Uttar Pradesh Electricity Regulatory Commission (FEES AND FINES) Regulations 2010
Regulations made under The Electricity Act, 2003
- Made under: The Electricity Act, 2003
This text is shown as one document.
Full text
UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION
(UPERC)
FEES & FINES REGULATIONS, 2010
Notification No. 429/24
Date- April 27, 2010
In exercise of powers conferred on it by Section 86 (1) (g) of the Electricity Act, 2003 and Section
52 of the Uttar Pradesh Electricity Reforms Act-1999 (U.P. Act No. 24 of 1999) in so far as these
are not inconsistent with the provisions of Electricity Act, 2003, and all powers enabling it in that
behalf, the Uttar Pradesh Electricity Regulatory Commission hereby makes the following
amendments to the UPERC (Fees and Fines) Regulations-2010.
AND
FIRST ADDENDUM/AMENDMENT TO UTTAR PRADESH ELECTRICITY REGULATORY
COMMISSION (FEES AND FINES) REGULATIONS, 2010
Notification No. UPERC/Secy./Regulation/1523
December 11, 2018
In exercise of powers conferred on it by Section 86(1)(g) of the Electricity Act, 2003 and Section
52 of the Uttar Pradesh Electricity Reforms Act, 1999 (U.P. Act no. 24 of 1999) in so far as these
are not inconsistent with the provisions of Electricity Act, 2003, and all powers enabling it in that
behalf, the Uttar Pradesh Electricity Regulatory Commission hereby makes the following
amendments to the UPERC (FEES AND FINES) REGULATIONS, 2010:
Chapter I
GENERAL
1.0 Short Title, Extent and Commencement
1.1 These regulations may be called the Uttar Pradesh Electricity Regulatory Commission (Fees
and Fines) Regulations, 2010.
1.2 These Regulations extend to the whole of the State of Uttar Pradesh.
1.3 These Regulations shall come into force from the date of their publication in the official
Gazette of Government of Uttar Pradesh.
Chapter II
DEFINITIONS AND INTERPRETATIONS
2.0 Definitions and Interpretation:
2.1 In these regulations, the words and expressions used shall have the same meaning as defined
in the Electricity Act-2003 and UP Electricity Reforms Act-1999 to the extent not inconsistent
with the Electricity Act-2003, jointly referred to as Acts under these regulations.
2.2 In the interpretation of these Regulations, unless the context otherwise requires:
i. Words in the singular or plural term, as the case may be, shall also be deemed to include
the plural or the singular term, respectively.
ii. The terms "include" or "including" shall be deemed to be followed by "without limitation"
or "but not limited to" regardless of whether such terms are followed by such phrases or
words of like import.
iii. References herein to the "Regulation" shall be construed as a reference to these
Regulations as amended or modified by the Commission from time to time in accordance
with the applicable laws in force.
iv. The headings are inserted for convenience and may not be taken into account for the
purpose of interpretation of these Regulations.
v. References to the statutes, regulations or guidelines shall be construed as including all
provisions consolidating, amending or replacing such statutes, regulations or guidelines,
as the case may be, referred to.
vi. Reference herein to the "Schedules" shall be construed as a reference to the 'Schedule of
Fee' & ‘Schedule of Pre-specified Fines/Penalties’ annexed to these regulations as
amended or modified by the Commission from time to time in accordance with the
applicable laws in force.
Chapter-III
FEES
3.0 Fees on Applications and Petitions
3.1 Every application, petition and appeal made to the Commission shall be accompanied by such
Fees as specified in the Schedule.
3.2 The Fees payable under these Regulations shall be paid by means of bank draft or pay order,
drawn in favour of 'Secretary, Uttar Pradesh Electricity Regulatory Commission', payable at
Lucknow.
3.3 The fees received by the Secretary of the Commission under these regulations shall be
deposited in a bank account to be maintained by the Commission.
4.0 Annual License Fee Payable by licensees
4.1 All existing licensees as well as deemed licensees shall pay an annual license fee as specified
in the Schedule.
4.2 In addition to the annual fee, new entrants seeking license from the Commission shall be
required to pay initial fee as specified in the Schedule for processing their application for grant of
license or exemption.
4.3 Annual license fee as specified under these regulations for each year shall be paid by 15th July
of that year. The date of submission of annual license fee as mentioned in this regulation shall
supersede the date as may be mentioned in any other regulation of the Commission.
4.4 In case of late payment of annual fee, interest will be payable on the delayed amount at the
rate of 1.25% per month.
4.5 The Commission shall have the right to recover any amount of fee outstanding or under-
realised, as and when it comes to its notice.
Chapter-IV
FINES
5.0 Imposition of Fines
5.1 Subject to the provisions of the Acts, the Commission may initiate a proceeding for imposition
of fines against any person (s) including generating companies and licensees for non-compliance
or violation on their part of the provisions or requirements of the Acts or Rules, Regulations &
Codes framed under the Acts or the directions or the orders of the Commission made from time
to time.
5.2 The provisions of UPERC (Conduct of Business) Regulations, 2004, shall apply mutatis
mutandis to such proceedings for imposition of fines.
5.3 While determining the quantum or extent of the fines to be imposed, the Commission shall
consider, amongst other relevant things, the following:
a) The nature and extent of non-compliance or violation.
b) The wrongful gain or unfair advantage derived as a result of the non-compliance or
violation.
c) The loss or degree of harassment caused to any person(s) as a result of the non-
compliance or violation.
d) The repetitive nature of the non-compliance or violation.
5.4 Before imposing any fines, the Commission shall give an opportunity to the person (s) upon
whom such Fines are proposed to be imposed, to represent against the proposal to impose such
Fines.
5.5 The Commission shall issue a notice to the person(s) specifying the nature of non-compliance
or violation on the person’s part and show cause him within the time specified in the notice as to
why Fines may not be imposed on him for such non-compliance or violation.
5.6 Based on the proceedings if the Commission reaches to the conclusion that a deliberate non-
compliance or violation has been committed by the person(s), the Commission shall record it and
may impose such Fines as it may consider fit in the circumstances of the case, subject to the
provisions of the Acts.
5.7 The Commission may on being satisfied that no non-compliance or violation of any provision
of the Acts, Rules or Regulations or an Order of the Commission has been committed, discharge
the notice.
5.8 The Commission shall have undivided powers to reduce or relax the pre-specified
fines/penalties through speaking order after providing an opportunity of hearing to the person,
subsequent to issuing him notice to the effect of imposition of specified fine/penalty.
6.0 Payment of Fines
6.1 The fines as ordered by the Commission shall be paid within 30 days of the order of the
Commission imposing the Fines or within such extended date as may be allowed by the
Commission in such order.
6.2 The fines/penalties shall be payable in the same manner as provided under sub-clause (ii) of
clause 3 of these Regulations. These fines/penalties will have to be mandatorily reflected in
Annual Accounts of the Generator or the Licensee as the case may be, but will not form part of
admissible expenditure under ARR.
6.3 If the fines ordered by the Commission are not paid within the prescribed time, they shall be
recovered as if it were an arrear of land revenue.
7.0 Amendment of Schedule
7.1 The Commission shall be entitled from time to time to add, amend, alter or vary the amounts
of Fees payable or the amounts of Fines/Penalties payable as provided in Schedules to these
regulations by an order to be made by the Commission subject to the condition specified under
section 181(3) of the Electricity Act, 2003, as it deems fit.
8.0 Power to remove difficulty
8.1 If any difficulty arises in giving effect to any of the provisions of these regulations, the
Commission may pass general or special order, not being inconsistent with the provisions of the
Acts, as may be necessary or expedient for the purpose of removing the difficulties.
9.0 Miscellaneous
9.1 Nothing in these Regulations shall be deemed to limit or otherwise affect the power of the
Commission to make such orders as may be necessary to meet the ends of justice.
9.2 Nothing in these Regulations shall bar the Commission from adopting in conformity with
provisions of the Acts, a procedure which is at variance with any of the provisions of these
Regulations, if the Commission, in view of the special circumstances of a matter or a class of
matters and for reasons to be recorded in writing, deems it just or expedient for deciding such
matter or class of matters.
9.3 Nothing in these Regulations shall, expressly or impliedly, bar the Commission dealing with
any matter or exercising any power under the Acts for which no regulations have been framed,
and the Commission may deal with such matters, powers and functions in a manner, as it
considers just and appropriate.
Sl. No. Nature of Application/Petition Fee
Part A- General
1 Application for inspection of documents of
the Commission.
Rs 500/Day
2 Petition/Application for approval of
investment in utility by the licensee.
0.05% of project cost for which
approval is sought.
3 Petition/Application for review of order for
approval of investment in utilities.
Rs. 10,000 (Rs. Ten Thousand
only)
4 Supply of certified copies of
documents/orders of the Commission.
Rs. 5/page
5 Applications for approval under section-17
of Electricity Act-2003.
0.01% value of the transaction
for which approval is sought.
Minimum Rs 5 Lakhs and
maximum Rs 20 Lakhs.
6 Miscellaneous applications i.e. application
not covered elsewhere.
a. Rs.25,000/ application if
filed by licensee or generating
company.
b. Rs.1,000/ application if filed
by anybody other than
licensee or generating
company.
7 Application for review or reconsideration of
any order of the Commission not covered
elsewhere.
50% of the original fee however
Commission may exempt if
review is concerned with small
consumers.
8 Surcharge for delay in submission of the
Petition.
Rs. 5,000 per day from due date
(if prescribed by the
Commission) up to the actual
date of submission. However,
this provision shall not be
applicable in case of delay in
submission of MYT/APR/True
up petitions for which a separate
express provision has been
suggested under fine portion.
Part B - Resolution of Disputes and Complaints
1 Complaint against the working of a
licensee/generating company.
Rs. 1,000 (Rs. One Thousand
only)
2a Adjudication of disputes and differences
between licensees and generating
companies and between licensees.
a. 0.05% of the disputed revenue
in revenue disputes.
b. Rs. 20,000/- in other than
revenue disputes.
2b Review petitions/ applications in this
regard.
25% of the fee paid for original
application.
3 Application for adjudication of dispute
regarding provision of non-discriminatory
open access under Section 39 (2) (d), 40 (c)
& 42 (2) of EA-2003 if such dispute is not
resolved by SLDC.
a. For a licensee or a generating
company Rs. 5 Lakhs.
b. For a person who has
constructed and maintains and
operates a captive generating
plant- Rs. 1 Lakh.
C. For a person having a captive
generating plant of energy from
renewable sources -Rs. 20,000.
d. For a consumer - Rs. 5,000.
4 Adjudication of disputes regarding extent of
surplus capacity under the proviso of
section 35.
Rs 5 Lakhs
5 (a) For adjudication on adequacy of
Transmission capacity U/s 9 of the Act.
(b) Review of order issued under 5 (a).
(a) Rs.50,000.
(b) Rs. 25,000.
6 (a) Dispute related to integrated grid
operation U/s 33(4).
(b) Review of order issued under 6 (a).
(a) Rs. 50,000.
(b) Rs. 25,000.
7 Disputes arising under sub-section 4 and 5
of Section 67 of the Act, (opening of Streets,
Railways etc).
Rs. 25,000.
Part C – Grant of License
1 Application/Processing Fee to accompany
application for grant of Distribution and
Retail Supply Licence, Transmission and
Trading in electricity.
Rs. 5,00,000.
or
Fee as may be prescribed by the
State Government under the
provisions of Electricity Act,
2003.
2 Annual Licence Fee payable by the
Distribution Licensee.
0.04% of amount to be billed by
the licensee initially at the time of
grant of licence and annual
payment at the same rate in each
subsequent financial year during
the validity of the licence.
or
Fee as may be prescribed by the
State Government.
3 Annual Licence Fee payable by the
Transmission Licence.
The transmission licensee on
being issued with intrastate
transmission license shall pay
the license fee at the rate of Rs
5.00 Lakhs per annum from date
of grant of license up to the date
of commercial operation of the
transmission system or an
element thereof. Subsequent to
commercial operation, the
licensee shall pay Rs 500.00 for
every million units of electricity
or part thereof handled by the
licensee in each subsequent
financial year during the validity
of the license. In case of partial
operation of the system in the
first year, the license fee shall be
charged at the same rate on pro-
rata basis.
Or
Fee as may be prescribed by the
State Government under the
provisions of Electricity Act,
2003.
4 Annual licensee fee to be paid by trading
licensee.
0.05 percent of the amount
billed/to be billed by the licensee
initially at the time of grant of
license, and annual payments at
the same rate in each subsequent
financial year during the validity
of the license.
or
Fee as may be prescribed by the
State Government under the
provisions of Electricity Act,
2003.
5 Fee to accompany review
application/petition for review of order on
application/petition for grant of
Distribution, Transmission or Trading
Licence.
Rs. 50,000 (Rs. Fifty Thousand)
or
Fee as may be prescribed by the
State Government under the
provisions of Electricity Act,
2003.
6 Application for amendment of license a. By licensee Rs. 1 Lakh.
b. By others Rs. 10,000.
7 Application seeking exemption from grant
of license
Rs 1 Lakh
8 Annual License fee for:
a) Special Economic Zone
b) Rural Electric Co-operative Society
(a) Rs. 1,00,000 per annum.
(b) Rs. 50,000 per annum,
however, Commission may relax
this fee if it feels appropriate.
9 Application for revocation of license under
sub-section (2) of Section 19 of the
Electricity Act.
a. By licensee Rs. 1,00,000.
b. By others Rs. 10,000.
Part D- Setting Tariff
1 Annual determination of tariff for retail sale
of electricity.
Rs. 10 Lakhs + Rs. 500 per MVA of
peak demand up to a maximum
of Rs. 50 Lakhs.
2 Annual determination of tariff for
Transmission of electricity.
Rs 15 Lakhs.
3 Fee to accompany review
petition/application for review of order on
Tariff Petition/Application by distribution
and transmission licensees.
Rs 50,000
4 Annual/Base Year determination of
generation tariff.
a) For renewable/Co. gen. generating
stations.
b) Other generating stations.
a) Rs 2000/MW
b) Rs 5000/MW not
exceeding Rs 50 Lakhs.
5 Review petition on determination of
generation tariff.
a) For renewable/Co. gen. generating
stations.
Other generating stations.
a) Rs 5000 only
b) Rs 50000 only.
6 Application for approval of Power Purchase
and procurement process:
a) Renewable Generating sources/Co.
Gen.
b) Others
c) Rs 1 Lakh
d) Rs 10 Lakh up to 100MW
and Rs 10,000 per
additional MW.
7 Fee to accompany Petition/ Application for
review of order for approval of Power
Purchase and procurement process.
a) Renewable Generating sources/Co.
Gen.
b) Others
a) Rs 25,000.
b) Rs 1 Lakh.
8 Determination of Tariff under MYT for retail
sale and wheeling of electricity.
Rs. 10 Lakhs + Rs. 500 per MVA of
peak demand up to a maximum
of Rs. 50 Lakhs.
9 Determination of tariff under MYT for
transmission & wheeling of electricity.
Rs 25 Lakhs.
10 Annual Performance Review of Distribution
Licensee under MYT.
Rs. 5 Lakhs + Rs. 500 per MVA of
peak demand up to a maximum
of Rs. 30 Lakhs.
11 Annual Performance Review of
Transmission Licensee or generating
company under MYT.
Rs 10 Lakhs.
12 Application for adoption of tariff for
short/long/medium term power purchases
to be made through competitive bidding.
Long Term/ Medium Term:
Conventional Fuel based (Coal,
Oil etc.) including Hydel Plant
above 25 MW Rs. 25,000/- per
MW or part thereof [Minimum of
Rs. 2,00,000/- and Maximum of
Rs. 10,00,000/-].
Non-Conventional and
renewable energy sources
including Hydel plant up to
25MW- Rs 10,000/MW or part
thereof [Min of Rs 50,000 and
Max of Rs 5,00,000].
Short Term: Rs 10,000 per
bidding process.
13 Application for Truing up of Tariff order, if
filed as a separate petition.
Rs 1 Lakh
14 (a) Petition with respect to FPPCA.
(b) Review of order issued under 14(a).
a) Rs 50,000
b) Rs 25,000
15 Petition for Tariff adoption towards tariff
discovered through competitive guidelines -
both for generation and transmission.
Rs 25 Lakhs.
Part E- Transmission Issues
1 Petition for determination of rates. charges,
terms and conditions under proviso to sub-
section (1) of Section 36 of the Electricity
Act, 2003 (Petition for use of intervening
transmission facility of another licensee).
Rs 1 Lakh
2 Transmission Service Agreement. Rs. 500 per MW with a minimum
of Rs.15,000/- and maximum of
Rs. 2,00,000/ both for
competitive bid projects and
MoU based projects.
3 Application for determination of Fees and
Charges of the State Load Dispatch Centre.
Rs 5 Lakhs
Schedule of 'Pre-specified Fines/Penalties' has been added as a separate Schedule in
Regulations, 2010: 'Schedule of Pre-specified Fines/Penalties
S.no. Nature of Application/Petition Fines/Penalty (in Rupees)
Part A – Information related to Generation
1 Non-submission of Performance Report by
Generating Companies in term of Section
10(3) of Act & Section 2(7) of UPERC
Generation Tariff Regulations, 14 in the
month of September & March respectively.
(a) Fine of Rs. 50,000.00 on
first contravention and a fine
of Rs.5,000.00 per day during
continuance of
contravention.
(b) If not cured by second
due date, then it will attract a
fine of Rs. 1,00,000.00
followed by a fine of Rs.
10,000.00 per day during
continuance of
contravention.
(c) If not cured by third due
date, then it will attract a fine
of Rs. 2.00,000.00 followed
by a fine of Rs.20,000.00 per
day during continuance of
contravention.
(d) On subsequent defaults,
a fine of Rs. 5,00,000.00 will
be repeatedly imposed
followed by a fine of Rs.
20,000.00 per day during
continuance of
contravention. This is without
prejudice to Commission
taking any other measure as
it may deem fit.
2 Non-submission of data related to cost,
expenditure & operation as per regulation
51(X) of UPERC Generation Tariff
Regulations, 14 in the month of September
& March respectively.
(a) Fine of Rs. 50,000.00 on
first contravention and a fine
of Rs. 5,000.00 per day
during continuance of
contravention.
(b) If not cured by second
due date, then it will attract a
fine of Rs. 1,00,000.00
followed by a fine of
Rs.10,000.00 per day during
continuance of
contravention during the
period subsequent to second
due date.
(c) If not cured by third due
date, then it will attract a fine
of Rs. 2,00,000.00 followed
by a fine of Rs.20,000.00 per
day during continuance of
contravention during the
period subsequent to third
due date.
(d) On subsequent defaults,
a fine of Rs. 5,00,000.00 will
be repeatedly imposed
followed by a fine of Rs.
20,000.00 per day during
continuance of
contravention during the
period subsequent to fourth
due date. This is without
prejudice to Commission
taking any other measure as
it may deem fit.
3 Non-submission of Information in
accordance with Section 11(2) of CRE
Regulations, 2014 within 90 days from date
of notification of regulation.
(a) A fine of Rs. 1,00,000.00
on contravention followed by
an additional fine of Rs.
10,000.00 per day for next 30
days.
(b) If not submitted in next 30
days also, then it will attract
a fine of Rs. 2,00,000.00 will
be imposed along with an
additional fine of Rs.
20,000.00 per day for a
period after 30 days. In such
matters, the Commission
may take any other action
that it may deem fit.
Part B – Information related to Distribution & Supply
1 On non-submission of quarterly MIS
reports giving category wise number of
complaints received and the complaints,
which could not be resolved within the
stipulated time and reasons thereof.
(Reference clause- 7.7.6 sub-clause 4(e) of
supply code).
(a) If the quarterly
information is not submitted
then it will attract a fine of
Rs. 25,000.00 on first default
with a continuing fine of Rs.
2500.00 day during
continuance of failure up to
the second quarter cut-off.
(b) If the information is not
submitted by second quarter
cut-off also, it will attract a
fine of Rs. 50,000.00 with a
fine of Rs. 5,000.00.00 day
after the second quarter cut-
off and during continuance of
failure up to 3rd quarter cut-
off.
(c) If the information is not
submitted by third quarter
cut off also, it will attract a
fine of Rs. 75,000.00 with a
fine of Rs. 7500.00 day after
the third quarter cut-off and
during continuance of failure
up to 4th quarter cut-off.
(d) If the information is not
submitted by 4th quarter cut-
off also, it will attract a fine of
Rs. 1,00,000.00 with an
additional fine of Rs.
10,000.00 per day after the
fourth quarter cut-off and
during continuance of failure
up to 5th quarter cut-off.
(e) Beyond this, it will
continue to attract a fine of
Rs. 10,000.00 per day till the
cure of default.
2 On non-submission of quarterly statement
to the Commission giving zone-wise details
of such bills (bills raised 6 months after
energization) along with compensation
given on this account during the quarter.
(Reference clause-7.7.2 (d) of supply
code).
a) If the quarterly information
is not submitted then it will
attract a fine of Rs. 25,000.00
on first default with a
continuing fine of Rs.
2500.00 day during
continuance of failure up to
the second quarter cut-off.
(b) If the information is not
submitted by second quarter
cut-off also, it will attract a
fine of Rs. 50,000.00 with a
fine of Rs. 5,000.00 day after
the second quarter cut-off
and during continuance of
failure up to 3rd quarter cut-
off.
(c) If the information is not
submitted by third quarter
cutoff also, it will attract a
fine of Rs. 75,000.00 with a
fine of Rs. 7,500.00 day after
the third quarter cut-off and
during continuance of failure
up to 4th quarter cutoff
(d) If the information is not
submitted by 4th quarter cut-
off also, it will attract a fine of
Rs. 1,00,000.00 with an
additional fine of Rs.
10,000.00 per day after the
fourth quarter cut-off and
during continuance of failure
up to 5th quarter cut-off
(e) Beyond this, it will
continue to attract a fine of
Rs. 10,000,00 per day till the
cure of default
3 Non-submission of quarterly reports on
following indices both to the
Commission as well as on its website:
3.a (a) Reliability Indices (Ref. Clause 7.14 of
Supply Code)
Failure to submit information
regarding the reliability index,
under clause 7.14, on time
shall attract a fine of Rs.
25,000.00 and Rs.
2,500.00.00 day in case of
continuing failure.
3.b (b) Billing Mistakes (Ref. Clause 7.17 of
Supply Code)
Failure to submit information
regarding the billing
mistakes, under clause 7.17,
on time shall attract a fine of
Rs 25,000.00 and Rs.
2,500.00.00 day in case of
continuing failure.
3.c (c) Faulty meters (Ref. Clause 7.18 of
Supply Code)
Failure to submit information
regarding the faulty meters,
under clause 7.18, on time
shall attract a fine of Rs.
25,000.00 and Rs. 2,500.00
day in case of continuing
failure.
Part C – Information Related to Tariff
1 Delay in submission of MYT petition /APR
petition/True Up petition beyond the
specified date.
A fine shall be levied at the
rate of Rs. 5000.00 day in the
first 30 days beyond the
specified date. After 30 days,
a fine of Rs. 1 lakh shall be
imposed in addition to a fine
at the rate of Rs. 10,000.00
day till the submission of
petition.
2 Delay in submission of Business Plan
beyond the specified date.
A fine shall be imposed of Rs.
1,00,000.00 if Business plan
is not submitted within 30
days of the specified date.
Further, if it is not submitted
within 60 days of the
specified date, a fine of Rs.
2,50,000.00 will be imposed
along with any other punitive
measure that the
Commission deems fit.
Part D – General Directions
Starred Directions* issued by Regulatory
Commission under Tariff Order /Supply
Code /Direction through any other order.
A penalty of Rs. 50,000.00
shall be imposed on the
licensee, if he fails to abide
by the starred direction by
the specified date in the
direction. Further, a penalty
of Rs. 5000.00 per day shall
be imposed during the period
of continuance of failure in
abiding the direction.
*(Henceforth the Commission shall issue all its general directions,
containing the date of implementation, under two heads viz starred
directions and un-starred directions. The decision of the Commission
regarding classification of its directions under starred & unstarred category
shall be final. The Commission, may also revisit its existing un-complied
directions and classify it under starred and un starred category.)
These regulations shall come into effect from the date of notification.
By the order of the Commission,
SANJAY SRIVASTAVA,
Secretary, UP. Electricity
Regulatory Commission,
Lucknow