Uttar Pradesh Electricity Regulatory Commission (Grant of Connectivity to intra-State Transmission System) Regulations, 2010
Regulations made under The Electricity Act, 2003
- Made under: The Electricity Act, 2003
This text is shown as one document.
Full text
1
UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION
No. UPERC/Secy/Regulation/10 - 1185 Lucknow : Dated, 28th October, 2010
In exercise of powers conferred under section 181 of the Electricity Act, 2003 and
all other powers enabling it in this behalf, and after previous publication, the Uttar
Pradesh Electricity Regulatory Commission, hereby makes the following regulations,
namely :-
1. Short Title and Commencement :
1.1 These regulations may be called the Uttar Pradesh Electricity Regulatory
Commission (Grant of Connectivity to intra-State Transmission System)
Regulations, 2010.
1.2 These regulations shall come into force from the date of their publication in the
Official Gazette.
1.3 These regulations shall apply throughout the State of Uttar Pradesh.
2. Definitions and Interpretations :
2.1 In these regulations, unless the context otherwise requires,-
(a) “Act” means the Electricity Act, 2003 (36 of 2003) as amended from time to
time;
(b) “applicant” means
- a generating company, which owns or operates or maintains a
generating station (including a captive generating plant) having installed
capacity of 5 MW and above, seeking connectivity for its new / modified /
expanded generating plant / electrical plant at voltage 33 kV and above;
or
2
- a distribution licensee, seeking connectivity for new / modified /
augmented substation or generating station and / or electric line at
voltage 33 kV and above; or
- a captive user or an open access consumer, seeking connectivity for its
new / modified / augmented substation and / or electric line to receive
electricity exceeding 10 MW at voltage 132 kV and above:
Provided that an application for connectivity is not required to be made
by any intra-State transmission licensee (other than the State Transmission
Utility), since transmission system planning is carried out in a co-ordinated
manner by the State Transmission Utility and the Central Electricity
Authority.
Explanation: An application for connectivity is not required to be made by
any captive user or open access consumer for receiving electricity upto and
including 10 MW at voltage below 132 kV, since their requirement shall be
taken up and integrated by the distribution licensee of their area in the
planning and development of distribution system.
(c) “captive user” means the person or member, within the meaning of section
2(8) of the Act, who has constructed a captive generating plant primarily for
his own use;
(d) “Commission” means the Uttar Pradesh Electricity Regulatory Commission
as referred to in sub‐section (1) of section 82 of the Act;
(e) “connection agreement” means an agreement between the State
Transmission Utility, intra-State transmission licensee (other than the State
Transmission Utility if any) and any applicant setting out the terms relating
to connectivity to the intra-State transmission system;
3
(f) “connection offer” means an offer made by the Nodal Agency to the
applicant along with terms, conditions and modalities for execution of
connectivity as referred to in clause 7.3 hereof;
(g) “connectivity” for an applicant or an intra-State transmission licensee (other
than the State Transmission Utility) means the state of getting connected to
the intra-State transmission system at voltage 33 kV and above;
(h) “inter-connection facilities” at point of connectivity in respect of generating
station other than those generate non-firm power means equipments,
control, protection & metering devices and all other appurtenants required at
feeder bay of concerned sub-station / switchyard of the State Transmission
Utility / any other transmission licensee;
(i) “interconnection point “ or “point of connectivity” means the interface point or
point(s) at which generating plant / electrical plant and / or electric line
(including inter-connection facilities) of the applicant or the intra-State
transmission licensee (other than the State Transmission Utility) is
connected to the intra-State transmission system;
(j) “Nodal Agency” means the State Transmission Utility for grant of
connectivity to the intra-State transmission system and related matters;
(k) “non-firm power” means the power generated from renewable energy
sources where the hourly variation is dependent upon natural phenomenon
such as sun, wind, etc., and which cannot be accurately predicted;
(l) “open access consumer” means any consumer availing or intending to avail
open access as specified by the Commission under sub-section (2) of
section 42 of the Act;
(m) “pooling station” means the sub-station or switchyard which shall be
constructed, owned, operated and maintained by the applicant(s) on their
own cost for connecting generating stations generating non-firm power;
4
(n) “procedure” means the procedure as laid down for grant of connectivity to
the intra-State Transmission System and related matters;
(o) “State” means the State of Uttar Pradesh;
(p) “State Grid Code” or “UPEGC” means the State Grid Code specified by the
Commission under clause (h) of sub-section (1) of section 86 of the Act;
(q) “State Transmission Utility (STU)” means the Board or the Government
company specified as such by the State Government under sub-section (1)
of section 39 of the Act;
(r) “user” means a person such as a generating company (including captive
generating plant and non-conventional energy sources based generating
station) or an intra-State transmission licensee (other than the State
Transmission Utility) or a distribution licensee or a captive user or an open
access consumer, whose generating plant / electrical plant and / or electric
line is connected to the intra-State transmission system at voltage 33 kV or
132 kV and above, as the case may be.
2.2 Words and expressions used in these regulations and not defined herein but
defined in the Act or the Central Electricity Authority (Technical Standards for
Connectivity to the Grid) Regulations, 2007 or the State Grid Code or any other
regulations specified by the Commission shall, unless the context otherwise
requires, have the same meaning as assigned to them therein under the Act or
the Central Electricity Authority (Technical Standards for Connectivity to the Grid)
Regulations, 2007 or the State Grid Code or other regulations specified by the
Commission.
3. Extent of Application :
These regulations shall be applicable to generating companies (including captive
generating plants and non-conventional energy sources based generating
5
stations), distribution licensees, captive users, open access consumers, intra-
State transmission licensees and the State Transmission Utility.
4. Nodal Agency :
The State Transmission Utility shall act as the Nodal Agency to undertake
functions incidental to grant of connectivity to intra-State transmission system in
accordance with the procedure and under the provisions of these regulations.
5. Procedure :
The Nodal Agency shall develop and submit within sixty (60) days of issue of
these regulations the draft procedure for approval of the Commission:
Provided that nothing in these regulations bar the Commission from issuing
the procedure on its own motion, by general or special order as it considers
appropriate, in consultation with the Nodal Agency and other stakeholders in
case the Nodal Agency fails to submit the draft procedure or in view of special
circumstances for which the reasons shall be recorded in writing.
6. Application for Connectivity :
6.1 Application for grant of connectivity shall be made to the Nodal Agency:
Provided that the application for connectivity shall contain such details as
may be laid down under the procedure, and, in particular, shall include the
geographical location of the generating plant / electrical plant, injection / drawl
point, commissioning schedule, quantum of power to be interchanged (i.e. the
quantum of power to be injected and / or the quantum of power to be drawn)
through the intra-State transmission system:
Provided further that technical details of the generating station, as referred
to in clause (a) of sub-section (3) of section 10 of the Act, shall be submitted to
the Commission.
6
6.2 The application referred to in clause 6.1 shall be accompanied by a non-
refundable application fee specified hereunder (or as determined by the
Commission from time to time by an order), payable in the name and in the
manner laid down in the procedure:–
S. No.
Quantum of power to be injected / drawn
through the intra-State transmission system
Application fee
(Rs. in lac)
1. Up to 100 MW 2
2. More than 100 MW and up to 500 MW 3
3. More than 500 MW and up to 1000 MW 6
4. More than 1000 MW 9
Provided that for the quantum of power to be injected up to 10 MW by a
generating station based on non-conventional energy sources or for the quantum
of power to be drawn up to 10 MW by a distribution licensee, the non-refundable
application fee shall be Rs. 0.10 lac.
6.3 In cases where once an application has been filed and thereafter there has been
any material change in the location of the generating plant / electrical plant,
injection point / drawl point or material change in the quantum of power to be
interchanged with the intra-State transmission system, the applicant shall make a
fresh application, which shall be considered in accordance with these
regulations.
6.4 In respect of the quantum of power to be interchanged with the intra-State
transmission system, the material change as referred to in clause 6.3 shall be
any change which is more than:
(a) fifteen percent (15%) of the quantum of power declared for interchange in
the original application in respect to applications submitted for grant of
connectivity up to 500 MW;
(b) 100 MW in the quantum of power declared for interchange in the original
application in respect to applications submitted for grant of connectivity for
more than 500 MW.
7
6.5 Any change in voltage level of connectivity shall require a fresh application for
grant of connectivity.
7 Grant of Connectivity :
7.1 The application for grant of connectivity shall be processed by the Nodal Agency
ensuring that the applicant has complied with provisions of the State Grid Code,
the Central Electricity Authority (Technical Standards for Connectivity to the Grid)
Regulations, 2007, as amended from time to time, in addition to mutually agreed
requirements.
7.2 The Nodal Agency shall carry out the necessary interconnection study as
specified in the Central Electricity Authority (Technical Standards for Connectivity
to the Grid) Regulations, 2007 and the State Grid Code, as amended from time
to time. Necessary coordination and consultation shall be established with other
agencies / users connected or to be connected with the intra-State transmission
system for materializing the connectivity. The Nodal Agency shall determine, but
not limited to, point of connectivity, required inter-connection facilities and the
necessity of any modifications required in the existing intra-State transmission
system, if any, as a consequence of grant of connectivity:
Provided that while granting connectivity in case of plant generating non-
firm power, the requirements as per Schedule to these regulations shall be
complied with, besides the general connectivity conditions given in these
regulations:
Provided further that in case of intra-State transmission licensee, on the
basis of approved transmission plan, the State Transmission Utility shall finalize
connectivity of such transmission licensee which shall be deemed to be grant of
connectivity:
Provided also that the intra-State transmission licensee may be required to
furnish additional information essential for signing of connection agreement:
8
Provided also that an intra-State transmission licensee (other than the State
Transmission Utility) shall sign a connection agreement with the State
Transmission Utility, as provided for in clause 8 hereof.
7.3 The Nodal Agency shall make a ‘connection offer’, along with terms, conditions
and modalities for execution of connectivity, to the applicant within one hundred
twenty (120) days from the date of receipt of application, with direction to the
applicant to sign the connection agreement. Such offer shall be deemed to be
grant of connectivity subject to signing of the connection agreement by the
applicant as provided for in clause 8 hereof:
Provided that in case an application is rejected, the rejection and reasons
for rejection shall be communicated to the applicant in writing by the Nodal
Agency within ninety (90) days from the date of receipt of application:
Provided further that before an application is finally rejected, the applicant
shall be given a reasonable opportunity of being heard.
7.4 A person aggrieved by the decision of the Nodal Agency under proviso to clause
7.3 may approach the Commission for redressal within forty five (45) days from
the date of such decision and the Commission may pass order, as deemed
appropriate.
7.5 While granting connectivity, the Nodal Agency shall specify the name of the sub-
station or switchyard or pooling station where connectivity is to be granted. In
case connectivity is to be granted by looping-in and looping-out of an existing or
proposed transmission line, the Nodal Agency shall specify the point of
connectivity and the name of the transmission line to which connectivity is to be
granted:
Provided that in case of solar photovoltaic and wind energy generating
station the point of connectivity shall be line breaker on outgoing feeder on HV
side of the pooling station, and for solar thermal generating station, the point of
9
connectivity shall be line breaker on outgoing feeder on HV side of generator
transformer.
7.6 The requirement of connectivity brought out in interconnection study shall be
integrated by the State Transmission Utility to the Transmission Plan.
7.7 The applicant and all intra-State transmission licensees including the State
Transmission Utility shall comply with the provisions of the Central Electricity
Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007,
other regulations of the Central Electricity Authority and the State Grid Code, as
amended from time to time, and in particular, but not limited to, the technical
requirements for connectivity to the grid i.e. voice and data communication
facilities, system recording instruments, responsibilities for safety, cyber security,
reactive power compensation and other statuary provisions.
7.8 These regulations shall supersede any other regulation or code or order thereof
issued / passed by the Commission in regard to the grant of connectivity in
respect of intra-State transmission system.
8. Execution of Connection Agreement :
8.1 The applicant or intra-State transmission licensee, as the case may be, shall sign
within forty five (45) days (unless otherwise indicated by the Nodal Agency) from
the date of ‘connection offer’, a connection agreement with the State
Transmission Utility / any other transmission licensee owning the sub-station or
switchyard or the transmission line as identified by the Nodal Agency where
connectivity is being granted:
Provided that in case connectivity is granted to a generating station
(including captive generating plant / non-conventional energy sources based
generating station) or a distribution licensee or a captive user or an open access
consumer to the intra-State transmission system of a transmission licensee other
than the State Transmission Utility, a tripartite connection agreement shall be
10
signed between the applicant, the State Transmission Utility and such
transmission licensee:
Provided further that the Nodal Agency shall prepare and submit within sixty
(60) days of issue of these regulations the model connection agreement(s) for
approval of the Commission.
8.2 If the applicant fails to enter into the connection agreement within the period
stipulated in clause 8.1, the Nodal Agency shall notify the parties to do so within
thirty (30) days failing which the grant of connectivity to the applicant shall be
deemed to have been withdrawn unless the applicant has been granted
additional time by the Nodal Agency under clause 8.3 hereunder.
8.3 The applicant may seek additional time beyond the period stipulated under
clauses 8.1 and 8.2 above, to sign the connection agreement, citing reasons
thereof. The Nodal Agency on being satisfied of the reasons cited by the
applicant may grant additional time for such period as it considers appropriate:
Provided that the additional time granted by the Nodal Agency above to sign
the connection agreement shall be granted to an applicant only once. Thereafter
any further request for grant of connectivity by the same applicant shall be
treated as a fresh application.
8.4 In the event of withdrawal of grant of connectivity under clause 8.2, the Nodal
Agency shall not be required to consider any further application from the same
applicant within twelve (12) months from the date of withdrawal of grant of
connectivity unless new application is substantially different from the original
application.
8.5 In case of modification to existing or proposed point of connectivity due to any
non-material change such as re-allocation of bays etc. by either of the parties of
the connection agreement, if mutually agreed, an amendment to the connection
agreement shall be executed between such parties subject to prior approval of
the Nodal Agency.
11
8.6 The decision of the Nodal Agency under clause 8.1 to clause 8.5 shall be final
and binding.
9. Construction, Operation and Maintenance of Inter-connection Facilities :
9.1 The State Transmission Utility / any other transmission licensee may be required
by the applicant or intra-State transmission licensee, as the case may be, to
construct, operate and maintain interconnection facilities at the point of
connectivity as below:
(a) The applicant or intra-State transmission licensee, as the case may be, shall
pay cost of construction of interconnection facilities on such terms and
conditions as may be specified by the State Transmission Utility / any other
transmission licensee.
(b) The State Transmission Utility / any other transmission licensee shall be
responsible for operation and maintenance of interconnection facilities and
the ownership of such interconnection facilities shall be deemed to have
been transferred by the applicant or intra-State transmission licensee, as
the case may be, to the State Transmission Utility / any other transmission
licensee. The operation and maintenance cost of such facilities shall be
included in the transmission charges of the State Transmission Utility / any
other transmission licensee.
9.2 The cost other than that referred to in clause 9.1(a) shall be borne by the State
Transmission Utility / any other transmission licensee.
Note: In case of plant generating non-firm power, the cost / expenses incurred for
accommodating the proposed connectivity and other matters connected
therewith shall be recovered as per Schedule to these regulations.
10. Construction, Operation and Maintenance of Dedicated Transmission Lines
10.1 In case of generating station other than those generate non-firm power, an
applicant may be required by the State Transmission Utility to construct a
12
dedicated transmission line (excluding the inter-connection facilities) up to the
point of connectivity to enable connectivity to the intra-State transmission system
which shall be owned, maintained and operated by the applicant. The
expenditure incurred towards construction, operation and maintenance of such
dedicated transmission line shall be borne by the applicant. The construction
shall be undertaken under supervision of the State Transmission Utility / any
other transmission licensee on payment of supervision charges approved by the
Commission:
Provided that a generating station of above 100 MW or one that is getting
connected to the intra-State transmission system at voltage 220 kV and above
(but excluding captive generating plants), shall be taken into account for
coordinated transmission planning by the State Transmission Utility and the
Central Electricity Authority and such transmission system shall be undertaken
by the State Transmission Utility or any other transmission licensee.
10.2 In cases where construction of such dedicated transmission line is undertaken by
the State Transmission Utility / any other transmission licensee at the option of
the applicant, such applicant shall sign a Dedicated Evacuation Agreement
(DEA) on terms and conditions as mutually agreed:
Provided that the applicant shall make payment of the cost of construction
of the dedicated transmission line to the State Transmission Utility or any other
transmission licensee.
10.3 In cases where maintenance of such dedicated transmission line is undertaken
by the State Transmission Utility / any other transmission licensee at the option
of the applicant, such applicant shall sign an Annual Maintenance Contract on
terms and conditions as mutually agreed:
Provided that the applicant shall make payment of the annual maintenance
charges for meeting expenses towards maintenance of the dedicated
13
transmission line to the State Transmission Utility / any other transmission
licensee.
10.4 In cases where construction or maintenance of such dedicated transmission line
is undertaken by any other agency (State Transmission Utility / any other
transmission licensee) at the option of the applicant, the Commission shall
assume no role to adjudicate upon the disputes between such licensee and
applicant or refer such dispute for arbitration.
Note: In case of plant generating non-firm power, construction and operation /
maintenance of evacuation infrastructure shall be undertaken as per Schedule to
these regulations.
11. Metering :
For installation of meters, its testing, calibration and reading and all matters
incidental thereto, the applicant or intra-State transmission licensee, as the case
may be, shall follow and be bound by the Central Electricity Authority (Installation
and Operation of Meters) Regulations, 2006, the State Grid Code and Availability
Based Tariff as amended and revised from time to time and shall also comply
with all metering requirements as notified by the State Transmission Utility.
12. Synchronization and Commissioning :
12.1 The applicant or intra-State transmission licensee, as the case may be, shall give
the Nodal Agency, the State Load Despatch Centre and other concerned
persons (including transmission licensee) at least sixty (60) days advance
preliminary written notice and at least thirty (30) days advance final written
notice, of the date on which it intends to synchronise its generating plant and/or
electrical plant and/or electric line to the State Grid.
12.2 Testing/retesting and measurement procedures applied during each
commissioning test shall be in accordance with the codes, practices and
procedures as generally / normally applied for the commissioning tests.
14
12.3 All costs, risk and expenses in synchronising, commissioning and/or testing or
retesting as referred hereinabove shall solely and completely be borne by the
applicant or intra-State transmission licensee, as the case may be.
13. Operation and Maintenance :
The applicant or intra-State transmission licensee, as the case may be, shall
comply with the provisions of the applicable Laws including, in particular, the
State Grid Code (as amended form time to time) regarding operation and
maintenance of the generating plant / electrical plant and/or electric line, as the
case may be, and all matters incidental thereto.
14. Interchange of Power with Intra-State Transmission System :
14.1 Even before availing any type of open access, a generating station (including
captive generating plant and a non - conventional energy sources based
generating station) which has been granted connectivity to the intra-State
transmission system shall be allowed to undertake interchange of power
including drawl of power for its commissioning activities and injection of infirm
power into the State grid during testing including full load testing before being put
into commercial operation. This shall be permitted only after it obtains permission
of the State Load Despatch Centre, who shall keep grid security in view while
granting such permission:
Provided that interchange of infirm and start up power through the grid shall
be subject to prior contract between the generating station and distribution
licensee(s):
Provided further that existing generating stations shall also ensure that
requirement of start up power is also agreed to with distribution licensee if such
agreement does not already exist.
14.2 The grant of connectivity shall not entitle an applicant / any other person to
undertake interchange of power through the grid (except for purposes mentioned
15
in clause 14.1 hereinabove) unless open access has been obtained in
accordance with the regulations specified by the Appropriate Commission.
Note: A person can apply for open access after application for connectivity has
been received by the Nodal Agency. However, separate application(s) for
connectivity and for open access may be submitted simultaneously to save time.
The application for open access shall be entertained only after grant of
connectivity under clause 7.3.
15. Treatment of Existing Connectivity :
15.1 The user already connected to the intra-State transmission system or for which
connectivity is already granted by the Nodal Agency under any other regulation
or order of the Commission, need not apply for connectivity afresh for the same
capacity. However, in case of extension of capacity of generating plant / electrical
plant or contracted load or augmentation of substation / electric line, as the case
may be, the user shall be required to apply afresh for connectivity under these
regulations.
15.2 In respect of existing connections to the intra - State transmission system, all
existing users shall enter into a connection agreement with the State
Transmission Utility. However, a relaxation of one year from the date of
notification of these regulations is allowed so that present arrangement may
continue in the interim till the connection agreement is established between the
concerned parties.
16. Exit Option :
A person shall relinquish or transfer his rights and obligations as specified in the
connection agreement unless it applies to the Nodal Agency at least six (6)
months prior to such relinquish or transfer.
17. Information System :
16
The Nodal Agency shall post the following documents / information on its website
in a separate web-page titled “Connectivity”:
(a) These regulations;
(b) Procedure as laid down under these regulations;
(c) List of applications received by the Nodal Agency for connectivity along with
necessary details;
(d) List of applicants granted connectivity, indicating;-
(i) Name of applicant;
(ii) Point of connectivity;
(iii) Name of transmission system;
(iv) Capacity (MW) for which connectivity has been granted.
(e) List of applications where approval for connectivity has not been granted
along with reasons thereof;
18. Redressal Mechanism :
All disputes arising out of or under these regulations shall be decided by the
Commission on a petition made in this behalf by the person aggrieved unless
provided otherwise.
19. General Power to Amend :
The Commission may, at any time and on such terms as it may deem fit, amend /
vary / delete / modify any of the provisions of these regulations and make
necessary amendments thereof.
20. Power to relax :
The Commission by general or special order may, for reasons to be recorded in
writing, relax any of the provisions of these regulations on its own motion or on
an application made before it by an interested person.
17
21. Miscellaneous :
21.1 Nothing in these regulations shall be deemed to limit or otherwise affect the
power of the Commission to make such orders as may be necessary to meet the
ends of justice or to prevent abuse of process of the Commission.
21.2 Nothing in these regulations shall bar the Commission from adopting in
conformity with provisions of the Act, a procedure which is at variance with any of
the provisions of these regulations, if the Commission, in view of the special
circumstance of matter or a class of matters and for reasons to be recorded in
writing, deems it just or expedient for deciding such matter or class of matters.
22. These Regulations are made in English and translated into Hindi. In case of
dispute, the English version shall prevail.
By order of the Commission
(A. K. Srivastava)
Secretary
Uttar Pradesh Electricity Regulatory Commission
Lucknow
18
SCHEDULE
Promotional Measures/ Conditions for Plants generating Non-firm Power
1. Connectivity of Generation Facility :
The Nodal Agency shall provide interconnection at the nearest pooling station:
Provided that where it is not feasible for the Nodal Agency to provide inter-
connection at the nearest pooling station, it shall propose to the applicant, other
feasible interconnection pooling station or sub-station or switchyard:
Provided further that the said proposal, along with the reasons for not
allowing interconnection at the nearest pooling station, shall be communicated in
writing to the applicant within forty five (45) days from the date of receipt of
application to the applicant.
Note: The interconnection point shall be common for all generating plants
connected to the pooling station.
2. Construction and Operation / Maintenance of Evacuation Infrastructure :
2.1 The applicant shall construct, operate and maintain its generation facility (up to
the point of connectivity) including pooling station at its own expense. For
construction and operation / maintenance of evacuation infrastructure beyond
point of connectivity up to main receiving sub-station or switchyard of the State
Transmission Utility / any other transmission licensee, the following shall be
responsible:
(a) for 33 kV and above works - the distribution licensee;
(b) for 132 kV and above - the State Transmission Utility / any other
transmission licensee (owning the main receiving sub-station or switchyard
or the transmission line as identified by the Nodal Agency where
connectivity is being granted)
19
2.2 The evacuation infrastructure construction cost and its operation / maintenance
cost as referred to in clause 2.1 of this Schedule shall be borne by -
(a) the distribution licensee and/or the State Transmission Utility / any other
transmission licensee, as the case may be, in case of supply of electricity
from a generating station to the distribution licensee of the area at the tariff
determined by the Commission. The cost incurred shall be allowed in tariff
of the distribution licensee and / or the State Transmission Utility / any other
transmission licensee, as the case may be;
(b) the applicant, in cases other than sub-clause (a) of clause 2.2 of this
Schedule.
2.3 For recovery of cost as referred to in sub-clause (a) of clause 2.2, the distribution
licensee and / or transmission licensee, as the case may be, shall, in consultation
with the State Transmission Utility, Non-conventional Energy Development
Agency or any other person whom it may deem fit, prepare a scheme for
augmenting and establishing the distribution system and / or transmission system
and evacuation infrastructure(s) beyond the point of connectivity(ies)
corresponding to the commissioning of the generating station(s). The scheme
shall be submitted by the concerned distribution licensee and the transmission
licensee for the approval of the Commission and expenditure allowed therein
shall be a pass through in tariff of the concerned distribution licensee and / or the
transmission licensee, as the case may be,
2.4 For recovery of cost as referred to in sub-clause (b) of clause 2.2, the applicant
shall sign Dedicated Evacuation Agreement(s) (DEAs) on such terms and
conditions as mutually agreed separately with concerned licensee(s), within forty
five (45) days of grant of connectivity:
Provided that the applicant shall make payment of the cost of construction
of dedicated evacuation infrastructure to the concerned licensee(s).
20
3. Co-ordination Committee :
The Commission shall, either on its own motion or on request of the Nodal
Agency, constitute by an order as deemed appropriate a co-ordination committee
in the State Load Despatch Centre and the State Transmission Utility within sixty
(60) days of issue of these regulations to ensure smother operations and grid
integration of non-firm renewable energy sources including the creation and
maintenance of database regarding future non-firm power generating stations.