Haryana Electricity Reform Act, 1997
Haryana Act
- Act 10 of 1998
- Enacted: 1998-02-20
- Ministry: NO MINISTRY
- Department: Haryana Vidyut Prasaran Nigam Limited
- Status: no repeal is recorded
The text of this Act is shown as one document.
Full text
75
THE HARYANA ELECTRICITY REFORM ACT, 1997
(HARYANA ACT NO. 10 OF 1998)
TABLE OF CONTENTS
Sections :
1. Short title, extent and commencement.
2. Definitions.
3. Establishment and Constitution of the Commission.
4. Constitution of the selection committee to select members.
5. Conditions for appointment as member of the Commission.
6. Term of office, conditions of service, etc. of members.
7. Removal of Members.
8. Appointment of the Secretary, Staff and consultants of the
Commission.
9. Proceedings of the Commission.
10. Powers of the Commission.
11. Functions of the Commission.
12. General Powers of the State Government.
13. Constitution and functions of the Transco.
14. Licensing.
15. Grant of licences by the Commission.
16. Exemptions from the requirement to have a licence.
17. General duties and powers of the licensees.
18. Revocation of licences.
19. Amendment of licences.
20. Provisions where licence is revoked.
21. Restrictions on licensees and Generating Companies.
22. Annual accounts of licensee.
23. Reorganisation of State Electricity Board.
24. Provisions relating to personnel.
25. Variation of transfers by Agreement.
26. Licensee’s revenues and tariffs.
27. Finances of licensees.
28. Interim orders for securing compliance.
29. Final Orders for securing compliance.
30. Effect and enforcement of interim and final orders and emergency
provision.
31. Fines and Charges.
ELECTRICITY REFORM1998 : Hr. Act 10]
76
31A. General control of the Commission.
32. Commission Advisory Committee.
33. Consumer Protection; Standards of Performance.
34. Electricity Supply; Overall Performance Standards.
35. Information with respect to levels of performance.
36. Restriction on disclosure of information.
37. Arbitration by the Commission.
38. Appeals from decisions of Electrical Inspector.
39. Appeals against the orders of the Commission.
40. Penalty for contravention of section 14.
41. Penalties for contravention of other provisions.
42. Offences by Companies.
43. Power to compound offences.
44. Cognizance of offences.
45. Penalties and proceedings not to prejudice other actions.
46. Recovery of Fees, Fines and Charges.
47. Application of fine and charges.
48. No part of the fines or penalties imposed to be passed on.
49. Protection of action taken in good faith.
50. Bar of Jurisdiction.
51. Power to remove difficulties.
52. Proceedings before the Commission to be judicial proceedings.
53. Members and staff of Commission to be public servants.
54. Power to make regulations.
55. Power to make rules.
56. Effect of the Act on the Indian Electricity Act, 1910 and the Electricity
(Supply) Act, 1948.
57. Savings.
SCHEDULE
I. Annual Financial Statement.
II. Accounts and Audit.
III. Remuneration, etc.
IV. Official Seal.
V. Performance of functions.
ELECTRICITY REFORM [1998 : Hr. Act 10
77
1THE HARYANA ELECTRICITY REFORM
ACT, 1997
(Haryana Act No. 10 of 1998)
[Received the assent of President of India on the 20th February, 1998, and
was first published for general information in the Haryana Government Gazette
(Extraordinary), Legislative Supplement Part I of the 10th March, 1998].
Year No. Short title Whether repealed or otherwise
affected by Legislation
1 2 3 4
1998 10 The Haryana Electricity —
Reform Act, 1997
AN
ACT
to provide for the constitution of an Electricity Regulatory Commission,
restructuring of the electricity industry, rationalization of the generation,
transmission, distribution and supply of electricity, avenues for participation
of private sector entrepreneurs in the electricity industry and generally for
taking measures conducive to the development and management of the
electricity industry in an efficient, economic and competitive manner
and for matters connected therewith or incidental thereto.
Be it enacted by the Legislature of the State of Haryana in the forty-eighth
Year of the Republic of India, as follows: -
PART-I
PRELIMINARY
1. (1) This Act may be called the Haryana Electricity Reform
Act, 1997.
(2) It extends to the whole of the State of Haryana.
2[(3) It shall come into force on such date as the State Government
shall notify in the Official Gazette.]
2. In this Act, unless the context otherwise requires,—
(a) “area of transmission” means the area within which the holder
or a transmission licence is for the time being authorised by
licence to transmit energy;
1 For Statement of Objects and Reasons, see Haryana Government Gazette (Extraordinary),
dated 21-7-1997, page-1665.
2. This Act came into force with effect from the 14th August, 1997 vide Haryana Government,
Power Department Notification No. SO-105/HA/10/1998/S.1998, dated the 13th August, 1998.
Short title, extent
and
commencement.
Definitions.
ELECTRICITY REFORM1998 : Hr. Act 10]
78
(b) “Commission” means the Haryana Electricity Regulatory
Commission constituted under sub-section (1) of section 3;
(c) “licence” means a licence granted under Part VI of this Act;
(d) “licensee” or “licence holder” means a person licensed under
part VI of this Act to transmit or supply energy including
Transco;
(e) “member or members” means the members of the Commission
and shall include the Chairman of the Commission;
(f) “prescribed” means prescribed by the rules or regulations made
under this Act;
(g) “Public Service Commission” means the Public Service
Commission for the State established pursuant to Article 315
of the Constitution of India;
(h) “regulations” means regulations made by the Commission under
the Act;
(i) “rules” means rules made by the State Government under this
Act;
(j) “selection committee” means the selection committee
constituted under section 4 of this Act;
(k) “State” means the State of Haryana;
(l) “State Government” means the Government of the State;
(m) “supply licence” means a licence under sub-section (1) (b) of
section 15;
(n) “transco” means the Transmission Corporation of Haryana
incorporated as a transmission company under the Companies
Act, 1956 for the purpose of undertaking transmission of
electricity under a licence granted under this Act;
(o) “transmission licence” means a licence under sub-section (1)
(a) of section 15;
(p) “transmit” in relation to electricity, means the transportation or
transmission of electricity by means of a system operated or
controlled by a licensee which consists, wholly or mainly, of
extra high voltage and extra high tension lines and electrical
plant and is used for transforming and for conveying and/or
transferring electricity from a generating station to a sub-station,
from one generating station to another or from one sub-station
to another or otherwise from one place to another;
ELECTRICITY REFORM [1998 : Hr. Act 10
79
(q) words and expressions used but not defined in this Act
and defined in the Electricity (Supply) Act, 1948 (Act No. 54
of 1948) have the meanings respectively assigned to them in
that Act;
(r) Words and expressions used but not defined either in this Act
or in the Electricity (Supply) Act, 1948 (Act No. 54 of 1948)
and defined in the Indian Electricity Act, 1910 (Act No.IX
of 1910), have the meanings respectively assigned to them in
these Acts.
PART II
HARYANA ELECTRICITY REGULATORY COMMISSION
3. (1) For the purposes of this Act, within three months of the Act
coming into force, the State Government shall establish by notification in the
Official Gazette a Commission to be known as the Haryana Electricity Regulatory
Commission, which shall be a body corporate with perpetual succession and a
common seal with power to acquire and hold property, movable and immovable,
and shall, by the said name, be entitled to sue and be sued.
(2) The Commission shall consist of three members to be appointed
by the State Government from persons selected by the selection committee
constituted for the purpose, in the manner provided in section 4 of this Act.
(3) The person to be appointed as a member of the Commission for
the first time for a period of three years in terms of proviso to sub-section (1) of
section 6 shall be the first Chairman of the Commission and thereafter at all times
the most senior member of the Commission shall act as Chairman, such seniority
being reckoned from the date of the appointment of the members. In case two or
more persons are selected at the same time the seniority amongst them shall be
determined by the State Government while making the appointment.
(4) When the Chairman of the Commission is unable to discharge
the functions owing to absence, illness or any other cause, the next senior member
of the Commission shall discharge the functions of the Chairman, until the day on
which the Chairman assumes the charge of his functions.
(5) No act or proceedings of the Commission shall be invalid by
reason only of the existence of any vacancy among its members or any defect in
the constitution thereof.
4. (1) The State Government shall expeditiously constitute a selection
committee, as often as may be required to select persons for appointment as
members.
(2) The selection committee shall consist of five members:—
(i) the Vice Chancellor of a Haryana University-Chairman.
Establishment and
Constitution of the
Commission.
Constitution of the
selection
committee to
select members.
ELECTRICITY REFORM1998 : Hr. Act 10]
80
(ii) a Member of the Haryana Public Service Commission
– Member.
(iii) the Chairman or a Member of Central Electricity Authority
– Member,
(iv) the Secretary in charge of Finance Department,
Government of Haryana – Member,
(v) the Secretary incharge of the Power Department,
Government of Haryana – Member.
The Secretary incharge of the Department of Power
Government of Haryana shall also act as the convenor of the
selection committee.
(3) The selection committee shall act expeditiously and shall
generally finalise the selection within a period of two months to enable the State
Government to make the final selection and appointment in time for the new
member to take effective charge at the expiry of the term of the retiring member.
(4) The selection committee shall select two suitable persons for
each vacancy in the Commission who have such qualification and experience as
provided in the Act and notify the State Government of the persons shortlisted by
the selection committee. The State Government shall appoint one of the two
candidates shortlisted by the selection committee as a member of the Commission.
(5) All decisions of the selection committee shall be by majority.
(6) The method and manner of the selection and appointment of
members and designation of one of the members as Chairman shall be as prescribed
by the State Government from time to time by the rules.
5. (1) The members of the Commission shall be persons of ability,
integrity and standing who have adequate knowledge or experience of, or have
shown capacity in dealing with problems relating to engineering, economics,
commerce, finance, accountancy, law or administration and further that at all
times—
(a) at least one member shall be an electrical engineer with
adequate experience of either generation, transmission or
distribution of electricity;
(b) at least one member shall have qualification and adequate
experience in any of the other disciplines, namely
economics, commerce, finance, accountancy, law or
administration; and
(c) the third member shall have the qualification and
adequate experience in any of the disciplines mentioned
above.
The selection and appointment of the members at all times shall be
made strictly in accordance with the above qualification and experience.
Conditions for
appointment as
member of the
Commission.
ELECTRICITY REFORM [1998 : Hr. Act 10
81
(2) A person shall be disqualified from being appointed a member
of the Commission if he is a member of Parliament or of any State Legislature or
any local authority or holds any post in a political party.
(3) The persons who are considered for appointment as members of
the Commission shall notify the convenor of the selection committee—
(a) of any office, employment or consultancy agreement or
arrangement which he has in his own name or in any firm,
association of person or body corporate; or in the names
of any relative, carrying on any of the following
businesses—
(i) generation, transmission, distribution or supply of
electricity;
(ii) manufacture, sale or supply of any fuel for generation
of electricity;
(iii) manufacture, sale, lease, hire or otherwise supply of
or dealing in machinery, plant, equipment, apparatus
or fittings for the generation, transmission,
distribution, supply or use of electricity; and
(iv) any entity providing professional services to any of
the businesses referred to in sub-clauses (i), (ii) and
(iii) above;
(b) such other details and information as may be prescribed
in the rules.
Explanation.—For the purpose of this section the term relative shall have
the same meaning as defined under section 6 of the Companies Act, 1956.
(4) The details received from the persons shall be placed for
consideration of the selection committee at the time of selection and
recommendation of the person for appointment as member.
(5) Each member of the Commission shall, before taking charge of
the office as member or within such time not exceeding three months after taking
charge as may be allowed by the State Government on the recommendation of the
selection committee, divest himself from the interest in the businesses mentioned
in sub-section (3) of this section as a condition of his appointment.
(6) If a person to be appointed as a member of the Commission
holds any office under the State or Central Government or any public sector
corporation or any Government body he shall submit his resignation or take
voluntary retirement from that service and shall not seek reappointment in the
service of the Government or any Government corporation or body dealing with
the power sector at any time after he ceases to be a member of the Commission.
ELECTRICITY REFORM1998 : Hr. Act 10]
82
(7) So long as the person holds the office of the member and for a
period of two years after he ceases to be a member for any reason whatsoever, he
shall not acquire, hold or maintain, directly or indirectly any office, employment
or consultancy arrangement or businesses mentioned in sub-section (3) of this
section and if he acquires any such interest involuntarily or by way of succession
or testamentary disposition he will divest himself from such interest within a period
of three months of such interest being acquired.
(8) Before recommending any person as a member of the
Commission, the selection committee shall satisfy itself that the person does not
have any financial or other interest as referred to in sub-section (3) or otherwise
which is likely to affect prejudicially his functions as a member.
6. (1) Every member shall hold office for a period of five years from
the date of his appointment as member or until the age of sixty-five years, whichever
is earlier and he shall not be eligible for re-appointment at any time after the
expiry of his term of appointment:
Provided that the first three members shall be appointed for varying
periods of three years, four years and five years respectively so as to avoid the
retirement of all the members at the same time and ensure continuity in the
functioning of the Commission:
Provided further that no person shall be appointed as member after
he has attained the age of sixty two years so that he has a minimum tenure of three
years as member.
(2) The Chairman of the Commission and other members shall
receive such remuneration and other allowances as provided in Schedule I and
shall be governed by such conditions of service as may be prescribed from time to
time under the rules:
Provided that the terms shall not be varied to their disadvantage during
the tenure of the appointment.
(3) The Chairman of the Commission and every other member shall
before entering upon his office, make and subscribe to an oath of office and of
secrecy in such form, in such manner and before such authority as may be
prescribed.
7. (1) The Governor of the State may remove from office any member
of the Commission, in accordance with sub-section (2) who—
(a) has been adjudged an insolvent; or
(b) has been convicted of an offence involving moral
turpitude; or
(c) has become physically or mentally incapable of acting as
such member; or
(d) has without reasonable cause refused or failed to act for a
period of at least six months; or
Term of office,
conditions of
service, etc., of
members.
Removal of
Members.
ELECTRICITY REFORM [1998 : Hr. Act 10
83
(e) ceases to fulfill any of the conditions of his appointment
as member; or
(f) has acquired such financial or other interest that can affect
prejudicially his functions as a member; or
(g) has conducted himself in a manner or has so abused
his position as to render his continuance in office
prejudicial to the public interest or to the objects and
purpose of the Act.
(2) Except where a member admits the charge, in writing, no
member of the Commission shall be removed from his office on the grounds
specified in clauses (c), (d) (e) (f) and (g) of sub-section (1) until a sitting judge of
the High Court of Punjab & Haryana, as recommended by the Chief Justice of the
High Court at the relevant time, has carried out an investigation and has forwarded
a report to the Governor of the State.
(3) The Governor and the State Government shall act in accordance
with the recommendation in the final report under sub-section (2) and the State
Government shall communicate its decision to the member concerned within a
period of two months of the receipt of such report.
(4) A member who has been removed shall not be eligible for re-
appointment as a member or in any other capacity in the Commission or in the
State Government or in any State Government undertakings.
(5) If the member removed under this section is the Chairman of
the Commission, he shall cease to be the Chairman of the Commission.
(6) The vacancy caused by the removal of the member shall be
filled in the same manner as provided for the appointment of a member or
designation of the Chairman of the Commission.
8. (1) The Commission shall appoint a person as Secretary of the
Commission to assist the Commission to discharge its functions.
(2) The Commission shall, in consultation with the State
Government, determine the number, nature and categories of other officers and
employees required to assist the Commission in the discharge of its functions.
(3) The salaries and allowances payable to the members and the
administrative expenses, including salaries, allowances and pensions payable to
or in respect of the Secretary, officers and other employees of the Commission,
shall be charged to the Consolidated Fund of the State.
(4) The method and manner of selection of the Secretary, officers
and other employees and the terms and conditions of their service may be
prescribed by the Commission by regulations.
(5) The Commission shall be entitled to appoint, from time to time,
consultants required to assist the Commission in the discharge of its functions on
terms and conditions to be decided by the Commission.
Appointment of
the Secretary, Staff
and Consultants of
the Commission.
ELECTRICITY REFORM1998 : Hr. Act 10]
84
PART III
PROCEEDINGS, POWERS AND FUNCTIONS OF THE COMMISSION
9. (1) The headquarters of the Commission shall be at Panchkula,
Haryana, but the Commission shall be entitled to conduct its proceedings,
consultations and hearings at any place in the State.
(2) The Commission shall have the exclusive power to frame
regulations for the conduct of its proceedings and discharge of its functions and
all such regulations framed shall be published in the Official Gazette.
(3) In case of a difference of opinion among the members of the
Commission, the opinion of the majority shall prevail and the opinion of the
Commission shall be expressed in terms of the views of the majority. Each member
of the Commission shall have one vote only. The Chairman shall have no casting
or second vote.
(4) The quorum for the meeting of the Commission shall be two;
provided that for a meeting of the Commission to review any previous decision
taken by the Commission or for consideration of any issue which could not be
decided on account of equality of votes in favour of and against the resolution
proposed, the quorum for the meeting shall be all members being personally present.
(5) The Chairman of the Commission may instruct the Secretary to
call a meeting of the Commission to be held at such time and at such place as the
Chairman may direct. In addition, any member of the Commission may request a
meeting of the Commission at any time by sending a notice in writing to the other
members and with a copy to the Secretary. The notice of all meetings shall be
given to the members in writing, unless all the members waive the notice in writing.
(6) The Commission shall be entitled to decide urgent matters by
circulation of the papers to members.
(7) All decisions, directions and orders of the Commission shall be
in writing and shall be supported by reasons. The decisions, directions and orders
of the Commission shall be available for inspection by any person and copies of
the same shall also be made available in a manner the Commission may prescribe.
10. (1) The Commission shall, for the purposes of any inquiry or
proceedings under this Act shall have the powers as are vested in a Civil Court
under the Code of Civil Procedure, 1908 (5 of 1908), while trying a suit in respect
of the following matters, namely:—
(a) the summoning and enforcing of attendance of any witness
and examining on oath;
(b) the discovery and production of any document or other
material object producible as evidence;
(c) the reception of evidence on affidavits;
Proceedings of the
Commission.
Powers of the
Commission.
ELECTRICITY REFORM [1998 : Hr. Act 10
85
(d) the requisition of any public record from any court or
office;
(e) the issue of commission for examination of witnesses;
(f) the appearance of parties and consequences of non-
appearance;
(g) the grant of adjournments at the hearing; and
(h) the review of its decisions, directions and orders.
(2) _________________ Deleted _______________.
(3) The Commission shall have the power to require any person—
(a) to produce before, and allowed to be examined and kept
by, an officer of the Commission specified in this behalf,
such books, accounts, or other documents in the custody
or under the control of the person so required as may be
specified or described in the requisition, being documents
relating to any matter concerning the generation,
transmission, distribution and supply or use of electricity,
the functioning of any undertaking involved in the above
areas and other matters, the examination of which the
Commission considers is necessary or relevant for the
purposes of this Act or the discharge of the functions by
the Commission under this Act; and
(b) to furnish to an officer so specified such information as
may be required for the purposes of this Act or such other
information as may be in his possession in relation to any
activity carried on by any other person.
(4) For the purpose of enforcing the attendance of witnesses the
local limits of the jurisdiction of the Commission shall be the limits of the territory
of India.
(5) Where, during any inquiry or proceedings under this Act, the
Commission has any grounds to believe that any books or papers or documents
of, or relating to any unit or person in relation to which such inquiry is being made
or which the owner of such unit may be required to produce in such inquiry, are
being, or may be, destroyed, mutilated, altered, falsified or secreted, it may, by a
written order authorise any officer of the Commission to exercise the powers of
entry, search and seizure as may be exercised by an Inspector appointed for
inspection under sections 240 and 240-A of the Companies Act, 1956 (1 of 1956).
(6) Notwithstanding anything contained in any other law for the
time being in force, the Commission may, by a general or special order, call upon
any person including the generating companies or the licensees to furnish to the
Commission periodically or as and when required any information concerning
ELECTRICITY REFORM1998 : Hr. Act 10]
86
the activities carried on by such person related to generation, transmission,
distribution and supply or use of electricity, the connection between such person
and any other person or undertaking including such other information relating to
the organisation, business, cost of production, conducts, etc. as may be prescribed
to enable the Commission to carry out its functions under this Act.
(7) In the discharge of its functions the Commission shall be entitled
to and shall consult to the extent the Commission considers appropriate from
time to time such persons or group who may be affected or are likely to be affected
by the decisions of the Commission.
(8) The Commission shall be entitled to exercise the above
mentioned powers to call for information, details, books, accounts and other
documents from any person and make inquiry for the purposes of providing the
same to the Central Electricity Authority, the Central Government, the State
Government or other persons. The Central Electricity Authority, the Central
Government and the State Government shall be entitled to ask the Commission to
make such inquiry and provide the information, details and documents to them.
(9) All persons to whom notices may be issued shall have a statutory
obligation under this Act to duly, faithfully and effectively furnish the information,
details, books, accounts and other documents, which the Commission considers
relevant in connection with its functions under this Act or which may be required
to be obtained at the directions of the Central Electricity Authority, the Central
Government or the State Government as the case may be and shall be proceeded
with and punishable for any failure or delay to comply with such requirements
and the directions and orders issued by the Commission.
(10) Notwithstanding anything contained in sections 12 to 16 (both
inclusive) and sections 18 and 19 of the Indian Electricity Act, 1910, for the placing
of the electric supply lines, appliances and apparatus for transmission, distribution
and supply of energy, the Commission may, by order in writing, confer upon
licensees or any other person engaged in the business of transmission, distribution
or supply of energy to the public under the Act, subject to such conditions and
restrictions as the Commission may provide, any of the powers which the telegraph
authority possess under the Indian Telegraph Act, 1885 with respect to placing of
telegraph lines and post.
11. (1) Subject to the provisions of this Act, the Commission shall be
responsible to discharge, amongst others, the following functions:—
(a) to aid and advise, in matters concerning electricity
generation, transmission, distribution and supply in the
State;
(b) to regulate the working of the licensees and to promote
their working in an efficient, economical and equitable
manner;
Functions of the
Commission.
ELECTRICITY REFORM [1998 : Hr. Act 10
87
(c) to issue licences in accordance with the provisions of this
Act and determine the conditions to be included in the
licences;
(d) to promote efficiency, economy and safety in the use of
the electricity in the State including and in particular in
regard to quality, continuity and reliability of service and
enable all reasonable demands for electricity to be met;
(e) to regulate the purchase, distribution, supply and
utilization of electricity, the quality of service, the tariff
and charges payable keeping in view both the interest of
the consumer as well as the consideration that the supply
and distribution cannot be maintained unless the charges
for the electricity supplied are adequately levied and duly
collected;
(f) to promote competitiveness and progressively involve
the participation of private sector, while ensuring fair deal
to the customers;
(g) to collect data and forecast on the demand for and use of
electricity and to require the licensees to collect such data
and forecast;
(h) to require licensees to formulate perspective plans and
schemes in coordination with others for the promotion of
generation, transmission, distribution and supply of
electricity;
(i) to set appropriate code of conduct and standards for the
electricity industry in the State;
(j) to regulate the assets, properties and interest in properties
concerning or related to the electricity industry in the
State; and
(k) to undertake all incidental or ancillary things.
(2) The Commission shall always act consistent with the objectives
and purposes for which the Commission has been established as an independent
statutory body corporate and all acts, decisions and orders of the Commission
shall be pursuant to and shall seek to achieve such object and purpose.
(3) Notwithstanding the provisions of section 52 of the Indian
Electricity Act, 1910 or the provisions of section 3 (1) (ii) and section 76 of the
Electricity (Supply) Act, 1948, the Commission shall have the power to act as
arbitrator or nominate arbitrator or arbitrators to adjudicate and settle the disputes
arising between the licenses in accordance with the regulations to be prescribed
and this shall be a condition of the grant of licences.
ELECTRICITY REFORM1998 : Hr. Act 10]
88
PART IV
POWERS OF THE STATE GOVERNMENT
12. (1) The State Government shall have the power to issue policy
directions on matters concerning electricity in the State including the overall
planning and coordination. All policy directions shall be issued by the State
Government consistent with the objects sought to be achieved by this Act and
accordingly shall not adversely affect or interfere with the functions and powers
of the Commission including but not limited to determination of the structure of
tariffs for supply of electricity to various classes of consumers.
(2) If any dispute arises between the Commission and the State
Government as to whether or not a question is a matter of policy or whether a
policy direction issued by the State Government adversely affects or interferes
with the exercise of the functions of the Commission, the same shall be referred to
the Central Electricity Authority and the decision given by the Central Electricity
Authority shall be final and binding. The Central Electricity Authority may appoint
one or more members of the Authority to act on behalf of the Authority in relation
to any matter referred to under this sub-section.
(3) The State Government shall be entitled to issue policy
directions concerning the subsidies to be allowed for supply of electricity to any
class or classes of persons in addition to the subsidies adjusted by the Commission
while regulating and approving the tariff structure provided that the State
Government shall contribute the amount to compensate such concerned body or
unit affected by the grant of the subsidies by the State Government to the extent
of the subsidies granted. The Commission shall determine the amounts and the
terms and conditions on which such amounts are to be paid by the State
Government.
(4) The State Government shall consult the Commission in relation
to any proposed legislation or rules concerning any policy direction and shall
duly take into account the recommendation by the Commission on all such matters.
PART V
TRANSCO
13. (1) Within sixty days of the Act coming into force, the State
Government shall cause Transco to be incorporated and organised under the
provisions of the Companies Act, 1956, as the Transmission Corporation of Haryana
Limited, with the principal objects of engaging in the business of procurement,
transmission and supply of electric energy.
(2) Subject to the powers of the State Government under section
12, the Transco established by the State Government in terms of sub-section (1)
shall be the principal company to undertake all planning and coordination in
regard to transmission, undertaking the works connected with transmission,
determining the electricity requirements in the State in coordination with the
Generating companies, State Government, the Commission, the Regional
Electricity Board and the Central Electricity Authority; the operation of the power
system.
General powers of
the State
Government.
Constitution and
functions of the
Transco.
ELECTRICITY REFORM [1998 : Hr. Act 10
89
(3) Transco shall own the extra high voltage transmission system,
shall be responsible for the transmission system operation and shall operate the
power system in an efficient manner.
(4) Transco shall undertake the functions specified in this section
and such other functions as may be assigned to it by the licence to be granted to it
by the Commission under this Act.
(5) Upon the grant of licence to the Transco under clause (a) of
sub-section (1) of section 15 of this Act, the Transco shall discharge such powers,
duties and functions of the Haryana State Electricity Board including those under
the Indian Electricity Act, 1910 and the Electricity (Supply) Act, 1948 or the
rules framed thereunder as the Commission may specify in the licence and it shall
be the statutory obligation of the Transco to undertake and duly discharge the
powers, duties and functions so assigned.
(6) Subject to sub-sections (1) and (2) and subject to the overall
supervision and control of the Transco, a number of subsidiary or associated
transmission companies may be established in the State and the Commission may
grant licences under the terms of this Act to such transmission companies, in
consultation with the Transco.
PART VI
LICENSING OF TRANSMISSION AND SUPPLY
14. (1) No person, other than those authorised to do so by licence or by
virtue of exemption under this Act or authorised to or exempted by any other
authority under the Electricity (Supply) Act, 1948, shall engage in the State in the
business of—
(a) transmitting electricity; or
(b) supplying electricity.
(2) Where any difference or dispute arises as to whether any person
is or is not engaged or about to engage in the business of transmitting or supplying
electricity as described in sub-section (1), the matter shall be referred to the
Commission and the decision of the Commission shall be final.
(3) The Commission shall have the power to order any unlicensed
person to cease operating and disconnect its apparatus.
(4) Notwithstanding anything contained in other provisions of this
Act and until the establishment of the Commission in terms of section 3, the State
Government shall for the period of six months from the date, this Act comes into
force have the power to grant provisional licences under this section having a
duration not exceeding six months to any person or persons to engage in the State
in the business of transmission for supply of electricity on such terms and conditions
Licensing.
ELECTRICITY REFORM1998 : Hr. Act 10]
90
as the State Government may determine consistent with the provision of this Act,
subject however, to the following conditions:—
(a) upon the establishment of the Commission, each of the
provisional licences granted by the State Government
shall be placed before the Commission and shall be deemed
to constitute an application for grant of a licence by the
Commission under the provisions of this Act; and
(b) each provisional licence granted under this section shall
cease to be valid and effective on the date on which the
Commission communicates the decision.
(5) The State Government shall be entitled to confer on the
provisional licensees under sub-section (4) such powers, rights and authorisation
as the Commission is entitled to grant to the licensees under this Act.
15. (1) The Commission may on an application made in such form and
on payment of such fee, if any, as it may prescribe, grant a licence authorizing any
person to—
(a) transmit electricity in a specified area of transmission;
and/or
(b) supply electricity in a specified area of supply.
(2) In respect of the grant of any such licence the following
provisions shall apply—
(a) any person applying for a licence shall publish a notice of
his application in such manner, and with such particulars
as may be prescribed by the Commission within 14 days
after making the application;
(b) the Commission shall not grant a licence until—
(i) all objections received relating to the application
for the licence have been considered by the
Commission; provided that no objection shall be
considered by the Commission unless it is received
within three months of the date of the first
publication of the notice under clause (a) above;
and
(ii) in the case of an application for a licence to supply
or transmit in an area which includes the whole or
any part of any cantonment, aerodrome, fortress,
arsenal, dockyard or camp or of any building or place
in the occupation of the Central Government for
defence purposes, the Commission has ascertained
that there is no objection to the grant of the licence
on the part of the Central Government;
Grant of licences
by the
Commission.
ELECTRICITY REFORM [1998 : Hr. Act 10
91
(c) where an objection is received from any local authority
concerned, the Commission shall, if in its opinion the
objection is insufficient, record in writing and
communicate to such local authority its reasons for such
opinion; and
(d) no application for a licence shall be made by any local
authority except pursuant to a resolution passed at a
meeting of such authority held after one month’s previous
notice of the same specifying the purpose thereof has been
given in the manner in which notices of meetings of such
local authority are usually given.
(3) A licence may prescribe the duration, extent to which, and the
terms and conditions under which the transmission or supply of energy is to be
made and contain such other conditions as the Commission may consider
appropriate for achieving the purposes of the Act.
(4) Without prejudice to the generality of sub-section (3), conditions
included in a licence by virtue of that sub-section may require the licensee to—
(a) enter into agreements on specified terms with other persons
for the use of any electric lines, electrical plant(s) and
associated equipment operated by the licensee;
(b) comply with any direction given by the Commission;
(c) act in accordance with the terms of the licence;
(d) refer all disputes arising under the licence for
determination by the Commission;
(e) furnish information, documents and details which the
Commission may require for its own purpose or for the
purposes of the Central or State Government or Central
Electricity Authority;
(f) comply with the requirements of the Indian Electricity
Act, 1910 and the Electricity (Supply) Act, 1948 or rules
framed thereunder in so far as they are applicable;
(g) undertake such functions and obligations of the Haryana
State Electricity Board under the Indian Electricity Act,
1910 and Electricity (Supply) Act, 1948 as the
Commission may prescribe;
(h) obtain the approval of the Commission of such things
that are required under the licence conditions or for
deviation from the same;
(i) notify the Commission of any scheme that he is proposing
to undertake including the schemes in terms of the
provisions of the Electricity (Supply) Act,1948;
ELECTRICITY REFORM1998 : Hr. Act 10]
92
(j) purchase of the power in an economical manner and under
a transparent power purchase procurement process; and
(k) supply in bulk to other licensees or to customers.
(5) Without prejudice to the generality of sub-section (3), conditions
included in a licence granted by the Commission may require the holder of such
a licence to establish a tariff or to calculate its charges from time to time in
accordance with the requirements prescribed by the Commission.
(6) The provisions contained in the Schedule to the Indian
Electricity Act, 1910 shall be deemed to be incorporated with, and to form part of,
every supply licence granted under this Part save in so far as they are expressly
varied or excepted by the supply licence and shall, subject to any such additions,
variations or exceptions which the Commission is empowered to make having
regard to the purposes of the Act, apply to the undertaking authorised by the
licence in relation to its activities in the State :
Provided that where a supply licence is granted by the
Commission for the supply of energy to other licensees for distribution by them,
then in so far as such licence relates to such supply, the provisions of clauses IV,
V, VI, VII, VIII and XII of the said Schedule shall not be deemed to be incorporated
within the supply licence.
(7) The conditions included in a licence may contain provision for
the conditions to cease to have effect or be modified at such times, in such manner
and in such circumstances as may be specified in or determined by or under the
conditions.
(8) Any provisions included by virtue of sub-section (7) above in
a licence shall have effect in addition to the provision made by sub-section (5) of
section 18 and section 19 with respect to the amendment of the conditions of a
licence.
(9) If so indicated in the terms of a licence, the grant of a licence
under this section to a person shall not in any way hinder or restrict the grant of a
licence to another person within the same area of supply for a like purpose, the
licensee shall not claim any exclusivity.
(10) The licence granted by the Commission in terms of this Act
may provide that the licensee shall have the powers and authorities to take
appropriate actions for revenue realization, prosecution for theft, meter tampering,
diversion of electricity, and all such and similar matters affecting the distribution
and supply of electricity to the consumer.
(11) The Commission shall be entitled to authorise the licensees
and persons to exercise such power and authority as the licensees and persons
could be given under the provisions of the Indian Electricity Act, 1910 and the
Electricity (Supply) Act, 1948.
ELECTRICITY REFORM [1998 : Hr. Act 10
93
16. (1) The Commission may make regulations to grant exemption
from the requirement to have a supply licence, but subject to compliance with
such conditions, if any, as may be specified in the order:
Provided that the Commission shall not, under any such regulation,
grant any exemption except with the consent—
(i) of the local authority, if any, constituted in the area where energy
is to be supplied;
(ii) in any case where energy is to be supplied in any area forming
part of any cantonment, aerodrome, fortress, arsenal, dockyard
or camp or any building or place in the occupation of the Central
Government for defence purposes, of the Central Government;
(iii) in any area falling within the area of supply of a licensee, of
that licensee:
Provided that, except in a case falling under sub-clause (ii) no such
consent shall be necessary if the Commission is satisfied that such consent has
been unreasonably withheld.
(2) An exemption may be granted—
(a) to persons of a particular category; or
(b) to a particular person; or
(c) for a particular period
and an exemption to persons of a particular category or to a particular person shall
be published in such manner as the Commission considers appropriate for bringing
it to the attention of that person or persons of that category and of the public in
general.
(3) The exemption granted may be revoked by the Commission at
any time for reasons to be recorded in writing.
(4) An exemption, unless previously revoked, shall continue in
force for such period as may be specified in or determined by or under the exemption.
(5) Every regulation or exemption made by the Commission under
this Act shall be published in the Official Gazette.
17. (1) It shall be the duty of the holder of a supply licence or a
transmission licence in respect of a particular area to develop and maintain an
efficient, coordinated and economical system of electricity supply or transmission
in the area of transmission or area of supply, as the case may be.
(2) Each licensee and Generating Company in discharge of its
duties shall comply with the provisions of the regulations framed from time to
time governing the terms and conditions for the operation and maintenance of
power system and electric supply lines.
Exemptions from
the requirement to
have a licence.
General Duties and
Powers of the
licensees.
ELECTRICITY REFORM1998 : Hr. Act 10]
94
(3) Subject to sub-section (4), sections 12 to 19 of the Indian
Electricity Act, 1910 (which relate to the carrying out of Works) shall have effect
in relation to a person authorised by a licence under this Act to transmit or supply
electricity, as if he is a licensee in that Act.
(4) Where any of the sections mentioned in sub-section (3) above
is applied to a licence holder by his licence, it shall have effect subject to such
restrictions, exceptions and conditions as may be included in the licence.
18. (1) The Commission may inquire into the conduct or functioning
or any licensee in carrying out the obligations under the Act or rules or regulations
framed thereunder or the terms and conditions of its licence—
(a) upon receiving a complaint from any consumer or
consumer association or any trade association; or
(b) upon a reference made to it by the State Government or
by the Central Government or the Central Electricity
Authority; or
(c) upon receiving a complaint from any company or person
involved in the generation, transmission, distribution or
supply; or
(d) upon its own knowledge or information derived from any
source.
(2) Upon making such inquiry the Commission may, if in its opinion
the public interest so requires, revoke a licence in any of the following cases,
namely—
(a) where the licensee, in the opinion of the Commission, has
committed a willful or unreasonable default in doing
anything required of him by or under this Act, the Indian
Electricity Act, 1910, or the Electricity (Supply) Act, 1948,
or rules made thereunder to the extent applicable in the
State, read with the provisions of this Act;
(b) where the licensee commits a breach of any of the terms
and conditions of his licence the breach of which is
expressly declared by such licence to render it liable to
revocation;
(c) where the licensee fails within the period specified in his
licence or any longer period which the Commission may
allow by order—
(i) to show, to the satisfaction of the Commission, that
he is in a position to fully and efficiently discharge
the duties and obligations imposed on him by his
licence; and
Revocation of
licences.
ELECTRICITY REFORM [1998 : Hr. Act 10
95
(ii) to make the deposit or furnish the security required
by his licence; and
(d) where in the opinion of the Commission the financial
position of the licensee is such that he is unable to fully
and efficiently discharge the duties and obligations
imposed on him by his licence.
(3) Notwithstanding the provisions of sub-section (1) and (2) where
in its opinion the public interest so requires, the Commission may, on the application
or with the consent of the licensee, and if the licensee is not a local authority, after
consulting the local authority concerned, if any, revoke a supply licence as to
the whole or any part of the area of supply upon such terms and conditions as it
think fit.
(4) No licence shall be revoked under sub-section (2) or (3) unless
the Commission has given to the licensee not less than three months’ notice in
writing, stating the grounds on which it is proposed to revoke the licence and has
considered any cause shown by the licensee within the period of that notice, against
the proposed revocation and has given reasons for such revocation.
(5) The Commission may, instead of revoking the licence, permit
it to remain in force subject to such further terms and conditions as it thinks fit to
impose and any further terms or conditions so imposed shall be binding upon, and
be observed by, the licensee, and be of like force and effect as if they were contained
in the licence.
19. (1) The Commission may, where in its opinion the public interest
so permits or requires, on the application of the licensee if the licensee is not a
local authority, on the application of the local authority concerned or otherwise
on its own may make such alterations and amendments to the terms and conditions
of a licence as it thinks fit taking into account the object and purposes of the Act:
Provided that no such alterations or amendments, other than an
alteration or amendment pursuant to a licence condition referred to in sub-section
(7) of section 15 or sub-section (5) of section 18 shall be made except with the
consent of the licensee.
(2) Where the licensee has made an application under sub-
section (1) proposing any alterations or amendments in his licence, the following
provisions shall apply—
(a) the licensee shall publish a notice of the application in
the manner and with the particulars as may be prescribed
by the Commission;
(b) the Commission shall not make any alterations or
amendments until all objections received by it with
reference to the application within three months from the
date of the first publication of the notice have been
considered; and
Amendment of
licences.
ELECTRICITY REFORM1998 : Hr. Act 10]
96
(c) in the case of an application proposing alterations or
amendments in an area of supply comprising the whole or
any part of the cantonment, aerodrome, fortress, arsenal,
dockyard or camp or of any building or place in the
occupation of the Central Government for defence
purposes, the Commission shall not make any alterations
or amendments except with the consent of the Central
Government.
(3) Before making any alterations or amendments in a licence
otherwise than on the application of the licensee, the Commission shall publish
the proposed alterations or amendments and consider all objections received by it
with reference to the proposed alterations or amendments within three months
from the date of the first publication of the notice.
20. (1) Notwithstanding the provisions of sections 6 and 7 of the Indian
Electricity Act, 1910, where the Commission revokes a licence, under sub-section
(2) of section 18 the following provisions shall apply:—
(a) the Commission shall serve a notice of revocation upon
the licensee and shall fix a date on which the revocation
shall take effect. On and with effect from that date, or on
and with effect from the date, if earlier, on which the
undertaking of the licensee is sold to a purchaser in
pursuance of any of the provisions of this Act all the rights,
duties, obligations and liabilities of the licensee under this
Act shall absolutely cease and determine except for any
liabilities that have accrued to that date;
(b) the Commission shall invite applications for acquiring
the undertaking of the licensee whose licence has been
revoked and determine terms and conditions of the sale of
the undertaking;
(c) the Commission may, by notice in writing, require the
licensee to sell, and thereupon the licensee shall sell the
undertaking to the person whose application has been
accepted by the Commission. Such person is referred to
in this section as the “purchaser”; and
(d) the Commission may make such interim arrangement in
regard to the undertaking of the licensee for maintaining
the electricity transmission and supply as may be
considered appropriate including the appointment of
administrators and special directors for the undertaking.
(2) Where an undertaking is sold under sub-section (1), the
purchaser shall pay to the licensee the purchase price of the undertaking determined
in accordance with the application submitted by the purchaser.
Provisions where
Licence is
Revoked.
ELECTRICITY REFORM [1998 : Hr. Act 10
97
(3) Where the Commission issues any notice under sub-section (1)
requiring the licensee to sell the undertaking, it may by such notice require the
licensee to deliver, and thereupon the licensee shall deliver on a date specified in
the notice, the undertaking to the designated purchaser pending the payment of
the purchase price of the undertaking :
Provided that in any such case, the purchaser shall pay to the
licensee interest at such percent exceeding the Reserve Bank lending rate ruling
at the time of delivery of the undertaking as the Commission may decide, on the
purchase price of the undertaking for the period from the date of delivery of the
undertaking to the date of payment of the purchase price.
(4) Where before the date fixed in the notice issued under sub-
clause (a) of sub-section (1) as the date on which the revocation of the licence
shall take effect, no notice has been issued to the licensee requiring him to sell the
undertaking or where for any reason no sale of the undertaking has been effected
under that sub-section, the State Government shall acquire the undertaking on
the date of revocation of the licence and shall pay to the licensee an amount
determined in accordance with sub-section (1) and (2) of section 7-A of the Indian
Electricity Act, 1910, as amended in the State and shall perform all the obligations
of the licensee until such time as the State Government is able to sell the
undertaking to a new licensee, which it shall endeavour to do when reasonably
practicable.
(5) The licensee shall duly implement the orders of the Commission,
notwithstanding that the licensee may be aggrieved by the orders of the Commission
and intends to take legal action challenging the orders of the Commission.
21. (1) No licensee or Generating Company shall, at any time, without
the previous consent in writing of the Commission, acquire by purchase or
otherwise the licence or the undertaking of, or associate himself with, so far as the
business of generating, transmitting, distribution or supply of energy is concerned,
any other licensee or person generating, transmitting, supplying or intending to
generate, transmit or supply electricity:
Provided that, before applying for such consent, the licensee
shall give not less than one month’s notice of the application-
(a) to the Commission; and
(b) if the licensee holds a supply licence, to every local
authority both in the licensee’s area of supply and also in
the area, if any, in which such other person supplies, or
intends to supply energy.
(2) The licensee shall not, at any time, assign his licence or transfer
his undertaking, or any part thereof, by sale, mortgage, lease, exchange or
otherwise without the previous consent in writing of the Commission.
(3) The provisions of section 44 of the Electricity (Supply) Act,
1948 shall apply except that the persons to whom the section applies shall be
Restrictions on
licensees and
Generating
Companies.
ELECTRICITY REFORM1998 : Hr. Act 10]
98
required to obtain the sanctions and consents from the Commission, instead of
such sanctions and consents to be obtained from the Board as provided under that
section.
(4) A holder of a supply or transmission licence may, unless
expressly prohibited by the terms of its licence, enter into arrangements for the
purchase of electricity from—
(a) the holder of a supply licence which permits the holder of
such licence to supply energy to other licensees for
distribution by them; and
(b) any person or Generating Company with the consent of
the Commission.
(5) Any agreement relating to any transaction of the nature
described in sub-sections (1), (2) (3) or (4) unless made with, or subject to such
consent as aforesaid, shall be void.
22. Every licensee shall, unless expressly exempted by the licence,
prepare and render to the Commission, or before the date in each year specified in
the licence, an annual statement or statements of accounts of its undertaking and
of each separate business unit as specified in the licence made up to such date, in
such form and containing such particulars, as may be set out in the licence. It shall
be a term of the licence that such statements shall be published.
PART VII
REORGANISATON OF THE ELECTRICITY INDUSTRY
23. (1) On and with effect from the date on which a transfer scheme
prepared by the State Government to give effect to the object and purposes of this
Act is published or such further date as may be prescribed by the State Government,
(hereinafter referred to as the effective date), any property, interest in property,
rights and liabilities which immediately before the effective date belong to the
Board shall vest in the State Government on such terms as may be agreed between
the State Government and the Board.
(2) Any property, interest in property, rights and liabilities vested
in the State Government under sub-section (1) shall be revested by the State
Government in the Transco and generating company(ies) in accordance with the
transfer scheme so published alongwith such other property, interest in property,
rights and liabilities of State Government as may be specified in such scheme, on
such terms and conditions as may be agreed between the State Government and
the Transco or generating company(ies), as the case may be. The State Government
would consult the major lenders while finalizing the transfer scheme. The State
Government would continue to guarantee all the liabilities transferred to the
successor companies.
Explanation: For the purposes of this chapter generating company(ies)
shall mean the company or companies to be incorporated by the State Government
to implement the reorganisation of the Electricity Industry in the State.
Annual Accounts
of licensee.
Reorganisation of
State Electricity
Board.
ELECTRICITY REFORM [1998 : Hr. Act 10
99
(3) Such of the rights and power exercisable by the Board under
the Electricity Supply Act, 1948 as the State Government may, by notification,
specify shall be exercisable by the Transco or generating company(ies), as the
case may be, for the purpose of discharging the functions and duties with which it
is charged.
(4) Notwithstanding anything in this section, where
(a) the transfer scheme involves the transfer of any property
or rights to any person or undertaking not wholly owned
by the State Government, the scheme shall give effect to
the transfer only for fair value to be paid by the transferee
to the State Government.
(b) a transaction of any description is effected in pursuance
of a transfer scheme, it shall be binding on all persons
including third parties, even if such persons third parties
have not consented to it.
(5) The State Government may, after consulting the Transco (the
“transferor licensee”), or generating company(ies), as the case may be, require
them to draw up a transfer scheme to vest in a further licensee (the “transferee
licensee”) or any generating companies, any property, interest in property, rights
and liabilities which have been vested in the transferor licensee or generating
companies, as the case may be, under this section.
(6) A transfer scheme may:—
(a) define the property, interest in property, rights and
liabilities to be allocated:—
(i) by specifying or describing the property, rights and
liabilities in question;
(ii) by referring to all the property, interest in property,
rights and liabilities comprised in a specified part of
the transferor’s undertaking; or
(iii) partly in the one way and partly in the other;
(iv) provide that in case of transfer scheme made for
distribution of the property, interest in property,
rights and liabilities could be allocated either to a
wholly State owned undertaking or a Joint Venture
Company.
(b) provide that any rights or liabilities specified or described
in the scheme shall be enforceable by or against the
transferor or the transferee;
(c) impose on any licensee an obligation to enter into such
written agreements with, or execute such other instruments
ELECTRICITY REFORM1998 : Hr. Act 10]
100
in favour of, any other subsequent licensee as may be
specified in the scheme; and
(d) make such supplemental, incidental and consequential
provisions as the transferor licensee considers appropriate
including provision specifying the order in which any
transfer or transaction is to be regarded as taking effect.
(7) All debts and obligations incurred, all contracts entered into
and all matters and things engaged to be done by, with or for the Board, or the
Transco or generating company(ies) before a transfer scheme becomes effective
shall, to the extent specified in the relevant transfer scheme be deemed to have
been incurred, entered into or done by with or for the State Government or the
transferee and all suits or other legal proceedings instituted by or against the Board
or transferor, as the case may be, may be continued or instituted by or against the
State Government or concerned transferee, as the case may be.
(8) In the event that a licensee is required to vest any part of its
undertaking in another licensee pursuant to sub-section (5), the Commission
shall amend the transferee licensee’s in accordance with section 19 or revoke its
licence in accordance with section 18.
(9) The Board shall cease to be charged with, and shall not perform,
the functions and duties specified in sub-section (3) with regard to transfers made
on and after the effective date.
(10) The exercise by a licensee of any of the Board’s rights and
powers may be made on such conditions as shall be specified in the transfer scheme
including a condition that they shall be exercised by the licensee only with the
approval of the Commission.
24. (1) The State Government may by a transfer scheme provide for the
transfer of the personnel to Transco, generating company(ies) and distribution
companies; on the vesting of properties, rights and liabilities in the Transco or
generating company(ies) under section 23.
(2) Upon such transfer scheme the personnel, shall hold office or
service under Transco or generating company(ies), as the case may be, on terms
and conditions that may be determined in accordance with the transfer scheme:
Provided that such terms and conditions on the transfer shall
not in any way be less favourable than these which would have been applicable to
them if there had been no such vesting.
(3) Notwithstanding anything contained in the Industrial Disputes
Act, 1947 or any other law as is applicable, and except for the provisions made in
this Act, the transfer of the employment of the personnel referred to in sub-section
(1) shall not entitle such employees to any compensation or damages under this
Act, or any other Central or State law or under the general law, save as provided in
the transfer scheme.
Provisions relating
to Personnel.
ELECTRICITY REFORM [1998 : Hr. Act 10
101
Explanation:-For the purposes of this section as well as the transfer scheme
the term “personnel” shall mean all persons who on the effective date are the
employees of the Board or the employees of the State Government on deputation
or assignment to the Board and other persons assigned for the electricity generation,
transmission, distribution and supply related work as may be notified by the State
Government as forming part of the personnel under this section notwithstanding
that they have been employed by other departments and organisations.
25. (1) The State Government may provide that the transfers in terms
of section 23 and 24 shall be provisional for a period of sixty months from the
effective date and reserve the right to alter, vary, modify, add or otherwise change
the terms in such manner as the State Government may consider appropriate.
(2) At any time before the end of the period of sixty months
commencing on the effective date, the Transco or generating company(ies) to
whom property, interests in property, rights, liabilities and personnel have been
transferred, may with the consent of the State Government, draw up a transfer
scheme to vest some or all of the property, rights, liabilities and personnel in
another licensee, or generating companies subject to the consents of such other
licensee of generating companies to such vesting and any such transfer scheme
shall take effect as if it were a transfer scheme under section 23 and 24.
PART VIII
TARIFFS
26. (1) The holder of each licence granted under this Act shall observe
the methodologies and procedures specified by the Commission from time to
time in calculating the expected revenue from charges which it is permitted to
recover pursuant to the terms of its licence and in designing tariffs to collect those
revenues.
(2) The Commission shall (subject to the provisions of sub-section
(3)) be entitled to prescribe the terms and conditions for the determination of the
licensees revenue and tariffs by regulations duly published in the Official Gazette
and in such other manner as the Commission considers appropriate provided that
in doing so the Commission shall be bound by the following parameters:—
(a) the financial principles and their applications provided
in the Sixth Schedule to the Electricity (Supply) Act, 1948
read with sections 57 and 57-A of the said Act;
(b) the factors which would encourage efficiency, economic
use of the resources, good performance, optimum
investments and other matters which the Commission
considers appropriate keeping in view the salient object
and purposes of the provisions of this Act; and
(c) the interest of the consumer including that the consumers
are not exploited because of any monopolistic or scarcity
Variation of
Transfers by
Agreement.
Licensee’s
Revenues and
Tariffs.
ELECTRICITY REFORM1998 : Hr. Act 10]
102
situation and at the same time the consumers pay for the
use of the electricity in a reasonable manner to maintain
the electricity generation, transmission, distribution and
supply on commercial principles.
(3) Where the Commission, departs from factors specified in the
Sixth Schedule of the Electricity (Supply) Act, 1948 while determining the
licensees’ revenues and tariffs it shall record the reasons thereof in writing.
(4) Any methodology or procedure specified by the Commission
under sub-section (1), (2) and (3) above shall be to ensure that the objects and
purposes of the Act are duly achieved.
(5) Every licensee shall provide to the Commission at least 3 months
before the ensuing financial year full details of its calculation for that financial
year of the expected aggregate revenue from charges which it believes it is permitted
to recover pursuant to the terms of its licence and thereafter it shall furnish such
further information as the Commission may reasonably require to assess the
licensee’s calculation. Within 90 days of the date on which the licensee has
furnished all the information that the Commission requires, the Commission shall
notify the licensee either:—
(a) that it accepts the licensee’s calculation; or
(b) that it does not consider the licensee’s calculation to be in
accordance with the methodology or procedure in its
licence, and such notice to the licensee shall:—
(i) specify fully the reasons why the Commission
considers that the licensee’s calculation does not
comply with the methodology or procedures
specified in its licence or is in any way incorrect;
and
(ii) propose a modification or an alternative calculation
of the expected revenue from charges, which the
licensee shall accept.
(6) Each holder of a supply licence shall publish in the daily
newspaper having circulation in the area of supply and make available to the
public on request the tariff or tariffs for the supply of electricity within its licensed
area and such tariff or tariffs shall take effect only after seven days from the date of
such publication. Any tariff implemented under this section—
(a) shall not show undue preference to any consumer of
electricity, but may differentiate according to the
consumer’s load factor or power factor, the consumer’s
total consumption of energy during any specified period,
or the time at which supply is required;
(b) shall be just and reasonable and be such as to promote
economic efficiency in the supply and consumption of
electricity; and
ELECTRICITY REFORM [1998 : Hr. Act 10
103
(c) shall satisfy all other relevant provisions of this Act and
the conditions of the relevant licence.
(7) No tariff or part of any tariff required by sub-section (6) may be
amended more frequently than once in any financial year except in respect of any
changes expressly permitted under the terms of any fuel surcharge formula
prescribed. At least three months before the proposed date for implementation of
any tariff or an amendment to a tariff the licensee shall provide details of the
proposed tariff or amendment to a tariff to the Commission, together with such
further information as the Commission may require to determine whether the tariff
or amended tariff would satisfy the provisions of sub-section (6). If the Commission
considers that the proposed tariff or amended tariff of a licensee does not satisfy
any of the provisions of sub-section (6), it shall, within 60 days for receipt of all
the information which it required, and after consultation with the Commission
Advisory Committee and the licensee, notify the licensee that the proposed tariff
or amended tariff is unacceptable to the Commission and it shall provide to the
licensee an alternative tariff or amended tariff which shall be implemented by the
licensee. The licensee shall not amend any tariff unless the amendment has been
approved by the Commission.
(8) Notwithstanding anything contained in sections 57-A and
57-B of the Electricity (Supply) Act, 1948, no Rating Committee shall be
constituted after the date of this enactment and the Commission shall secure that
licensees comply with the provisions of their licences regarding their charges for
the sale of electricity (both wholesale and retail) and for the connection to and use
of their assets or systems in accordance with the provisions of this Act.
(9) In this section:–
(a) “the expected revenue from charges” means the total
revenue which a licensee is expected to recover from
charges for the level of forecast supply used in the
determination under sub-section (5) above in any financial
year in respect of goods or services supplied to customers
pursuant to a licensed activity; and
(b) “tariff” means a schedule of standard prices or charges for
specified services which are applicable to all such
specified services provided to the type or types of
customers specified in the tariff.
27. (1) The State Government may, with the approval of the State
Legislature, from time to time make subventions to any licensee for the purpose
of this Act or the Electricity (Supply) Act, 1948 for such amounts as may be
recommended by the Commission and on such terms and conditions as the State
Government may determine.
(2) The State Government may from time to time advance loans to
any licensee or Generating Company which for the time being is wholly or partly
Finances of
licensees.
ELECTRICITY REFORM1998 : Hr. Act 10]
104
owned by the State Government on such terms and conditions, not inconsistent
with the provisions of this Act or the Electricity (Supply) Act, 1948, as the State
Government may determine.
(3) The State Government may guarantee in such manner as it thinks
fit the repayment of the principal or the payment of interest (or both) on any loan
proposed to be raised by any licensee or Generating Company which is for the
time being wholly or partly owned by the State Government or the discharge of
any other financial obligation of any licensee or Generating Company:
Provided that the State Government shall, so long as such guarantees
are in force, lay before the State Legislature during the budget session in every
year a statement of the guarantees, if any, given during the current financial year
of the State and an up-to-date account of the total sums, if any, which have been
paid out of State revenues in each case by reason of any such guarantees or paid
into State revenues towards repayment of any money so paid out.
PART IX
COMMISSION’S POWER TO PASS ORDERS
AND ENFORCE DECISIONS
28. (1) Where the Commission is satisfied that a licensee is
contravening, or is likely to contravene any relevant condition or requirement, it
shall by final order under section 29 and, if it thinks it appropriate in accordance
with sub-section (2) by interim order under this section, issue such directions as it
deems proper for securing compliance.
(2) In determining whether it is appropriate that an interim order
be made, the Commission shall have regard, in particular to—
(a) the extent to which the contravention or likely
contravention by the licensee will affect the achievement
of the objects and purposes of this Act;
(b) the extent to which any person is likely to sustain loss or
damage in consequence of anything which, is likely to be
done, or omitted to be done, in contravention of the
relevant condition or requirement, before a final order
can be made; and
(c) the extent to which (having regard to the following
provisions of this section) there is any other available
remedy in respect of the alleged contravention of a relevant
condition or requirement.
(3) If the Commission proposes to make an interim order, it shall
give notice to the licensee—
(a) stating that it proposes to make the order;
Interim Orders for
Securing
Compliance.
ELECTRICITY REFORM [1998 : Hr. Act 10
105
(b) setting out:—
(i) the relevant conditions or requirement which the
proposed order is intended to secure compliance;
(ii) the acts or omissions which, in its opinion constitute
contravention of that condition or requirement;
(iii) the other facts which in its opinion, justify the making
of the proposed order; and
(iv) the effects of the proposed order.
(c) specifying the period (being not less than 5 days from the
date of notice) within which the licensee may make representations or objections
to the proposed order.
(4) Subject to sub-section (5), having considered any representations
or objections from the licensee pursuant to sub-section (3) (c), the Commission
may make an interim order (which may be modified from the proposed order
following the licensee’s representations or objections) at any time after expiry of
the period referred to in sub-section (3) (c), if—
(a) the Commission has good reason to believe that the
licensee to whom the order relates has contravened or is
contravening or is likely to contravene any relevant
condition or requirement; and
(b) the provisions made by the order are requisite for the
purpose of securing compliance with that condition or
requirement.
(5) The Commission may not make an interim order if it is satisfied
that the licensee has agreed to take and is taking all such steps as the Commission
considers that the licensee should take to secure or facilitate compliance with the
condition or requirement in question.
(6) An interim order—
(a) shall require the licensee to whom it relates (according to
the circumstances of the case) to do, or not to do, such
things as are specified in the order or are of a description
so specified;
(b) shall take effect from such time, being the earliest
practicable time, as is determined by the order; and
(c) may be revoked, modified or rescinded at any time by the
Commission, but in any event shall cease to have effect at
the end of such period as is stated in the order unless the
Commission is at that time following the procedure set
out in section 29 to declare the interim order to be a
final order.
ELECTRICITY REFORM1998 : Hr. Act 10]
106
(7) As soon as practicable after making an interim order, the
Commission shall—
(a) serve a copy of the order on the licensee to whom the
order relates;
(b) publish the order in such manner as it considers appropriate
for the purpose of bringing it to the attention of persons
likely to be affected by it; and
(c) commence proceedings to declare the interim orders to
be a final order in accordance with section 29.
29. (1) If the Commission proposes to make a final order or to declare
an interim order to be a final order, the Commission shall give notice—
(a) stating that it proposes to make the final order or to declare
the interim order to be a final order;
(b) setting out the information referred to in sub
section (3) (b) of section 28 in respect of the proposed
final order; and
(c) specifying the period (being not less than 60 days from
the date of publication of the notice) within which
representations or objections to the proposed order may
be made;and shall consider any representations or
objections that are duly made and not withdrawn. The
Commission shall publish notice of such representations
or objections and specify a period (being not less than 30
days from the date of publication of the notice) within
which further representations or objections may be made.
(2) A notice under sub-section (1) above shall be given—
(a) by publishing the notice in such manner as the Commission
considers appropriate for the purpose of bringing the
matters to which the notice relates to the attention of
persons likely to be affected by them; and
(b) by serving a copy of the notice, and a copy of the proposed
final order on the licensee to whom the order relates.
(3) The Commission shall not modify the proposed final order as a
result of any representations or objections received following publications of the
notice referred to in sub-section (1), except—
(a) with the consent to the modification of the licensee to
whom the proposed final order relates; and
(b) after complying with the requirements of sub-section (4)
below.
Final Orders for
Securing
Compliance.
ELECTRICITY REFORM [1998 : Hr. Act 10
107
(4) The requirements mentioned in sub-section (3) above are that
the Commission shall:—
(a) serve on the licensee to whom the proposed final order
relates such notice as appears to the Commission requisite
of its proposal to modify the proposed final order, together
with details of such modifications;
(b) in that notice specify the period (being not less than 30
days from the date of the service of the notice) within
which representations or objections to the proposed
modifications can be made; and
(c) consider any representations or objections which are duly
made and not withdrawn within 10 days.
(5) The provisions of clauses (a) and (b) of sub-section (6) of section
28 shall apply to final orders.
(6) As soon as practicable after making a final order, the
Commission shall with respect to the final order, follow the procedure set out in
clauses (a) and (b) of sub-section (7) of section 28.
(7) The Commission may revoke a final order at any time, but
before revoking a final order the Commission shall give notice:—
(a) stating that it proposes to revoke the order and setting out
its effect; and
(b) specifying the period (being not less than 30 days from
the date of delivery of the notice) within which
representations or objections to the proposed publication
may be made, and shall consider any representations or
objections which are duly made and not withdrawn within
10 days.
(8) If, after giving a notice under sub-section (7) above, the
Commission decides not to revoke the final order to which the notice relates, it
shall give notice of its decision to the concerned persons.
(9) A notice under sub-section (7) or (8) above shall be given by
the procedure set out in clauses (a) and (b) of sub-section (7) of section 28.
30. (1) Without prejudice to section 46 of this Act, all orders and
directions, interim or final, passed by the Commission shall be enforceable in law
as if it is a decree passed by a Civil Court.
(2) The Commission shall be entitled to take such assistance of the
police and other authorities in the State required to effectively enforce the orders
and directions given by the Commission.
Effect and
enforcement of
Interim and Final
Orders and
Emergency
Provision.
ELECTRICITY REFORM1998 : Hr. Act 10]
108
(3) The Commission shall be entitled to give directions for vesting
of the management and control of any of the undertaking of the licensee with the
assets, interests and rights of the undertaking pending any inquiry and passing of
interim or final orders in the matter, if the Commission considers, taking into
account the object and purposes of this Act and the need to maintain continued
supply of electricity in an efficient and safe manner to the consumer, it is imminent
to pass such orders or directions. Such directions or orders shall not be questioned
on the ground that no prior notice of or hearing on the intention to pass the order
or direction was given to the licensee. The Commission shall however give
opportunity to the licensee and hear the licensee before passing further orders in
terms of sections 28 and 29 of this Act.
31. (1) The Commission shall be entitled to impose such fines and
charges as may be prescribed by the Commission in the regulations for non
compliance or violation on the part of the Generating Companies, licensees or
other persons, of the provisions or requirements of this Act or rules and regulations
framed thereunder and directions or orders of the Commission made from time to
time. The fines which the Commission shall be entitled to impose may extend up
to Rs. 1,00,000 (one lakh) for an act of non compliance or violations and a further
amount not exceeding Rs. 6,000 (six thousand) for every day during which the
non-compliance or violation continues.
(2) The Commission shall, while making an interim or final orders
under this Part, shall be entitled to direct compensation to be paid by the person
guilty of violation or non compliance as provided in sub-section (1) to the person
or persons affected by such violation or non compliance.
(3) The fines, charges and compensation which may be imposed
by the Commission under this section shall be in addition to and not in derogation
of any other liability, which the person guilty of violation or non compliance,
may have incurred.
31A. (1) The generating companies shall comply with the provisions of
the regulations framed by the Commission from time to time governing the terms
and conditions for the operation and maintenance of the power system and electric
supply lines.
(2) After the Act comes into force all assets, properties, interests
in property and other facilities forming part of or used in connection with
the electricity industry in the State of Haryana, established in the State whether
before or after the commencement of the Act, shall be deemed to be special
properties and the same shall be subject to the regulations to be framed by the
Commission.
Fines and Charges.
General Control of
the Commission.
ELECTRICITY REFORM [1998 : Hr. Act 10
109
PART X
ADVISORY COMMITTEE, CONSUMER CONSULTATION, ETC.
32. (1) The Commission shall constitute a committee to be known as
the Commission Advisory Committee, in consultation with the State Government
which shall consist of such number of persons being not less than 9 and not more
than 15 as the Commission may appoint after consultation with such representatives
or bodies representatives of the following interests as the Commission thinks fit,
that is to say, holders of supply licences in the State, holders of transmission licences
in the State; generating companies operating in the State, commerce, industry,
transport, agriculture, labor employed in the electricity supply industry and
consumers of electricity.
(2) The Chairman and members of the Commission shall be ex-
officio Chairman and members of the Commission Advisory Committee.
(3) The Commission Advisory Committee shall meet at least once
in every 3 months.
(4) The functions of the Commission Advisory Committee shall
be as follows:—
(a) to advise the Commission on major questions of policy
relating to the electricity industry in the State; and
(b) to advise the Commission on any matters which the
Commission may put before it, including matters relating
to the quality, continuity and extent of service provided
by licensees and compliance by licensees with the
conditions and requirements of their licences.
33. (1) The Commission may, after consultation with (a) holders of
supply licences, (b) other persons or bodies appearing to the Commission to be
representative of persons and categories of person likely to be affected and (c) the
Commission Advisory Committee, frame regulations prescribing:—
(a) the circumstances in which such licensees are to inform
customers of their rights;
(b) the standards of performance in relation to any duty
arising under sub-section (a) above or otherwise in
connection with the electricity supply to the consumer;
and
(c) the circumstances in which licensees are to be exempted
from any requirements of the regulations or this section
and may make different provision for different licensees.
(2) Nothing in this or other provisions of this Act shall in any way
prejudice or affect the rights and privileges of the Consumers under other laws
including but not limited to the Consumer Protection Act, 1986.
Commission
Advisory
Committee.
Consumer
Protection;
Standards of
Performance.
ELECTRICITY REFORM1998 : Hr. Act 10]
110
34. (1) The Commission may, after consultation with the licensees,
the Commission Advisory Committee, and with persons or bodies appearing to it
to be representative of persons likely to be affected, from time to time:—
(a) determine such standards of overall performance in
connection with the provision of electricity supply services
and in connection with the promotion of the efficient use
of electricity by consumers as, in its opinion, is economic
and ought to be achieved by such licensees; and
(b) arrange for the publication, in such form and in such
manner as it considers appropriate, of the standards so
determined.
(2) Different standards may be determined under this section for
different licensees.
35. (1) The Commission shall from time to time collect information
with respect to—
(a) the fines or penalties levied on licensees under this Act;
(b) the levels of overall performance achieved by such
licensees in connection with the transmission and provision
of electricity supply services; and
(c) the levels of performance achieved by such licensees in
connection with the promotion of the efficient use of
electricity by consumers.
(2) On or before such date in each year as may be specified in a
direction given by the Commission, each licensee shall furnish to the Commission
the following information:—
(a) with respect to each standard prescribed the number of
cases in which a penalty was levied and the aggregate
amount of value of those penalties; and
(b) with respect to each standard determined such information
with respect to the level of performance achieved by the
licensee as may be so specified.
(3) The Commission shall, at least once in every year, arrange for
the publication, in such form and in such manner as it considers appropriate, of
such of the information collected by or furnished to it under this section as may
appear to the Commission to be so required.
36. (1) Subject to the provisions of this Act, no confidential information
with respect to any particular business which:—
(a) has been obtained by the Commission under or by virtue
of any of the provisions of this Act; and
Electricity Supply;
Overall
Performance
Standards.
Information with
respect to Levels
of Performance.
Restriction on
Disclosure of
Information.
ELECTRICITY REFORM [1998 : Hr. Act 10
111
(b) relates to the affairs of any individual or to any particular
business;
shall during the lifetime of that individual or for so long as that particular business
continues to be carried on, be disclosed by the Commission without the consent of
that individual or the person for the time being carrying on that business.
(2) The restriction contained in sub-section (1) above shall not apply
to any disclosure of information which is made:—
(a) for the purpose of facilitating the carrying out by the State
Government of any of its functions under a statute;
(b) for the purpose of facilitating the carrying out by the
Central Government of any of its duties or functions under
this Act or any Central legislation;
(c) for the purpose of facilitating the carrying out by the
Accountant General, Haryana of his duties and functions
under this Act;
(d) for the purpose of enabling or assisting any competent
person to carry out its functions under the enactment
relating to insolvency;
(e) in connection with the investigation of any
criminal offence or for the purposes of any criminal
proceedings; or
(f) for the purpose of any civil proceedings brought under or
by virtue of this Act or any other State or Central legislation
to which the information is directly relevant.
(3) The restrictions contained in sub-section (1) above do not apply
to the disclosure of any information which is otherwise in the public domain.
PART XI
ARBITRATION AND APPEALS
37. (1) Notwithstanding anything contained in the Arbitration and
Conciliation Act, 1996 (No. 26 of 1996), any dispute arising between licensees or
in respect of matters provided under section 33 shall be referred to the Commission.
The Commission may proceed to act as arbitrator or nominate arbitrator(s) to
adjudicate and settle such dispute. The practice or procedure to be followed in
connection with any such adjudication and settlement shall be such as may be
prescribed by regulations.
(2) Where the award is made by the arbitrator appointed by the
Commission it shall be filed before the Commission and the Commission shall be
entitled to pass appropriate orders on the award including, orders to:—
(a) confirm and enforce the award;
Arbitration by the
Commission.
ELECTRICITY REFORM1998 : Hr. Act 10]
112
(b) set aside or modify the award; or
(c) remit the award for reconsideration by the arbitrator.
(3) The award given by the Commission under sub-section (1) or
the order passed by the Commission under sub-section (2) shall be a decision or
order of the Commission and shall be appealable as provided in this Act.
(4) An award made or an order passed by the Commission under
sub-section (2) shall be enforceable as if it were a decree of the Civil Court.
38. Notwithstanding the provisions of section 36(2), Indian Electricity
Act, 1910 in the absence of any express provision to the contrary in the Indian
Electricity Act, 1910 or the Electricity (Supply) Act, 1948 or any rule made
thereunder, an appeal shall lie from the decision of an Electrical Inspector (other
than an Inspector of the Central Government or the Central Electricity Authority)
to the Commission or to an arbitrator to be appointed by the Commission in terms
of section 37.
39. A person aggrieved by any decision or order of the Commission
passed under this Act may file an appeal to the High Court of Punjab and Haryana
within 90 days from the date of communication of the decision or order of the
Commission to him, on questions of law arising out of such order:
Provided that the High Court may, if it is satisfied that the appellant
was prevented by sufficient cause from filing the appeal within the said period,
allow it to be filed within a further period not exceeding 60 days.
PART XII
OFFENCES AND PENALTIES
40. Whoever in contravention of the provisions of this Act or the
regulations framed under this Act or of the provisions of the Indian Electricity
Act, 1910 or the Electricity (Supply) Act, 1948 or the rules framed under the said
Acts, engages in the business of transmission or supply or use of energy, shall be
punishable with imprisonment which may extend to 2 years or with penalty by
way of fine which may extend to Rs. 1,00,000 (one lakh) or both and a further
penalty which may extend to Rs. 6,000 (six thousand) for each day after the first
during which the offence continues.
41. If any licensee or other person refuses or fails without reasonable
excuse to comply with or give effect to, any direction, order or requirement made
under any of the provisions of this Act he shall be punishable with imprisonment
which may extend to 2 years or with penalty by way of fine which may extend to
Rs. 1,00,000 (one lakh) or both and a further penalty which may extend to
Rs. 4,000 (four thousand) for each day after the first during which the offence
continues.
Appeals from
decisions of
Electrical
Inspector.
Appeals against
the orders of the
Commission.
Penalty for
contravention of
section 14.
Penalties for
contravention of
other provisions.
ELECTRICITY REFORM [1998 : Hr. Act 10
113
42. (1) Where an offence under this Act has been committed by a
company, every person who, at the time the offence was committed, was incharge
of, and was responsible to the company for, the conduct of the business of the
company, as well as the company, shall be deemed to be guilty of the offence and
shall be liable to be proceeded against and published accordingly:
Provided that nothing contained in this sub-section shall render any
such person liable to any punishment if he proves that the offence was committed
without his knowledge or that he had exercised all due diligence to prevent the
commission of such offence.
(2) Notwithstanding anything contained in sub-section (1), wherein
an offence under this Act, has been committed by a company and it is proved that
the offence has been committed with the consent or connivance of, or is attributable
to any neglect on the part of, any director, manager, secretary or other officer of
the company, such director, manager, secretary or other officer shall also be deemed
to be guilty of that offence and shall be liable to be proceeded against and punished
accordingly.
For the purposes of this section—
(a) “company” means a body corporate and includes a firm or other
association of individuals; and
(b) “director” in relation to a firm, means a partner in the firm.
43. The Commission may for reasons to be recorded in writing either
before or after the institution of proceedings compound any offence relating to
contravention of any order made by it.
44. (1) No Court shall take cognizance of any offence punishable under
this Act except upon a complaint in writing made by an officer of the Commission,
generally or specially authorised in this behalf by the Commission and no Court
other than that of a Metropolitan Magistrate or a Judicial Magistrate of First
Class or a Court superior thereto shall try any such offence.
(2) Notwithstanding anything contained in the Code of Criminal
Procedure, 1973 (2 of 1974) the Court may, if he sees reason so to do, dispense
with the personal attendance of the officer of the Commission filing the complaint.
45. The proceedings and actions under this Act against a person
contravening the provisions of the Act or orders passed by the Commission shall
be in addition to and without prejudice to actions that may be initiated under other
Acts including and in particular under the Indian Electricity Act, 1910 and the
Electricity (Supply) Act, 1948.
Offences by
Companies.
Power to
compound
offences.
Cognizance of
offences.
Penalties and
Proceedings not to
prejudice other
actions.
ELECTRICITY REFORM1998 : Hr. Act 10]
114
PART XIII
MISCELLANEOUS
46. The Commission shall be entitled to recover all sums due to it under
this Act, whether by way of licence, fees or fines and charges, in accordance with
the provisions of the Haryana Govt. Electrical Undertaking (Dues Recovery) Act,
1970, as if any such sum were a public demand as defined in that Act and hand
over the amount due to the person or authority concerned.
47. The Commission or Court imposing the fine and charges under this
Act may direct that the whole or any part thereof shall be applied in or towards
payment of the costs of the proceedings.
48. The licensee, Generating Companies and others on whom the fines,
charges, penalties etc. are imposed under this Act shall not, directly or indirectly,
pass the same to the consumers in the form of tariff or charges payable.
49. No suit or legal proceedings shall lie against the Commission or the
Chairman or other members of the Commission or the staff or representatives of
the Commission in respect of anything which is in good faith done or intended to
be done under this Act or any rule or regulations or order made thereunder.
50. No order or proposal made under this Act or rules or regulations
framed under the Act shall be appealable except as provided in the Act and no
Civil Court including under the Arbitration & Conciliation Act, 1996 shall have
jurisdiction in respect of any matter which the Commission or the Appellate
Authority under the Act is empowered by or under this Act.
51. (1) If any difficulty arises in giving effect to the provisions of this
Act or the rules, regulations, scheme or orders made thereunder, the State
Government may by order published in the Official Gazette, make such provision,
not inconsistent with the provisions of this Act as appear to it to be necessary or
expedient for removing the difficulty.
(2) Every order made under this section shall, as soon as may be
after it is made, be laid before the State Legislature.
52. All proceedings before the Commission shall be deemed to be judicial
proceeding within the meaning of sections 193, 219 and 228 of the Indian Penal
Code (45 of 1860) and the Commission shall be deemed to be a Civil Court for the
purposes of section 195 and Chapter XXVI of the Code of Criminal Procedure,
1973 (Act 2 of 1974.)
53. The Chairman, other members and officers and other employees of
the Commission appointed for carrying out the objects and purposes of this Act
shall be deemed to be public servants within the meaning of section 21 of the
Indian Penal Code.
Recovery of Fees,
Fines and Charges.
Application of fine
and charges.
No part of the
fines or penalties
imposed to be
passed on.
Protection of
action taken in
good faith.
Bar of Jurisdiction.
Power to remove
difficulties.
Proceedings before
the Commission to
be judicial
proceedings.
Members and staff
of Commission to
be public servants.
ELECTRICITY REFORM [1998 : Hr. Act 10
115
54. (1) The Commission may, make regulation by notification in the
Official Gazette, for the proper performance of its functions under this Act.
(2) In particular, and without prejudice to the generality of the
foregoing provisions and matters specifically provided for in this Act, such
regulations may provide for all or any of the following matters, namely:—
(a) the administration of the affairs of the Commission
including the exercise of its administrative, quasi-judicial
and judicial powers including arbitration and procedure,
summoning and holding of the meeting of the
Commission, the times and places at which such meetings
shall be held, the conduct of the business thereof;
(b) the duties of the Secretary, officers and employees of the
Commission, their salaries, allowances and conditions of
service;
(c) determination of the functions to be assigned to licensees
and others involved in the generation, purchase,
transmission, distribution and supply, the manner in which
such functions shall be discharged and the procedure and
code to be adopted in regard to power system and electric
supply lines;
(d) the procedure for licensing of transmission and supply,
the conditions for the grant of licenses and particulars,
details and documents to be made available by the persons
applying for the licence, the standard and general
conditions subject to which the licence shall be granted,
the exemption from grant of licence, revocation and
amendment and effect thereof, of the licence, and all
matters related to the above;
(e) the duties, powers, rights and obligations of the licensee;
(f) the particulars to be furnished, the collection of
information, details, particulars, documents, accounts,
books, etc. from or of the persons involved in the
generation, transmission, distribution, supply and use of
electricity, the form and manner in which the same are to
be furnished and enforcing and compelling the production
of the same;
(g) method and manner of determination of licensee’s
revenues, tariff fixation, the matters to be considered in
such determination and fixation;
(h) the constitution of the Commission Advisory Committee;
Power to make
regulations.
ELECTRICITY REFORM1998 : Hr. Act 10]
116
(i) the determination of the standard of performance of the
persons involved in the generation, transmission,
distribution and supply of electricity in the State;
(j) the amount of fines and penalties to be imposed for
violation of provisions of this Act including the method
and manner of imposition of fines and penalties and
collection of the same;
(k) to prescribe the form and manner in which the accounts of
the Commission shall be maintained; and
(l) to regulate the properties, assets and interest in the
properties used for or in connection with the electricity
industry in the state.
55. (1) The State Government may, by notification make rules to carry
out its functions under the provisions of the Act.
(2) In particular, and without prejudice to the generality of the
foregoing power and matters specifically provided for in this Act, such rule may
provide for all or any of the following matters, namely—
(a) the procedure to be adopted by the selection committee
for discharge of functions under the Act;
(b) the preparation and implementation of the transfer scheme,
the transfer of assets, liabilities and personnel to
Generating Companies, licensees and others in the State;
and
(c) the financing, funding giving of guarantee etc., to the
persons involved in the generation, transmission,
distribution and supply of electricity in the State.
(3) Every rule made under this section shall be laid, as soon as may
be after it is made, before the State Legislature while it is in session, for a total
period of thirty days and if before the expiry of the above period the State
Legislature agrees in making any modification in the rule, the rule shall thereafter
have the effect only in such modified form, however that any such modification
shall be without prejudice to the validity of anything previously done under that
rule.
PART XIV
EFFECT ON EXISTING CENTRAL LEGISLATION
56. (1) Except as provided in section 57 of this Act, the provisions of
this Act, notwithstanding that the same are inconsistent with or contrary to the
provisions of the Indian Electricity Act, 1910, or the Electricity (Supply) Act,
1948 shall prevail in the manner and to the extent provided in sub-section (3).
(2) Subject to sub-section (1) in respect of all matters in the Indian
Electricity Act, 1910 and the Electricity (Supply) Act, 1948 with which Haryana
Power to make
Rules.
Effect of the Act
on the Indian
Electricity Act,
1910 and the
Electricity
(Supply) Act,
1948.
ELECTRICITY REFORM [1998 : Hr. Act 10
117
State Electricity Board has been concerned or dealing with, upon the constitution
of the Commission the functions of the Board shall be discharged by the
Commission and the Transco, provided however:—
(a) the State Government shall be entitled to issue all policy
directives and undertake overall planning and coordination
as specified in section 12 of this Act and to this extent the
powers and functions of the Haryana State Electricity
Board as per the provisions of the Indian Electricity Act,
1910 and the Electricity (Supply) Act, 1948 or rules
thereunder shall vest in the State Government and the State
Government shall coordinate and deal with the Central
Government and the Central Electricity Authority;
(b) in respect of such matters which the Commission directs
in terms of a general or special order, or in the regulations
or in the licence as the case may be the Generating
Company or Companies, the licensees or other body
corporate as may be designated by the Commission shall
discharge the functions of the Board under the Indian
Electricity Act, 1910 and the Electricity (Supply) Act, 1948
to the extent directed by the Commission or specified in
licences.
(3) Subject to sub-section (1) and (2) of this section, upon the
establishment of the Commission the provisions of the Indian Electricity Act,
1910 and the Electricity (Supply) Act, 1948 shall, in so far as the State is concerned,
shall be read subject to the following modifications and reservations:—
INDIAN ELECTRICITY ACT, 1910
(i) All references to State Electricity Board in the Indian Electricity Act,
1910 in so far as the State is concerned shall be read as reference to
the Haryana Electricity Regulatory Commission or Transco or other
licensees or wherever it relates to general policy matters of the State
Government.
(ii) In respect of matters provided in sections 3 to 11, 28, 36(2), 49-A,
and 50 & 51 of the Indian Electricity Act, 1910, to the extent this Act
has made specific provisions, the provisions of the Indian Electricity
Act, 1910 shall not apply in the State.
(iii) The provisions of all other sections of the Indian Electricity Act,
1910 shall apply except that:—
(a) the term “licence” “licensee” “license holder” shall have the
meaning as defined under this Act and the licences shall be
construed as having been issued under this Act;
ELECTRICITY REFORM1998 : Hr. Act 10]
118
(b) the reference to the sections of the Indian Electricity Act, 1910
and the Electricity (Supply) Act, 1948 in the provisions of the
Indian Electricity Act, 1910 shall be taken as reference to the
corresponding provisions of this Act to the extent modified by
the said Act.
(c) the reference to arbitration in these provisions except where it
is by the Central Electricity Authority shall be taken as reference
to the proceedings under section 37 of this Act and the arbitration
procedure prescribed under the Indian Electricity Act, 1910 shall
not apply.
(iv) The Schedules to the Indian Electricity Act, 1910 shall be applicable
only with reference to the provisions in this Act wherein the
applications of the Schedules are specified and not otherwise.
ELECTRICITY SUPPLY ACT, 1948
(v) All references to State Electricity Board in the Electricity (Supply)
Act, 1948 in so far as the State of Haryana is concerned shall be read
as reference to the Haryana Electricity Regulatory Commission or
Transco or other licensees or where it relates to general policy matters,
the State Government.
(vi) In respect of matters provided in sections 5 to 18, 19, 20, 23 to 27, 37,
40 to 45, 46 to 54, 56 to 69, 72 and 75 to 83 of the Electricity
(Supply) Act, 1948, to the extent this Act has made specific provisions,
the provisions of the Electricity (Supply) Act, 1948 shall not apply
in the State.
(vii) The provisions of all other sections of the Electricity (Supply) Act,
1948 shall apply except that:—
(a) the term “licence” “licensee” “license holder” shall have the
meaning as defined under this Act and the licences shall be
construed as having been issued under this Act;
(b) the reference to the sections of the Indian Electricity Act, 1910
and the Electricity (Supply) Act, 1948 in the provisions of the
Electricity (Supply) Act, 1948 shall be taken as reference to the
corresponding provisions of this Act to the extent modified by
this Act.
(c) the reference to arbitration in these provisions except where it
is by Central Electricity Authority shall be taken as reference to
the proceedings under section 37 of this Act and the arbitration
procedure prescribed under the Electricity (Supply) Act, 1948
shall not apply.
ELECTRICITY REFORM [1998 : Hr. Act 10
119
(viii) The provisions of sections 72, 73 of the Electricity (Supply) Act,
1948 shall be restricted to Generating Companies and reference to
the State Electricity Board in these sections shall stand deleted.
(ix) The Schedules to the Electricity (Supply) Act, 1948 shall be
applicable only with reference to the provisions in this Act wherein
the applications of the Schedules are specified and not otherwise.
57. (1) Notwithstanding anything contained in this Act, the powers
rights and functions of Regional Electricity Authority, the Central Electricity
Authority, the Central Government and authorities, other than the State Electricity
Board and the State Government under the Indian Electricity Act, 1910 or the
Electricity (Supply) Act, 1948 or rules framed thereunder shall remain unaffected
and shall continue to be in force.
(2) Nothing contained in this Act will apply to the Power Grid
Corporation, BBMB or other bodies or licensees in relation to the inter-State
transmission of the electricity or generating companies owned or controlled by
Central Government or undertaking owned by the Central Government.
Schedule
THE HARYANA ELECTRICITY REGULATORY COMMISSION
PART-I
The Commission’s Finance, Accounts and Audit
I. (1) (In December of) each year the Commission shall submit to the
State Government a statement of its estimated expenditure for the ensuing financial
year.
(2) The State Government shall as soon as possible after the receipt
of the said statement cause it to be laid on the table of the State Legislature.
(3) The Commission may at any time during the year in respect of
which a statement under sub-paragraph (1) has been submitted, submit to the
State Government a supplementary statement, and all the provisions of this section
shall apply to such statement as they apply to the statement under the said sub-
section.
II. (1) The Commission shall cause proper accounts and other records
in relation thereto to be kept, including a proper system of internal check and
shall prepare an annual statement of accounts, in such form as may be prescribed
by regulations made by the Commission in consultation with the Accountant
General, Haryana.
(2) The accounts of the Commission shall be audited by the
Accountant General, Haryana or by such person as he may authorise on his behalf
and any expenditure incurred by him in connection with such audit shall be
payable by the State Government.
Savings.
Annual Financial
Statement.
Accounts and
Audit.
ELECTRICITY REFORM1998 : Hr. Act 10]
120
(3) The Accountant General Haryana or any person authorised by
him in connection with the audit of the accounts of the Commission shall have the
right to demand the production of books, accounts, connected vouchers and other
documents and papers of the Commission.
(4) The account of the Commission as certified by the Accountant
General Haryana or any other person authorised by him on his behalf, together
with the audit report thereon shall be forwarded to the State Government within
six months of the close of the year to which the accounts audit report relates and
the Commission shall cause the said accounts of the Commission to be published
and make available copies thereof on sale at a reasonable price. The audit report
shall contain full details of any discrepancies or irregularities in the accounts of
the Commission. At the same time, the Commission shall publish an annual
statement of its activities in relation to the functions carried out by it under this
Act during the year to which the said accounts relate and make available copies
thereof on sale at a reasonable price.
(5) The State Government shall cause the accounts of the
Commission, together with the audit report thereof forwarded to it under sub-
paragraph (4) to be laid annually before the State Legislature.
PART II
GENERAL
III. (1) As an expense of the Commission there shall be paid to the
Chairman and the Members of the Commission such remuneration, and such
traveling and other expenses and allowances, as the State Government may
determine, provided that the remuneration determined by the State Government
for the Chairman and Members of the Commission shall at no time be inferior to
the remuneration paid to Chairman and Members of Haryana Public Service
Commission respectively.
(2) The State Government may cause to be paid, as an expense of
the Commission, to or in respect of any person holding the office of Chairman or
a Member of the Commission such pension, allowance or gratuity or such
contributions or payments towards provision of such a pension, allowance or
gratuity.
IV. The Commission shall have an official seal for the authentication of
documents required for the purposes of its functions.
V. Anything authorised or required by or under this Act or any other
enactment to be done by the Commission may be done by any member of the staff
of the Commission who is authorised generally or specially in that behalf by the
Commission.
Remuneration, etc.
Official Seal.
Performance of
Functions.
ELECTRICITY REFORM [1998 : Hr. Act 10