the Act and these
rules belongs to of any agency of the Government, Local Authority, Statutory Body,
Gram Panchayat, Municipality, State owned Corporation, or any other authority or
Agency constituted or established under any Rajasthan law or under administrative
control of the Government, the State Empowered Committee may recommend, the
appropriate Disciplinary Authority to initiate appropriate action or disciplinary
proceedings against the official for imposing penalties mentioned in applicable service
rules.
(5) Notwithstanding anything contained, the State Government shall be competent to
initiate appropriate action or disciplinary proceedings against any official who fails to
comply with the provisions of Act and these rules.
(10) Removal of doubt:— If any difficulty arises in the application or interpretation of these
rules, it shall be decided by the State Government in the Industries Department whose
decision thereon shall be final.
Schedule-l
(See rule 3 (1) 6 and 6(A))
Part - A
Time Limit for Various Permissions/Clearances
No.
DEPARTMENTS
/ORGANIZATION
PERMISSIONS/
CLEARANCES
TIME LIMIT
(WITHIN WORKING DAYS)
Factories and Boilers
Inspectorate
a) Factory building plan approval’ (under the Factories Act, 1948)
i) Factories as defined under section
2m(ii) and involving non hazardous
process as defined under rule 2(m)
10 days
ii) Other factories 30 days
b) Factories license
i) Factories as defined under section
2m(ii) and involving non hazardous
process as defined under rule 2(m)
7 days
Factories involving non hazardous
process as defined under rule 2(m)
15 days
Factories involving hazardous
process as defined under section
2(cb)
21 days
Factories involving dangerous
operations as defined under section
87
21 days
V) MAH factories as defined under
Rajasthan Control of Major Accident
Hazard Rules, 1991
60 days
C) Renewal under 'Factories license
i) Factories as defined under section
2m(ii) and involving non hazardous
process as defined under rule 2(m)
7 days
Factories involving non hazardous
process as defined under rule 2(m)
15 days
iii) Factories involving hazardous
process as defined under section
2(cb)
21 days
iv) Factories involving dangerous
operations as defined under section
87
21 days
v) MAH factories as defined under
Rajasthan Control of Major Accident
Hazard Rules, 1991
60 days
d) Registration under Boiler Act After the receipt of
complete application
i) Provisional order Exempted
(under the Boilers Act, 1923)
ii) Final order 30 days
(under the Boilers Act, 1923)
e) Renewal under ‘Registration under Boiler Act’
i) In cases in which the Competent 48 hours
Person is empowered to issue a
certificate under section 8 without
further reference.
ii) In any other case 15 days
f) Steam Pipeline Drawing approval 15 days
(under the Boilers Act, 1923)
Labour Department a) Permission for engaging contractor for labour
Under Contract Labour (Regulation and Abolition) Act, 1970
i) Registration of Principal Employers 30 days
Establishments
ii) Issuance of Licence to Contractor for 15 days
employment of contract labours
b) Registration of Establishments under 15 days
Building and other Construction Workers
(Regulation of. Employment and
conditions of Services) Act, 1996
c) ‘Registration under Shops and 30 days
Establishments Act’
d) Renewal under ‘Shops and 15 days
Establishments Act’
Revenue Department a) Land conversion—Conversion of land use Sending applications
under Rajasthan Land Revenue
(Conversion of Agricultural Land for Non-
Agricultural Purposes in Rural Areas)
Rules, 2007
directly to the concerned
District Collectors under
intimation to Revenue
Department, Jaipur, to save
time. Revenue Department
would issue on line receipt
and update online status of
the application.
All communication would
be addressed to PS,
Revenue for early action.
up to 10 hectares 60 days from submission of
completed application to
District Collector
ii) above 10 hectares 90 days from submission of
completed application to
State Government
Energy Department
(All Vidhyut Vitran
Nigam Ltd.)
a) Release Connection (where no extension in Distribution Mains is
required) Electricity connection
1) Release of Connection
Explanation:
i) If LT supply of electricity can be
provided to a premises by existing
service line or by laying service line
up to 50 meters, from an existing
overhead line or underground cable
where a cable box, junction box
pillar box etc. has been provided,
shaH be
deemed to require no extension.
the distribution mains
ii) In case of HT supply of electricity
the distribution
system shall be deemed to require
to a premises,
augmentation and procedure laid
down in Clauses b) & c) hereunder
shall be followed.
Within one month of the
receipt of completed
application
b) Supply where distribution mains require extension
1) Notice to the applicant to deposit
additional expenses
Within one month of the
receipt of application (for a
period ofone month)
2) Where extension of distribution
mains is required but no additional
sum is required to be deposited
The Nigam shall complete
the extension work within
15 days
3) the
mains
shall
of distribution
The Nigam complete
extension
within the time specified below for
different voltage levels after deposit
of additional sum by the applicant
i) L.T. line 15 days
ii) 11 KV line-first 5 Kmp 30 days
Next 5 Km each 15 days
iii) 33 KV line-first 5 Km 60 days
Next 5 Km each 30 days
iv) 132 KV line-first 5 Km 180 days
Next 5 Km each 45 days
Note: After extension work connection will be released within 15 days
after inspection of the installation.
C) Supply where new sub-station or augmentation of transformer sub-
station is required
1) Supply where new substation is to The Nigam will intimate
be commissioned within two month of receipt
of application, the date of
commencement of work, to
the consumer and complete
the work within time limit
specified below
i) 11/O.4 KV sub-station 30 days
ii) 33/11 KV sub-station 120 days
iii) Extension of bay at 33/11 KV sub- 30 days
station
iv) 132/33/11 KV sub-station 12 month
v) Extension of bay at 132 KV sub- 45 days
station
2) Supply where augmentation of
transformer sub-station capacity is
required
i) 11/O.4 KV sub-station 15 days
ii) 33/11 KV sub-station 60 days
iii) 132/33/11 KV sub-station 6 months
After commencement of work of
sub-station
i) Intimation to the consumer if any
additional sum is to be deposited by
the applicant.
Intimation—
Time of deposition—
Release of connection—
Within 15 after
commencement of work.
days
1 month or such extended
period as the Nigam may
allow.
Within 15 of
commissioning
days
of sub-
station.
0') Supply in localities where no provision for
supply exists
Once electrification of such
locality is completed supply
shall be provided to the
applicant in accordance
with the provisions of sub-
clauses a) to c) above as
may be applicable to him.
e) electric line/plant is
by
Supply where
provided applicant
The Nigam shall provide
supply of electricity within
15 days of intimation given
by the applicant regarding
completion of work.
RIICO Allotment of plots in Industrial Areas Form A—3O days
Form A(Preferential) —90
days
b) Approval of building plans 15 Days (After
complete
receiving
modification/
correction in submitted
drawing)
Water Connection 20 days (After receiving of
complete information)
UDH
(JDA/UlTs)
Department a) 90A of Agriculture Land/ Conversion of
land under
Rules 2012
Rajasthan Land Revenue
60 days
b) Change of Land use/Conversion of land
use from residential to commercial
Matters to be decided
at Local level
committees- 60 days
(i)
Matters to be decided
at State level
committees-120 days
(ii)
c) Issuance of Lease Deed for institutional (i) To be issued at local
plots level-30 days
(ii) When approval of
State Govt. is required-
60 days
d) Allotment of institutional land except the 90 days
allotment of land through lottery/auction
and of the developed land given as
compensation for Government/
Semi-Government departments/
institutions and acquired land—under
instruction of Urban Development and
Local Self Department dated 4.1.2010
e) Building map approval of all kinds of 60 days
institutional buildings
7. Local Self Government a) NOC from Fire Department 30 Days
(LSG)
b) 90A of Agriculture Land/ Conversion of 60 Days
land under Rajasthan Land Revenue
Rules 2012
c) Change of Land use/Conversion of land (i) Matters to be decided
use from residential to commercial at Local level
committees- 60 days
(ii) Matters to be decided
at State level
committees - 120 days
d) Building map approval of all kinds of 60 days
institutional buildings
8. Public Health a) Water Connection 07 days as per availability of
Engineering water and after deposition
Department (PHED) ofall fees
9. Tourism Department a) Project Approval 45 days from the date of
submission of complete
application
10 Industries Department a) Incentives under Industrial Policy/ As perSchedu/el(b)
Investment Promotion Scheme
Part - B
Time Limit for Incentives under RIPS-2014
Rules
S. Department Application for Benefits under Time Limit for disposal of
No. Rajasthan Investment Promotion application
Scheme -2014 (Decision on eligibility under
RIPS-2014)
1. Industries Department a) Exemption from stamp dUtY and 07 days from date of
conversion charge submission of complete
application
b) Exemption from land tax 45 days from date of
submission of complete
application
c) Investment subsidy and 45 days from date of
Employmentsubsidy submission of complete
application
d) Exemption from 45 days from date of
(1) Electricity dUtY submission of complete
(ii) Entertainment tax
application
(iii) Luxury tax
(iv) Mandi fee
(V) Entry tax
e) Interest subsidy 45 days from date of
submission of complete
application
f) Reimbursement ofVAT 45 days from date of
submission of complete
application
g) Capital subsidy on ZLD treatment 45 days from date 0f
plant submission of complete
application
Part-C
Time Limit for Various Permissions/Clearances
S. ORGANISATION PERMISSIONS/ TIME LIMIT
No. CLEARANCES (WITHIN WORKING DAYS)
1. Rajasthan Pollution a) Consent to Establish (under Water Act & 120 Days
Control Board (RPCB) Air Act)
b) Consent to Operate (under Water Act & 120 Days
Air Act)
c) Renewal of 'Consent to Operate (under 120 Days
Water Act & Air Act)
d) Authorization under Hazardous Waste 120 Days